Handover date

When is the Verdana handover date?

Updated 11 October 2026 Verdana

Short answer

Reportage's Verdana phases 3 to 10 are registered with the Dubai Land Department (DLD) to complete on 30 September 2028 (Verdana 3, 4, 5), 31 December 2028 (Verdana 6, 7, 8) and 31 March 2029 (Verdana 9, 10). The most advanced, Verdana 6, was 0.14% complete at its DLD inspection on 22 July 2026. Earlier Verdana phases passed their registered dates before completion, so the dates above are not guaranteed.

Registered completion dates (DLD)

30 Sep 2028 to 31 Mar 2029

Verdana 3 to 10, DLD register via Continental Club

Latest construction progress

0.14%

Verdana 6, DLD inspection, 22 Jul 2026

Portal dates

Q2 2028 to Q3 2029

Dubainary and JRE, accessed Oct 2026

First Verdana phase

96.14% vs 31 Dec 2025 date

DLD inspection, 3 Jun 2026, via dxbpropy

Verdana handover date: the latest position

The newer Verdana phases by Reportage Properties in Dubai Investments Park are registered to complete between 30 September 2028 and 31 March 2029. The Dubai Land Department (DLD) register files them as Verdana 3 to Verdana 10, each with its own date. Full project details are on the Verdana page.

Work has barely begun. The highest recorded figure is 0.14% at Verdana 6 on 22 July 2026, and three phases were still at 0% at their last inspection. Earlier Verdana phases passed their registered dates, which is the main reason to treat the 2028 and 2029 dates with caution.

Verdana handover date by phase

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
Verdana 3 (131 units) 0.11% (28 Jul 2026) 30 Sep 2028 Q3 2029 for “Verdana III” (JRE)
Verdana 4 (306 units) 0.13% (22 Jul 2026) 30 Sep 2028 Q3 2028 (developer, via Continental Club); Q2 2028 (Dubainary)
Verdana 5 (271 units) 0.1% (28 Jul 2026) 30 Sep 2028 Q4 2028 (Dubainary, OffPlanIndex)
Verdana 6 (280 units) 0.14% (22 Jul 2026) 31 Dec 2028 Q4 2028 (developer, via Continental Club); Q2 2029 (JRE)
Verdana 7 (293 units) 0.12% (22 Jul 2026) 31 Dec 2028 Not published
Verdana 8 (154 units) 0% (8 Dec 2025) 31 Dec 2028 Q2 2029 (Dubainary)
Verdana 9 (204 units) 0% (13 May 2026) 31 Mar 2029 Q1 2029 (developer, via Continental Club); Q2 2029 (JRE)
Verdana 10 (135 units) 0% (10 Dec 2025) 31 Mar 2029 Q4 2028 (Dubainary)

The register also holds separate “Verdana Residence” registrations. Verdana Residence 9 and 10 share the 31 March 2029 date of Verdana 9 and 10 (Continental Club). Portal phase names such as “Verdana III” may refer to these apartment registrations, which explains some of the gaps in the last column.

How the Verdana handover date has changed

Date What was stated Source
31 Dec 2025 Registered completion date of the first Verdana phase DLD register via dxbpropy
30 Apr 2026 Registered completion date of Verdana Residence 2 DLD register via Dubai Handover
11 May 2026 Verdana Residence 2 inspected at 20% DLD register via Dubai Handover
3 Jun 2026 First Verdana phase inspected at 96.14% DLD register via dxbpropy
22 to 28 Jul 2026 Verdana 3 to 7 inspected at 0.1% to 0.14% DLD register via Continental Club
4 Oct 2026 Verdana 3 to 10 still registered for Sep 2028 to Mar 2029 DLD register via Continental Club

The first phase climbed from 43.25% in March 2025 to 68.11% in October 2025 and 96.14% in June 2026 (dxbpropy). It was still short of 100% more than five months after its registered date, a useful guide to how Verdana dates have behaved.

What the Verdana handover date means for payments

Most Verdana plans put a large share on handover. A common Verdana III plan is 10% on booking, 1% a month during construction (43%) and 47% on handover (JRE). Verdana V options run from 70% on handover with 20% down to 35% on handover with 30% down (OffPlanIndex). Monthly instalments run until handover, so a later completion date means more months of payments before the final balance falls due.

What to check before relying on the Verdana date

  1. The DLD project number on the Oqood, to confirm whether the unit is in a “Verdana” or a “Verdana Residence” registration.
  2. The completion date and grace period in the SPA, since the first phase and Verdana Residence 2 both ran past their registered dates.
  3. Whether monthly instalments stop at the registered date or continue until actual handover.
  4. Inspections through 2027. A phase due in September 2028 needs steady progress from late 2026 to meet its date.

Questions buyers also ask

When will Verdana be completed?

The DLD register gives 30 September 2028 for Verdana 3, 4 and 5, 31 December 2028 for Verdana 6, 7 and 8, and 31 March 2029 for Verdana 9 and 10 (Continental Club, registry updated 4 October 2026).

When will Verdana 6 be ready?

Verdana 6 has a registered completion date of 31 December 2028. It was 0.14% complete at the DLD inspection on 22 July 2026, with construction registered to start on 31 December 2025.

Has the Verdana handover date been delayed?

For the first phase, yes. It had a registered completion date of 31 December 2025 and was 96.14% complete on 3 June 2026. Verdana Residence 2 passed its 30 April 2026 date at 20%. The registered dates for Verdana 3 to 10 have not changed in the register as of October 2026.

Is Verdana finished?

No phase of Verdana 3 to 10 is finished; construction had barely started by July 2026. The first Verdana phase was in its final stage in mid 2026.

Sources

  1. Dubainary, Verdana phases (opens in a new tab)dubainary.com · accessed 11 Oct 2026
  2. JRE Dubai, Verdana III (opens in a new tab)jre.ae · accessed 11 Oct 2026
  3. OffPlanIndex, Verdana V payment plans (opens in a new tab)offplanindex.ae · accessed 11 Oct 2026