When is the Veona by Gutti handover date?
Short answer
Veona by Gutti has a registered completion date of 31 December 2027, and Gutti Development states Q4 2027. The latest DLD inspection, on 18 June 2026, recorded the building 11.08% complete. Data Habibi records an original promise of Q2 2027, so the date has already moved back about six months, and an early buyer's SPA may show a different date from the register.
Registered completion date (DLD)
31 Dec 2027
DLD register via Continental Club
Latest construction progress
11.08%
DLD inspection, 18 Jun 2026
Developer's stated date
Q4 2027
Gutti Development, reviewed 3 Sep 2026
Original promise
Q2 2027
Data Habibi, six month postponement
Veona by Gutti handover date: the latest position
Veona by Gutti is registered with the Dubai Land Department (DLD) for completion on 31 December 2027. Gutti Development’s official project page, reviewed on 3 September 2026, gives an anticipated completion of Q4 2027, and Property Finder lists 31 December 2027. Full project details are on the Veona by Gutti page.
The building was 11.08% complete at the DLD inspection on 18 June 2026. Data Habibi records that the developer first promised Q2 2027, so the current date is already about six months later than the original one.
Veona by Gutti handover date by building
Veona is a single low-rise building in Wadi Al Safa 5, Dubailand Residence Complex, registered as DLD project 4001 with 89 units: 87 homes and two shops. The escrow account is held at Mashreq Bank (Mitchells).
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Veona by Gutti (G+P+5+R) | 11.08% (18 Jun 2026) | 31 Dec 2027 | Q4 2027 (Gutti); 31 Dec 2027 (Property Finder); Q2 2027 originally (Data Habibi) |
How the Veona by Gutti handover date has changed
| Date | What happened | Source |
|---|---|---|
| Jul 2025 | Construction begins, by Data Habibi’s record; original promise Q2 2027 | Data Habibi |
| 1 Nov 2025 | Sales start; registered construction start | Property Finder; DLD register via Mitchells |
| 10 Mar 2026 | First registered sale | Mitchells |
| 18 Jun 2026 | DLD inspection, 11.08%; registered completion 31 Dec 2027 | DLD register via Continental Club |
| 3 Sep 2026 | Gutti’s official page states Q4 2027 | Gutti Development |
| 11 Oct 2026 | Property Finder lists 31 December 2027 | Property Finder |
The six month change came between the original Q2 2027 promise and the Q4 2027 date now used by Gutti and the register. Gutti has not published an explanation. Property Finder, Gutti’s own page and the DLD register now all point to the end of 2027, so the current sources agree.
What the Veona by Gutti handover date means for payments
Gutti’s current plan puts 60% of the price on completion: 20% on booking, 20% in four 5% instalments during construction and 60% at handover. On the cheapest studio, at AED 647,967, that is about AED 389,000 at handover (ezre). Earlier listings show 50% on handover (Property Finder) or 60% after a 10% deposit (OffPlanIndex). Under every version, at least half the price waits for the handover date.
What to check before relying on the Veona by Gutti date
- The completion date in the SPA. Buyers who booked early may have a Q2 2027 date, which the register no longer shows.
- The share due on handover in the SPA, since 50% and 60% versions have both been advertised.
- The next DLD inspection. A figure well above 11.08% would support the December 2027 date.
Questions buyers also ask
When will Veona by Gutti be completed?
The DLD register gives 31 December 2027. Gutti Development states Q4 2027, and Property Finder lists 31 December 2027 as expected completion.
Has the Veona by Gutti handover date been delayed?
Yes, compared with the first promise. Data Habibi records an original developer promise of Q2 2027 and a current target of Q4 2027, a six month postponement. The registered date of 31 December 2027 has not moved since then.
How far along is Veona by Gutti?
11.08% at the DLD inspection on 18 June 2026 (DLD project register via Continental Club and Mitchells). No later inspection had been published by 28 September 2026.
Is Veona by Gutti on track for December 2027?
It is possible on the figures so far. The building is low-rise, ground plus podium plus five floors, and reached 11.08% about seven months after the registered start on 1 November 2025.