Handover date

When is the Vela Viento handover date?

Updated 1 October 2026 Vela Viento

Short answer

Omniyat said on 7 May 2025, when it appointed ACC Group as main contractor, that Vela Viento is scheduled for handover in Q3 2027; the Dubai Land Department register gives an earlier registered completion date of 13 May 2027. The DLD inspection on 18 May 2026 recorded 21.81% complete. With 40% of the price due at handover, the gap between the May 2027 register date and Omniyat's Q3 2027 target decides when the largest payment falls.

Registered completion date (DLD)

13 May 2027

DLD project 2885, via Continental Club

Latest construction progress

21.81%

DLD inspection, 18 May 2026

Developer's stated date

Q3 2027

Omniyat, ACC Group appointment, 7 May 2025

Portal estimate

Q3 2027

Property Finder, accessed 28 Sep 2026

Vela Viento handover date: the latest position

Omniyat said on 7 May 2025, when it appointed ACC Group as main contractor for Vela and Vela Viento in Marasi Bay, that Vela Viento is scheduled for handover in Q3 2027. The Dubai Land Department register gives an earlier registered completion date of 13 May 2027, and Property Finder lists Q3 2027. Prices, sizes and the payment plan are on the Vela Viento page.

The DLD inspection on 18 May 2026 recorded 21.81% complete. No newer inspection had been added to the register by 25 September 2026.

Vela Viento handover date by building

Vela Viento is a single tower, registered as DLD project 2885 with 86 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Vela Viento, 86 units (DLD 2885) 21.81%, 18 May 2026 13 May 2027 Q3 2027 (Omniyat, May 2025); Q3 2027 (Property Finder)

Progress rose by 3.78 points between the DLD inspections of 16 February and 18 May 2026, from 18.03% to 21.81%. Omniyat’s latest site update reported structural slabs up to Level 6, core walls up to Level 8, blockwork up to Level 2, facade fabrication under way and about 700 workers on site each day.

How the Vela Viento handover date has changed

Date What happened Source
9 Jan 2024 Registered construction start; registered completion 13 May 2027 DLD register, via Continental Club
25 Jan 2024 Omniyat launches Vela Viento; no completion date in the release Omniyat via Zawya
7 May 2025 ACC Group appointed main contractor; handover scheduled Q3 2027 Omniyat via Middle East Construction News
16 Jan 2026 Raft slab and ground floor slabs complete; Omniyat says projects on track against completion dates Omniyat
16 Feb 2026 DLD inspection: 18.03% DLD register, via Continental Club
18 May 2026 DLD inspection: 21.81% DLD register
Sep 2026 Register unchanged: 13 May 2027 DLD register, via Continental Club

Omniyat’s Q3 2027 date has not changed since May 2025. The register date of 13 May 2027 is one to four months earlier.

What the Vela Viento handover date means for payments

Property Finder lists 5% at launch, 55% during construction and 40% at handover. At Vela Viento’s prices, the handover share is the largest single payment: AED 11.2 million on a 2 bedroom apartment listed from AED 28 million, and AED 24.8 million on a 4 bedroom apartment listed from AED 62 million. Whether that falls in May 2027 or later in Q3 2027 depends on when Omniyat issues the completion notice.

What to check before relying on the Vela Viento date

  1. The completion date in the SPA. It may follow the 13 May 2027 registered date or Omniyat’s Q3 2027 target, and the grace period counts from whichever the SPA states.
  2. A newer DLD inspection for project 2885. The latest figure on the register is from May 2026.
  3. That the unit is in Vela Viento and not Vela. The two towers share a contractor and a brand but have different dates, Q3 2027 and Q2 2027.
  4. The unit count on the Oqood registration. The register holds 86 units, while Omniyat has published 92 and 95, so the unit reference on the Oqood record is the one that counts.

Questions buyers also ask

Is Vela Viento finished?

No. The DLD inspection on 18 May 2026 recorded 21.81% complete. Omniyat's latest site update reported structural slabs up to Level 6 and core walls up to Level 8.

What is the Vela Viento completion date?

The DLD register gives 13 May 2027. Omniyat's own date, given when it appointed ACC Group in May 2025, is Q3 2027, and Property Finder lists Q3 2027.

When will Vela Viento be ready?

Omniyat's target is Q3 2027. In January 2026 it said all its projects were on track to deliver against their completion dates, and it has not announced a change for Vela Viento.

Has the Vela Viento handover date been delayed?

Omniyat has not announced a delay. Its Q3 2027 target is a few months later than the 13 May 2027 registered completion date, and the tower was 21.81% built a year before that registered date.

Does Vela hand over at the same time as Vela Viento?

No. Omniyat gave Q2 2027 for VELA, the sister tower, and Q3 2027 for Vela Viento (7 May 2025). ACC Group is main contractor for both.