Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Tonino Lamborghini Residences handover date?

Updated 11 October 2026 Tonino Lamborghini Residences

Short answer

Tonino Lamborghini Residences has a registered completion date of 31 December 2026, and most listings give a Q1 2027 handover. The DLD inspection on 21 September 2026 recorded 60% complete. The project started in October 2017 with a 2021 completion date, stalled near 26% for four years, and was only re-dated in the register in August 2026.

Registered completion date (DLD)

31 Dec 2026

DLD project register via Continental Club

Latest construction progress

60%

DLD inspection, 21 Sep 2026

Listed handover

Q1 2027

Continental Club; JRE; Driven Properties, accessed 11 Oct 2026

Original registered date

31 Dec 2021

Held in the register until 27 Aug 2026 (Dubai Handover)

Tonino Lamborghini Residences handover date: the latest position

The DLD project register gives Tonino Lamborghini Residences a registered completion date of 31 December 2026, and most listings show a Q1 2027 handover. Prices, sizes and the payment plan are on the Tonino Lamborghini Residences page.

The latest DLD inspection, on 21 September 2026, recorded 60% complete, a jump of 6.1 points in 11 days after the 10 September inspection. To reach 100% by the end of December, work would need to move far faster than at any time since 2017. Dubai Handover’s projection from the recent pace points to about 2 September 2027.

Tonino Lamborghini Residences handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Tonino Lamborghini Residences, four buildings (DLD project 1941, 553 units) 60%, 21 Sep 2026 31 Dec 2026 Q1 2027 (Continental Club, JRE, Driven Properties); 31 Dec 2026 (Property Finder)

The four buildings, two of six floors and two of 11 floors on a shared podium, sit under one registration, so the 60% figure covers all of them. Tonino Lamborghini Phase 2 in Nad Al Sheba 2 is a separate registration with its own date.

How the Tonino Lamborghini Residences handover date has changed

Date What happened Source
1 Oct 2017 Bookings open; construction start registered; completion registered for 31 Dec 2021 Property Finder; DLD register
17 Apr 2019 DLD inspection records 25.6% DLD register
17 Aug 2020 26.2% DLD register
7 Jun 2024 27.2% after almost four years with little change DLD register
18 Jun 2025 50.1% DLD register
17 Jan 2026 Gulf Land releases the final phase, construction above 50% DRE Homes
24 Mar 2026 51.9% DLD register
28 Aug 2026 Registered completion changes from 31 Dec 2021 to 31 Dec 2026 Dubai Handover
21 Sep 2026 60% DLD register
Oct 2026 Listings show Q1 2027 Continental Club; JRE

Against the original 2021 date, the project is about five years late. Between August 2020 and June 2024 the recorded progress rose by only one point. Since Gulf Land restarted work, progress has risen by about 33 points in just over two years.

What the Tonino Lamborghini Residences handover date means for payments

Broker listings show 30% of the price due on handover under a 20/50/30 plan (JRE, July 2026), or 40% on completion under a 60/40 plan (Offplans.com). On a 1 bedroom at the recent registered price of AED 2,522,070, 30% is about AED 757,000 and 40% about AED 1,009,000. A move from December 2026 to 2027 shifts that payment, and any mortgage drawdown, into the next year.

What to check before relying on the Tonino Lamborghini Residences date

  1. The completion date written in the SPA. Buyers from 2017 to 2019 signed when the register showed 2021; newer buyers may have 2026 or 2027.
  2. That the unit is in project 1941, not Tonino Lamborghini Phase 2.
  3. The next DLD inspection. Finishing by 31 December 2026 would need the last 40 points in just over three months.

Questions buyers also ask

When will Tonino Lamborghini Residences be completed?

The DLD register gives 31 December 2026. Most listings give Q1 2027, and Dubai Handover's projection from the recent pace points to about September 2027.

Is Tonino Lamborghini Residences finished?

No. The DLD inspection on 21 September 2026 recorded 60% complete across the four buildings.

Has the Tonino Lamborghini Residences handover date been delayed?

Yes. Construction started in October 2017 with a registered completion date of 31 December 2021 and a Propsearch estimate of January 2022. Progress stalled between 2019 and 2024. The register moved the date to 31 December 2026 in late August 2026.

Do all four Tonino Lamborghini buildings hand over together?

The register holds one project, number 1941, with one completion date for all 553 units. No separate building dates have been published.

Sources

Request a Unit Review