Handover date

When is The Wilds handover date?

Updated 11 October 2026 The Wilds

Short answer

The Wilds villas are registered with the Dubai Land Department (DLD) to complete on 31 January 2029 (The Wilds 1), 28 February 2029 (The Wilds 2) and 31 May 2029 (The Wilds 3); Aldar gave 2029 at launch and broker pages show Q2 2029. At the DLD inspection on 14 September 2026 the three phases were 7.48%, 5.74% and 3.1% complete. The date for any one villa depends on which of the three registrations it belongs to.

Registered completion dates (DLD)

31 Jan to 31 May 2029

The Wilds 1, 2 and 3, DLD register via Continental Club

Latest construction progress

7.48% / 5.74% / 3.1%

DLD inspection, 14 Sep 2026

Developer's stated date

2029

Aldar via The National, 19 Feb 2025; Q2 2029 on broker pages

Date change since launch

None recorded

2029 at launch; registered dates still in 2029 in Oct 2026

The Wilds handover date: the latest position

The Wilds villas have three registered completion dates in the Dubai Land Department (DLD) register: 31 January 2029 for The Wilds 1, 28 February 2029 for The Wilds 2 and 31 May 2029 for The Wilds 3. Aldar gave 2029 when it launched the community in February 2025. Full project details are on The Wilds page.

Construction is at an early stage. The DLD inspection on 14 September 2026 found the three phases between 3.1% and 7.48% complete, with between 28 and 32 months left to their registered dates.

The Wilds handover date by phase

The register files the villas under Aurora SPV 2, the Aldar and Dubai Holding joint venture company, as three projects in Majan (Wadi Al Safa 3).

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
The Wilds 1 (267 units, project 3600) 7.48% (14 Sep 2026) 31 Jan 2029 Q1 2029 (developer, via Continental Club); Jan 2029 (Property Finder)
The Wilds 2 (266 units, project 3606) 5.74% (14 Sep 2026) 28 Feb 2029 Q1 2029 (developer, via Continental Club); Feb 2029 (Property Finder)
The Wilds 3 (408 units, project 3607) 3.1% (14 Sep 2026) 31 May 2029 Q2 2029 (developer, via Continental Club)

Progress between the June and September 2026 inspections was 3.66 points at The Wilds 1, 3.02 points at The Wilds 2 and 0.69 points at The Wilds 3 (Continental Club). The apartment phase, The Wilds Residences, is a separate registration with a completion date of 30 June 2030.

How The Wilds handover date has changed

Date What was stated Source
19 Feb 2025 Launch announced; delivery expected in 2029 Aldar via The National
28 Feb 2025 Registered construction start, The Wilds 1 DLD register
5 Mar 2025 734 villas sold out for AED 5 billion Aldar
28 Apr 2025 Registered construction start, The Wilds 2 DLD register
28 Jul 2025 Registered construction start, The Wilds 3 DLD register
16 Jun 2026 DLD inspection: 3.82%, 2.72%, 2.41% DLD register via Continental Club
14 Sep 2026 DLD inspection: 7.48%, 5.74%, 3.1% DLD register via Continental Club
Oct 2026 Registered dates still 31 Jan, 28 Feb and 31 May 2029 DLD register via Continental Club

No change to the 2029 target has been published since launch. Broker pages give Q2 2029 for the whole community, which is later than the registered dates for The Wilds 1 and 2.

What The Wilds handover date means for payments

The villas were sold on a 65/35 plan: 10% on booking, 55% during construction and 35% on handover (Property Finder; The Wilds Dubai FAQ). GRAF’s schedule for first phase villas places the construction instalments on fixed dates, with the last one in June 2028. That means 65% is paid before handover whether or not building work keeps pace. On a villa bought at the AED 5.1 million launch price, the handover payment is about AED 1.79 million, due when the phase is completed.

What to check before relying on The Wilds date

  1. The registration number on the SPA or Oqood. Project 3600, 3606 or 3607 decides which of the three dates applies.
  2. The grace period in the SPA, since the registered dates fall between January and May 2029 while marketing material says Q2 2029.
  3. The pace at The Wilds 3. It added 0.69 points between June and September 2026, the slowest of the three.
  4. The DLD project status enquiry for the latest inspection before paying the next dated instalment.

Questions buyers also ask

When will The Wilds be completed?

The DLD register gives 31 January 2029 for The Wilds 1, 28 February 2029 for The Wilds 2 and 31 May 2029 for The Wilds 3 (Continental Club, registry updated October 2026).

How far along is construction at The Wilds?

At the DLD inspection on 14 September 2026, The Wilds 1 was 7.48% complete, The Wilds 2 5.74% and The Wilds 3 3.1%. In June 2026 the figures were 3.82%, 2.72% and 2.41%.

Has The Wilds handover date been delayed?

No change has been recorded. Aldar said 2029 at launch in February 2025, and the registered completion dates were still in early to mid 2029 in October 2026. Portal dates vary between January, April and Q2 2029.

Is The Wilds Residences handed over at the same time as the villas?

No. The Wilds Residences apartments have a separate registered completion date of 30 June 2030, more than a year after the villa phases.

Sources