When is The Oasis handover date?
Short answer
The first The Oasis handover date is December 2027, for the Palmiera cluster, the completion date in Emaar's payment plan brief; the other clusters follow between June 2028 and early 2030, with registered completion dates of 31 October 2028 for Palmiera 3, 31 January 2029 for Lavita and 28 February 2030 for Mareva 2. The Dubai Land Department (DLD) inspection of 20 July 2026 recorded Palmiera 81.72% complete, up from 72.56% in March. Nothing at The Oasis has been handed over, and Propsearch still shows an older November 2026 estimate for Palmiera.
Registered completion dates (DLD)
Oct 2028 to Feb 2030
Palmiera 3, Lavita, Tierra, Mareva 2. None on file for Palmiera. Via Mitchells and Continental Club, Sep 2026
Latest construction progress, Palmiera
81.72%
DLD inspection, 20 Jul 2026
Developer's stated date, Palmiera
Dec 2027
Emaar payment plan brief, via Mitchells, accessed 1 Oct 2026
Earlier portal estimate, Palmiera
Nov 2026
Propsearch, updated 29 Jul 2026
The Oasis handover date: the latest position
The first homes at The Oasis are due in December 2027, when Palmiera, the first cluster, is scheduled for completion in Emaar’s payment plan brief. The DLD inspection of 20 July 2026 recorded Palmiera 81.72% complete, up 9.16 points since 27 March 2026. Prices and sales across the community are covered on The Oasis page.
Every later cluster has its own date. Emaar gives June 2028 for Mirage, October 2028 for Palmiera 3 and December 2028 for Lavita, and the DLD register holds dates of 30 June 2029 for Address Villas Tierra and 28 February 2030 for Mareva 2. Nothing has been handed over. Sources disagree on Palmiera: Propsearch still shows November 2026, and an Emaar agent’s June 2026 summary gave Q4 2026 to Q1 2027, both earlier than Emaar’s own brief.
The Oasis handover date by cluster
Each cluster is a separate DLD project with its own inspection and, in some cases, its own registered completion date. Mitchells’ copy of the register shows no completion date on file for Palmiera, Palmiera 2, Mirage or Mareva.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Palmiera, 265 homes (project 2732) | 81.72%, 20 Jul 2026 | None on file | Dec 2027 (Emaar brief); Nov 2026 (Propsearch, 29 Jul 2026) |
| Palmiera 2, 56 villas (3031) | 77.11%, 3 Aug 2026 | None on file | Q2 2028 (Data Habibi) |
| Palmiera 3, 59 villas (3221) | 72.62%, 9 Jun 2026 | 31 Oct 2028 | Oct 2028 (Emaar brief) |
| Mirage, 204 villas (3025) | 46.94%, 29 Jun 2026 | None on file | Jun 2028 (Emaar brief) |
| Lavita, 43 mansions (3266) | 20.13%, 2 Jun 2026 | 31 Jan 2029 | Dec 2028 (Emaar brief) |
| Palmiera Collective (4209) | About 1% (Data Habibi) | Not republished | Q1 2029 (Data Habibi) |
| Address Villas Tierra (3580) | 6.81%, 21 Jul 2026 | 30 Jun 2029 | Q2 2029 (Data Habibi) |
| Palace Villas Ostra, 526 villas (3581) | 6.54%, 20 Jul 2026 | Not republished | Q3 2029 (Continental Club); 30 Sep 2029 (Property Finder) |
| Mareva, 311 homes (4269) | 2.05%, 16 Jun 2026 | None on file | Q1 2030 (Continental Club; Data Habibi) |
| Mareva 2 (4270) | 1.32%, 6 Jul 2026 | 28 Feb 2030 | Q1 2030 (Data Habibi) |
Continental Club dates the Mirage reading of 46.94% to 29 July 2026 rather than 29 June. Lavita’s register entry counts 49 homes against Emaar’s 43 mansions.
How The Oasis handover date has changed
Emaar has not announced a change to any cluster date. The differences are between sources rather than over time.
| Date | What happened | Source |
|---|---|---|
| Jun 2023 | Emaar launched The Oasis, about 7,000 homes planned. | Real Estate Club Dubai |
| Jul to Aug 2023 | Palmiera launched from AED 8.5 million. Emaar’s payment schedule runs from booking in August 2023 to completion in December 2027. Construction start registered 14 August 2023. | Emaar brief, via Mitchells; DLD register |
| Apr to Oct 2024 | Mirage (June 2028), Palmiera 2, Palmiera 3 (October 2028) and Lavita (December 2028) followed. | Emaar briefs; DLD register |
| 2025 | Tierra (registered for 30 June 2029) and Ostra (Q3 2029) started; Mareva and Mareva 2 were first inspected in December 2025. | DLD register, via Continental Club; Property Finder |
| 18 Jun 2026 | Agent summary of DLD data put Palmiera’s first handovers at Q4 2026 to Q1 2027. | Oasis Emaar |
| 20 Jul 2026 | Palmiera 81.72% complete. | DLD register |
| 29 Jul 2026 | Propsearch still showed November 2026 for Palmiera. | Propsearch |
What The Oasis handover date means for payments
Emaar’s plans for the early clusters leave between 10% and 20% to completion. Palmiera’s plan collects 85% during construction, with the last 15% due at 100% construction in December 2027, which is AED 1.275 million on the AED 8.5 million starting price. Mirage leaves 10% to June 2028, Palmiera 3 leaves 20% to October 2028 and Lavita leaves 20% to December 2028. Data Habibi lists a 10/80/10 plan for Palmiera 2. Most instalments are tied to construction milestones, so the timing of payments follows DLD progress as well as the completion date.
What to check before relying on The Oasis date
- Which cluster your villa is in. Dates run from December 2027 for Palmiera to February 2030 for Mareva 2.
- The completion date in your SPA for Palmiera, Palmiera 2, Mirage or Mareva, since the register shows no completion date on file for these clusters.
- For Lavita, whether your SPA uses December 2028 or the registered 31 January 2029.
- The DLD progress for your cluster’s project number, through DLD’s project status enquiry service, since milestone instalments follow it.
Questions buyers also ask
What is The Oasis completion date?
It depends on the cluster. Emaar gives December 2027 for Palmiera, June 2028 for Mirage, October 2028 for Palmiera 3 and December 2028 for Lavita in its payment plan briefs. Registered completion dates on the DLD register run from 31 October 2028 (Palmiera 3) to 28 February 2030 (Mareva 2).
Is The Oasis by Emaar finished?
No. No cluster has been handed over. The most advanced, Palmiera, was 81.72% complete at the DLD inspection of 20 July 2026, and Palmiera 2 was 77.11% complete on 3 August 2026.
When will Palmiera at The Oasis be ready?
Emaar's payment plan brief gives December 2027, with the final 15% due on completion. Propsearch still shows an older estimate of November 2026, and an Emaar agent's June 2026 summary gave Q4 2026 to Q1 2027. The DLD register holds no completion date for Palmiera.
Has The Oasis handover date been delayed?
Emaar has not announced a delay. Palmiera's December 2027 date in Emaar's brief matches the payment schedule that began with bookings in August 2023. The only difference is between sources: Propsearch's November 2026 estimate is earlier than Emaar's date, and Lavita's registered date of 31 January 2029 is a month after Emaar's December 2028.
When will Mareva at The Oasis be handed over?
Mareva and Mareva 2 are due in Q1 2030, with a registered completion date of 28 February 2030 for Mareva 2. At DLD inspections in June and July 2026, Mareva was 2.05% complete and Mareva 2 was 1.32% complete (Continental Club).