Handover date

When is The Community Sports Arena handover date?

Updated 11 October 2026 The Community Sports Arena

Short answer

The Community Sports Arena has a registered completion date of 31 October 2027 at the Dubai Land Department (DLD), matching the Q4 2027 completion AQUA Properties announced at launch in December 2024. The only DLD inspection on the register, on 31 October 2024, recorded 22.42% complete. No newer DLD reading had been published by October 2026, so current progress is not known from the register.

Registered completion date (DLD)

31 Oct 2027

DLD project 3362, via Continental Club

Latest construction progress

22.42%

DLD inspection, 31 Oct 2024

Developer's stated date

Q4 2027

AQUA Properties, 6 Dec 2024

Portal estimate

Sep 2027

Propsearch, updated 5 Apr 2026

The Community Sports Arena handover date: the latest position

The Community Sports Arena, AQUA Properties’ 396 apartment tower in Dubai Sports City, has a registered completion date of 31 October 2027 at the Dubai Land Department (DLD). AQUA announced a Q4 2027 completion at launch, and the two dates agree. Full project details are on The Community Sports Arena page.

The only DLD inspection on the register, dated 31 October 2024, recorded 22.42% complete (DLD project register via Continental Club, inspection 31 October 2024). That was a month after the registered construction start. No later DLD figure had been published by October 2026, a year before the registered date.

The Community Sports Arena handover date by building

The project is one tower, filed with DLD as a single project.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
The Community - Sports Arena (DLD project 3362, 396 units) 22.42%, 31 Oct 2024 31 Oct 2027 Q4 2027 (AQUA); Sep 2027 (Propsearch); Dec 2027 (JRE Dubai)

How The Community Sports Arena handover date has changed

Date Event Source
1 Oct 2024 Construction start on the DLD register; completion date 31 Oct 2027 Data Dubai (DLD)
31 Oct 2024 DLD inspection: 22.42% DLD via Continental Club
29 Nov 2024 Project registered with DLD Data Dubai (DLD)
6 Dec 2024 Launch: 396 apartments, AED 477 million, completion by Q4 2027 AQUA Properties
29 Apr 2025 First of 102 registered sales in the period to 9 Sep 2026 Mitchells (DLD)
Apr 2026 Propsearch estimate: September 2027 Propsearch
Q2 2026 Latest site photo update on AQUA’s page, no percentage AQUA
23 Sep 2026 Register: under construction, date unchanged Mitchells

The registered date and the developer’s quarter have stayed the same since launch. The gap is in the progress record: two years have passed without a published DLD reading.

What The Community Sports Arena handover date means for payments

The plan is 76/24: 5% on booking, 19% during construction, 52% on handover at 100% completion, and 24% over the 24 months after handover (Continental Club). The 52% handover payment and the start of the post-handover instalments both depend on the completion date. If handover falls in late 2027, the last post-handover payment would fall in late 2029.

What to check before relying on The Community Sports Arena date

  1. A dated progress figure. The register’s 22.42% is from October 2024, so a newer DLD inspection or a dated developer certificate shows how far the tower has come.
  2. The completion date and grace period in the SPA, compared with the registered 31 October 2027.
  3. The post-handover schedule. 24% is spread over two years after completion, so the handover date also sets when those payments end.

Questions buyers also ask

Is The Community Sports Arena finished?

No. The register listed it as under construction on 23 September 2026 (Mitchells). The last published DLD reading was 22.42% on 31 October 2024.

What is The Community Sports Arena completion date?

31 October 2027, the completion date on file at DLD for project 3362, registered as The Community - Sports Arena.

Has The Community Sports Arena handover date been delayed?

Not on paper. AQUA gave Q4 2027 at launch in December 2024 and the registered date is 31 October 2027. Without a DLD reading since October 2024, the register does not show whether construction is on pace.

Why has the DLD progress figure not changed since 2024?

DLD inspections are irregular, and the register published for this project holds only the 31 October 2024 inspection. An unchanged figure does not mean work stopped; AQUA's project page shows quarterly site photo updates up to Q2 2026.