When is the Terra Tower handover date?
Short answer
Dugasta now publishes a Q2 2028 handover for Terra Tower, while the DLD project register still holds a completion date of 30 April 2027. The latest DLD inspection, on 8 July 2026, recorded 7.43% complete. At the pace recorded since October 2025, about 0.58 points a month, even the 2028 date needs construction to speed up sharply.
Registered completion date (DLD)
30 Apr 2027
DLD project register via Continental Club, accessed 11 Oct 2026
Latest construction progress
7.43%
DLD inspection, 8 Jul 2026
Developer's stated date
Q2 2028
Dugasta, via EZRE, accessed Oct 2026
Earliest advertised date
Q2 2026
Earlier listings, via JRE and OffPlanIndex
Terra Tower handover date: the latest position
Dugasta’s published handover for Terra Tower is now Q2 2028, a year after the 30 April 2027 completion date held on the DLD register. At the latest DLD inspection, on 8 July 2026, the tower was 7.43% complete. Prices and plans are on the Terra Tower page.
The registered date cannot be met: about 92.6 points of work remained with less than ten months to go. Q2 2028 leaves about two years, which would need several times the pace recorded since October 2025.
Terra Tower handover date by building
Terra Tower is a single building of three basements, ground, 12 floors and roof.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Terra Tower (366 units, project 3278) | 7.43%, 8 Jul 2026 | 30 Apr 2027 | Q2 2028 (Dugasta, via EZRE); 30 Jun 2028 (DubaiHaus); April 2027 (Property Finder) |
DLD figures are from Continental Club, Dubai Data and Mitchell’s, which republish the DLD project register.
How the Terra Tower handover date has changed
| Date | What happened | Source |
|---|---|---|
| Earlier listings | A Q2 2026 handover is advertised. | JRE; OffPlanIndex |
| 12 Sep 2024 | First DLD inspection at 0%. | DLD register, via Dubai Data |
| 10 Oct 2024 | Registered with the DLD, completion date 30 April 2027. | DLD register, via Dubai Data |
| 1 Nov 2024 | Bookings open from AED 633,763; construction start on the register. | Property Finder; DLD register |
| 31 Oct 2025 | 2.7% complete. | DLD inspection, via Dubai Data |
| 2 Mar 2026 | 6.8% complete. | DLD inspection, via Dubai Data |
| 8 Jul 2026 | 7.43% complete. | DLD inspection, via Continental Club |
| Sep to Oct 2026 | Dugasta’s published handover is Q2 2028; some agents still show Q2 2027. | EZRE; Luxury Located, 4 Sep 2026 |
Tanami Properties also carried a June 2027 date at one stage. Portal pages copy different versions, so dates from Q2 2026 to Q2 2028 can all still be found online.
What the Terra Tower handover date means for payments
How much a delay matters depends on the plan. On the 50/50 plan, 50% is due on handover, so a later handover pushes back the largest payment. On the 3 and 5 year plans, only 1% is due on handover and 49% follows over 36 or 60 months, so those instalments start later too. On the 10 year plan, 60% is paid over 10 years after handover (EZRE). The 40% to 50% paid before handover goes into the project’s escrow account with Mashreq Bank.
What to check before relying on the Terra Tower date
- The handover date written in the SPA, since contracts signed at different times may carry Q2 2026, April 2027 or a later date.
- The grace period the SPA allows after that date.
- A DLD inspection newer than 8 July 2026, through DLD’s project status enquiry for project 3278.
Questions buyers also ask
When will Terra Tower be ready?
Dugasta publishes Q2 2028, and DubaiHaus lists 30 June 2028. The DLD register still holds 30 April 2027. The tower was 7.43% complete on 8 July 2026.
What is the Terra Tower completion date?
30 April 2027 in the DLD project register, where it is DLD project 3278, Terra Tower, registered on 10 October 2024 by Dugasta Properties Development.
Has the Terra Tower handover date been delayed?
Yes. Earlier listings gave Q2 2026, later material June 2027 (Tanami Properties), and Dugasta now publishes Q2 2028. The registered date of 30 April 2027 has not been updated in the sources checked.
How far along is Terra Tower construction?
7.43% at the DLD inspection on 8 July 2026, up from 6.8% on 2 March 2026 and 2.7% on 31 October 2025 (Dubai Data).