
When is the Taormina Village handover date?
Short answer
Taormina Village phase 1 has a registered completion date of 20 December 2027, matching the Q4 2027 handover Reportage has marketed since December 2023. The DLD inspection on 3 June 2026 recorded phase 1 at 20.4% complete. Phase 2 is a separate DLD project registered for 6 July 2029, so the date depends on which phase a home is in.
Registered completion date, phase 1 (DLD)
20 Dec 2027
Taormina Village 1, DLD project 3108, via Continental Club
Latest construction progress, phase 1
20.4%
DLD inspection, 3 Jun 2026
Developer's stated date, phase 1
Q4 2027
Reportage listings since Dec 2023
Registered completion date, phase 2 (DLD)
6 Jul 2029
Taormina Village 2, DLD project 4121; 0% on 5 Nov 2025
Taormina Village handover date: the latest position
Taormina Village, Reportage’s community of about 838 townhouses and villas in Wadi Al Safa 3, Dubailand, hands over in two phases. Phase 1 has a registered completion date of 20 December 2027 at the Dubai Land Department (DLD), and Reportage markets Q4 2027. Full project details are on the Taormina Village page.
The DLD inspection on 3 June 2026 recorded phase 1 at 20.4% complete (DLD project register via Continental Club, inspection 3 June 2026). Phase 2 is a separate project with a registered completion date of 6 July 2029. It was at 0% when DLD last inspected it, on 5 November 2025.
Taormina Village handover date by building
| Phase | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Taormina Village 1 (DLD project 3108, 530 homes) | 20.4%, 3 Jun 2026 | 20 Dec 2027 | Q4 2027 (Reportage, Property Finder) |
| Taormina Village 2 (DLD project 4121, 309 homes) | 0%, 5 Nov 2025 | 6 Jul 2029 | Q2 2028 on some broker plans (Takween Aldar); Q3 2029 (Grand Reve) |
DLD files each phase as a single project with one completion date. No cluster dates within a phase have been published.
How the Taormina Village handover date has changed
| Date | Event | Source |
|---|---|---|
| 23 Dec 2023 | Launch listings: from AED 2.86 million, 30/70 plan, handover Q4 2027 | Dubai Homes Online |
| 31 Oct 2024 | First sale registered in phase 1 | Mitchells (DLD) |
| 21 Dec 2024 | Phase 1 construction start on the DLD register; completion date 20 Dec 2027 | Mitchells (DLD) |
| 5 Nov 2025 | Phase 2 inspected by DLD at 0% | DLD via Continental Club |
| 3 Jun 2026 | Phase 1 inspected at 20.4% | DLD via Continental Club |
| 30 Jun 2026 | Phase 2 construction start on the register; completion date 6 Jul 2029 | Mitchells (DLD) |
| Oct 2026 | Q4 2027 still marketed for phase 1 | Property Finder; ezre |
The phase 1 date has not moved since launch. The register allows three years from the recorded start to completion. At 20.4% after about 18 months, the larger share of the work falls in the last 18 months. Phase 2 was filed later, with a three year programme of its own.
What the Taormina Village handover date means for payments
The handover payment is large. The launch plan put 70% of the price on handover (Property Finder). The plans Reportage publishes in 2026 leave between 58% and 70% for completion, with no instalments after handover (ezre; Takween Aldar). Some phase 2 payment schedules give “Q2 2028” as the handover milestone, earlier than the 6 July 2029 date on the register. If completion moves, the handover payment moves with it.
What to check before relying on the Taormina Village date
- The phase named in the SPA. Phase 1 and phase 2 have registered dates about 18 months apart.
- The handover milestone in the payment schedule. Some phase 2 plans name Q2 2028, while DLD holds 6 July 2029.
- The grace period. With 20.4% recorded in June 2026, the SPA’s grace period after 20 December 2027 matters.
- The registered developer. Phase 2 is filed by M H L Real Estate Development, a branch of Millennium Holding, not by Reportage Prime Properties.
Questions buyers also ask
Is Taormina Village finished?
No. Phase 1 was 20.4% complete at the DLD inspection on 3 June 2026, and phase 2 was at 0% on 5 November 2025. Both were listed as under construction on 4 October 2026 (Mitchells).
What is the Taormina Village completion date?
20 December 2027 for phase 1 and 6 July 2029 for phase 2, as filed with DLD (DLD project register via Continental Club).
When will Taormina Village 2 be ready?
The DLD register gives 6 July 2029. Broker listings disagree, with some showing Q2 2028 and others Q3 2029. The registered start of construction is 30 June 2026.
Has the Taormina Village handover date been delayed?
Not for phase 1. Q4 2027 was the date at launch in December 2023 and the registered date is 20 December 2027. Phase 2 was launched later with its own, later date.
