When is the Sports View Residence 2 handover date?
Short answer
Sports View Residence 2 has a registered completion date of 10 November 2029 in the DLD project register, and the developer gives Q4 2029. The DLD inspection on 12 August 2026 recorded 13.35% complete. The recent pace is faster than the date needs, and Continental Club projects 100% in November 2028, but buyers are bound by the date in their SPA, not the projection.
Registered completion date (DLD)
10 Nov 2029
DLD project register via Continental Club, accessed 11 Oct 2026
Latest construction progress
13.35%
DLD inspection, 12 Aug 2026
Developer's stated date
Q4 2029
Continental Club; Bayut listings, Jul 2026
Projected completion at recent pace
Nov 2028
Continental Club projection from DLD inspections
Sports View Residence 2 handover date: the latest position
Sports View Residence 2 has a registered completion date of 10 November 2029 in the DLD project register, and the developer’s stated handover is Q4 2029. Prices, sizes and the payment plan are on the Sports View Residence 2 page.
The DLD inspection on 12 August 2026 recorded 13.35% complete. That leaves more than three years to the registered date for a ground plus six floor building, a long schedule for its size. At the pace of mid 2026, Continental Club projects completion in November 2028.
Sports View Residence 2 handover date by building
Sports View Residence 2 is one building in International City Phase 2 (Warsan 4). The developer’s earlier building, Sports View Residence, is a separate project with its own dates.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Sports View Residence 2 (DLD 3836, 128 units) | 13.35%, 12 Aug 2026 | 10 Nov 2029 | Q4 2029 (developer via Continental Club; Bayut listings) |
| Sports View Residence (first building) | Not published | Not published | Q4 2025 (Westgate Dubai, 28 Jan 2026); Q4 2026 (Binayah, 11 Jul 2026) |
How the Sports View Residence 2 handover date has changed
| Date | What happened | Source |
|---|---|---|
| 16 Jun 2025 | First inspection, 0% | DLD register via Continental Club |
| 1 Aug 2025 or 10 Nov 2025 | Construction start (the register shows both dates) | DLD register via Continental Club |
| 2 Feb 2026 | First unit sale registered with DLD | DLD transactions via Continental Club |
| 5 May 2026 | Inspection records 3.01% | DLD register via Continental Club |
| 23 Jul 2026 | Listing gives Q4 2029, with Q1 2027 in its highlights | Bayut |
| 12 Aug 2026 | Inspection records 13.35% | DLD register via Continental Club |
| 8 Oct 2026 | Registered completion date still 10 Nov 2029 | DLD register via Continental Club |
The registered date has not moved. The only conflicting figure is the Q1 2027 mention in one agent listing, which no other source repeats.
What the Sports View Residence 2 handover date means for payments
Agent listings advertise a 60/40 plan, which points to 40% falling due on or around handover (Bayut, 23 July 2026). On a studio at the AED 571,054 DLD median, that would be about AED 228,000. The developer has not published the full schedule on the main portals, so whether the 60% is spread by date or by construction stage depends on the SPA. If construction runs ahead of the 2029 date, stage-linked instalments would also come sooner.
What to check before relying on the Sports View Residence 2 date
- The completion date in the SPA, compared with the registered 10 November 2029 and the Q1 2027 figure seen in one listing.
- Whether instalments are tied to construction stages. At the mid 2026 pace, stage payments could arrive well before 2029.
- Progress on the first Sports View Residence building, whose marketed date has moved between Q4 2025 and Q4 2026.
Questions buyers also ask
When will Sports View Residence 2 be ready?
The registered completion date is 10 November 2029 (DLD project register via Continental Club), and the developer gives Q4 2029. The building was 13.35% complete on 12 August 2026.
What is the Sports View Residence 2 completion date?
10 November 2029 in the DLD project register, where it is listed as Sports View Residence 2 By Al Helal Al Zahaby, DLD project 3836.
Could Sports View Residence 2 be handed over early?
Possibly. Progress rose from 3.01% to 13.35% between May and August 2026, and Continental Club projects 100% in November 2028 at that pace. An early handover depends on the developer obtaining the completion certificate sooner; the SPA date stays the contractual one.
Is the Q1 2027 handover date for Sports View Residence 2 correct?
No register source supports it. One Bayut listing from 23 July 2026 mentions Q1 2027 in its highlights, but the same listing, the developer's stated date and the DLD register all give Q4 2029 or 10 November 2029.