When is the Sky Line by Peace Homes handover date?
Short answer
The registered completion date for Sky Line by Peace Homes is 30 May 2030 on the Dubai Land Department (DLD) project register, with the developer's date recorded as Q2 2030. The only DLD inspection on record, on 14 October 2025, showed 0% progress, before construction started in 2026. Launch reports in November 2025 gave Q4 2028, so marketing and the register are about 18 months apart.
Registered completion date (DLD)
30 May 2030
DLD register via Continental Club, updated 8 Oct 2026
Latest construction progress
0%
DLD inspection, 14 Oct 2025 (only one on record)
Developer's stated date
Q2 2030
Developer supplied, via Continental Club
Date at launch
Q4 2028
Alnair, 25 Nov 2025; Metropolitan, Oct 2026
Sky Line by Peace Homes handover date: the latest position
The Dubai Land Department (DLD) project register gives Sky Line by Peace Homes, the Peace Homes Development tower in Dubailand Residence Complex (DLRC), a registered completion date of 30 May 2030. Continental Club records the developer’s date as Q2 2030. Full project details are on the Sky Line by Peace Homes page.
Launch reports gave an earlier date. Alnair’s report on 25 November 2025 said Q4 2028, and Metropolitan’s project page still says Q4 2028. The only DLD inspection on record, on 14 October 2025, showed 0% progress, and it took place before the registered construction start.
Sky Line by Peace Homes handover date by building
Sky Line is one tower, DLD project number 4125, with 565 units including offices and shops. Its escrow account is held at Abu Dhabi Commercial Bank.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Sky Line by Peace Homes (565 units) | 0% (14 Oct 2025) | 30 May 2030 | Q2 2030 (developer, via Continental Club); Q4 2028 (Alnair, Nov 2025; Metropolitan) |
How the Sky Line by Peace Homes handover date has changed
- 14 October 2025: first DLD inspection, at 0%.
- 25 November 2025: Alnair reports the presale, with expressions of interest from AED 40,000, studios from AED 750,000 and a Q4 2028 handover.
- 1 March 2026: construction start on the DLD register (1 May 2026 in another field on the same page).
- 2 September 2026: Continental Club’s 2030 handover list shows 30 May 2030.
- October 2026: the register still shows 30 May 2030 (Continental Club, updated 8 October 2026), while Metropolitan keeps Q4 2028.
The register date sits about 18 months after the launch date. The registered date is the one on DLD’s project records.
What the Sky Line by Peace Homes handover date means for payments
Alnair reported two plans at launch: 20/80 with 1% monthly instalments and a post-handover element, and 50/50. Metropolitan describes the 20/80 plan as 20% during construction and 80% at handover, while Continental Club lists 20% down and 80% during construction. Under Metropolitan’s version, 80% of the price is tied to completion, so a move from Q4 2028 to May 2030 pushes most of the payment back by about 18 months. Under Continental Club’s version, payments run through construction instead.
What to check before relying on the Sky Line by Peace Homes date
- Which completion date the SPA states. Launch material in November 2025 referred to Q4 2028, while the register says 30 May 2030.
- How the 80% is scheduled. The three published versions of the 20/80 plan put it at different stages.
- A first DLD inspection after construction began. No progress figure after 14 October 2025 is on record.
- The mix of uses in the tower. Offices and shops sit below 24 residential floors and are part of the same completion date.
Questions buyers also ask
What is the Sky Line by Peace Homes completion date?
The DLD register gives 30 May 2030 (Continental Club, registry updated 8 October 2026). Launch reports and Metropolitan give Q4 2028.
Has construction started at Sky Line by Peace Homes?
The DLD register gives a construction start of 1 March 2026, with 1 May 2026 shown elsewhere on the same page. The only DLD inspection on record, on 14 October 2025, showed 0%, and no later figure has been published.
Has the Sky Line by Peace Homes handover date been delayed?
Launch material in November 2025 gave Q4 2028. The register now shows 30 May 2030 and the developer's recorded date is Q2 2030, about 18 months later. Some broker pages still carry Q4 2028.
When will Skyline by Peace Homes in DLRC be ready?
Skyline, written Sky Line on the DLD register, has a registered completion date of 30 May 2030.