Handover date

When is the Sierra by Iman handover date?

Updated 11 October 2026 Sierra by Iman

Short answer

Sierra by Iman has a registered completion date of 30 June 2029 in the Dubai Land Department (DLD) register, matching the Q2 2029 that Iman Developers gave at the groundbreaking. The DLD inspection on 10 August 2026 recorded 3.74% complete, up from 0.20% in January. Property Finder shows an earlier January 2029, which neither the developer nor the register supports.

Registered completion date (DLD)

30 Jun 2029

DLD project register via Continental Club, inspection 10 Aug 2026

Latest construction progress

3.74%

DLD inspection, 10 Aug 2026

Developer's stated date

Q2 2029

Iman Developers, groundbreaking announcement, accessed 11 Oct 2026

Portal estimate

January 2029

Property Finder, accessed 11 Oct 2026

Sierra by Iman handover date: the latest position

Sierra by Iman is registered for completion on 30 June 2029, the date the Dubai Land Department (DLD) holds for project 3835. Iman Developers gave Q2 2029 when it announced the groundbreaking, so the developer and the register agree. More on prices and sizes is on the Sierra by Iman page.

The DLD inspection on 10 August 2026 recorded 3.74% complete. Property Finder and Binayah show January 2029, about five months earlier than the developer and the register.

Sierra by Iman handover date by building

Sierra is one tower registered as a single DLD project.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Sierra by Iman (598 units, B+G+41) 3.74%, 10 Aug 2026 30 Jun 2029 Q2 2029 (Iman); Jan 2029 (Property Finder)

The 598 units are 593 apartments and 5 shops (Iman Developers, 9 September 2025).

How the Sierra by Iman handover date has changed

The developer’s date has held at mid-2029. The gap is between portals and the register.

Date What happened Source
Jun 2025 Construction start recorded by Property Finder (15 June) and Data Habibi. Property Finder gives completion as 1 January 2029. Property Finder; Data Habibi
9 Sep 2025 Iman launches Sierra, AED 900 million and 598 units, from AED 799,000. Iman Developers; Gulf News
1 Nov 2025 Construction start on the DLD register. Registered completion date 30 June 2029. DLD register via Continental Club
14 Jan 2026 DLD inspection records 0.20%. DLD register via Continental Club
10 Aug 2026 DLD inspection records 3.74%. DLD register via Continental Club

Iman’s groundbreaking announcement, which carries no date on its website, gives completion in Q2 2029. Progress rose 3.54 points in the seven months to August 2026 (Continental Club, DLD data).

What the Sierra by Iman handover date means for payments

The 60/40 plan takes 20% on booking, 40% in four instalments during construction and 40% on handover (Continental Club). On the median studio price of AED 862,257, the handover payment is about AED 344,900; on the median 2 bedroom at AED 1,818,725, it is about AED 727,500.

Nothing is listed as payable after handover, so the date mainly sets when the final 40% falls due.

What to check before relying on the Sierra by Iman date

  1. The completion date written in the SPA, and whether it follows the DLD’s 30 June 2029 or a January 2029 date shown on a portal.
  2. Whether the four construction instalments are tied to dates or to progress, given 3.74% complete in August 2026.
  3. The grace period in the SPA, measured from the contract date rather than the DLD date.
  4. The next DLD inspection for project 3835, which should show the structure rising if mid-2029 is to hold.

Questions buyers also ask

Is Sierra by Iman under construction?

Yes. Iman announced the groundbreaking, and DLD inspections recorded 0.20% on 14 January 2026 and 3.74% on 10 August 2026 (Continental Club, DLD data).

What is the Sierra by Iman completion date?

The DLD registered completion date is 30 June 2029. Iman Developers gives Q2 2029. Property Finder and some brokers show January 2029.

Is the Sierra by Iman handover date January 2029 or June 2029?

The developer's Q2 2029 and the DLD's 30 June 2029 agree. January 2029 appears on Property Finder and some broker pages but not in Iman's own announcement or the register.

When did construction start at Sierra by Iman?

The DLD register gives 1 November 2025. Property Finder and Data Habibi give June 2025, so sources differ.

Sources

  1. Property Finder, Sierra by Iman (opens in a new tab)propertyfinder.ae · accessed 11 Oct 2026
  2. Data Habibi, Sierra (opens in a new tab)datahabibi.ae · accessed 11 Oct 2026