When is the Shahrukhz by Danube handover date?
Short answer
The Shahrukhz by Danube handover date is 30 June 2029, the registered completion date on the DLD register, and Danube gives completion in 2029. The DLD recorded the tower 1.86% complete on 13 August 2026, up from 1.22% on 24 April 2026. The date has not changed since the November 2025 launch, but about 35 months of work remain for a 55 storey tower still at foundation stage.
Registered completion date (DLD)
30 Jun 2029
DLD project 4166, via Continental Club
Latest construction progress
1.86%
DLD inspection, 13 Aug 2026
Developer's stated date
2029
Danube, accessed 11 Oct 2026
Date at launch
June 2029
Dubai Property News, 9 Dec 2025
Shahrukhz by Danube handover date: the latest position
Shahrukhz by Danube is due for completion on 30 June 2029. That is the registered completion date the Dubai Land Department holds for project 4166, and Danube’s page gives completion and handover in 2029. More on prices, office sizes and the payment plan is on the Shahrukhz by Danube page.
The DLD recorded the tower 1.86% complete on 13 August 2026. Construction was registered as starting on 1 January 2026, so this is early foundation work, with almost 35 months left to the registered date. The date has not changed since the launch.
Shahrukhz by Danube handover date by building
Shahrukhz is a single 55 storey office tower, so one date applies to every unit.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Shahrukhz by Danube (662 commercial units on the DLD register) | 1.86%, 13 Aug 2026 | 30 Jun 2029 | 2029 (Danube); Q2 2029 (Propsearch; Continental Club) |
How the Shahrukhz by Danube handover date has changed
| Date | What happened | Source |
|---|---|---|
| 21 Oct 2025 | First DLD inspection on record, 0%. | DLD register, via Dubai Handover |
| 14 Nov 2025 | Tower unveiled in Mumbai with Shah Rukh Khan; completion slated for 2029. | Hindustan Times |
| 9 Dec 2025 | Launch coverage gives expected handover in June 2029. | Dubai Property News |
| Dec 2025 | Dubai launch at the Dubai Exhibition Centre; Danube says the project sold out on the day. | APN News, 16 Dec 2025 |
| 1 Jan 2026 | Registered construction start. | DLD register |
| 24 Apr 2026 | DLD inspection records 1.22%. Registered completion 30 June 2029. | DLD register, via Continental Club |
| 13 Aug 2026 | DLD inspection records 1.86%. | DLD register, via Continental Club |
What the Shahrukhz by Danube handover date means for payments
Shahrukhz is sold on Danube’s 1% monthly plan, which runs past handover. Brokers describe 70% paid before handover and 30% after it, over about 30 months (Proptz; Continental Club). Danube’s chairman described the plan at launch as 20% down and then 1% a month for six years (Hindustan Times). With a June 2029 handover, the post handover instalments would run to about the end of 2031. On a AED 2 million office, roughly AED 600,000 would remain at handover. A later handover would push the whole post handover schedule back.
What to check before relying on the Shahrukhz by Danube date
- The completion date and grace period in the SPA, which may differ from the 30 June 2029 registered date.
- When post handover instalments start in the SPA, whether at a fixed date or at the actual handover.
- The DLD progress for project 4166, through the DLD project status enquiry service, as the tower moves from foundations to structure.
Questions buyers also ask
What is the Shahrukhz by Danube completion date?
30 June 2029 on the DLD register for project 4166. Danube gives 2029 and broker listings Q2 2029.
How far along is construction at Shahrukhz by Danube?
1.86% at the DLD inspection on 13 August 2026, up from 1.22% on 24 April 2026. Propsearch lists Atlas Foundations as foundation contractor.
Has the Shahrukhz by Danube handover date been delayed?
No. The date given at launch, June 2029, matches the DLD registered completion date of 30 June 2029, and no change had been published by 11 October 2026.
How much is due at the Shahrukhz by Danube handover?
Under Danube's 1% plan, about 70% is paid before handover and the remaining 30% after it, over roughly 30 months (Proptz; Continental Club). On a AED 2 million office, that post handover balance is about AED 600,000.