When is the Shahrukhz by Danube handover date?

Updated 11 October 2026 Shahrukhz by Danube

Short answer

The Shahrukhz by Danube handover date is 30 June 2029, the registered completion date on the DLD register, and Danube gives completion in 2029. The DLD recorded the tower 1.86% complete on 13 August 2026, up from 1.22% on 24 April 2026. The date has not changed since the November 2025 launch, but about 35 months of work remain for a 55 storey tower still at foundation stage.

Registered completion date (DLD)

30 Jun 2029

DLD project 4166, via Continental Club

Latest construction progress

1.86%

DLD inspection, 13 Aug 2026

Developer's stated date

2029

Danube, accessed 11 Oct 2026

Date at launch

June 2029

Dubai Property News, 9 Dec 2025

Shahrukhz by Danube handover date: the latest position

Shahrukhz by Danube is due for completion on 30 June 2029. That is the registered completion date the Dubai Land Department holds for project 4166, and Danube’s page gives completion and handover in 2029. More on prices, office sizes and the payment plan is on the Shahrukhz by Danube page.

The DLD recorded the tower 1.86% complete on 13 August 2026. Construction was registered as starting on 1 January 2026, so this is early foundation work, with almost 35 months left to the registered date. The date has not changed since the launch.

Shahrukhz by Danube handover date by building

Shahrukhz is a single 55 storey office tower, so one date applies to every unit.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Shahrukhz by Danube (662 commercial units on the DLD register) 1.86%, 13 Aug 2026 30 Jun 2029 2029 (Danube); Q2 2029 (Propsearch; Continental Club)

How the Shahrukhz by Danube handover date has changed

Date What happened Source
21 Oct 2025 First DLD inspection on record, 0%. DLD register, via Dubai Handover
14 Nov 2025 Tower unveiled in Mumbai with Shah Rukh Khan; completion slated for 2029. Hindustan Times
9 Dec 2025 Launch coverage gives expected handover in June 2029. Dubai Property News
Dec 2025 Dubai launch at the Dubai Exhibition Centre; Danube says the project sold out on the day. APN News, 16 Dec 2025
1 Jan 2026 Registered construction start. DLD register
24 Apr 2026 DLD inspection records 1.22%. Registered completion 30 June 2029. DLD register, via Continental Club
13 Aug 2026 DLD inspection records 1.86%. DLD register, via Continental Club

What the Shahrukhz by Danube handover date means for payments

Shahrukhz is sold on Danube’s 1% monthly plan, which runs past handover. Brokers describe 70% paid before handover and 30% after it, over about 30 months (Proptz; Continental Club). Danube’s chairman described the plan at launch as 20% down and then 1% a month for six years (Hindustan Times). With a June 2029 handover, the post handover instalments would run to about the end of 2031. On a AED 2 million office, roughly AED 600,000 would remain at handover. A later handover would push the whole post handover schedule back.

What to check before relying on the Shahrukhz by Danube date

  1. The completion date and grace period in the SPA, which may differ from the 30 June 2029 registered date.
  2. When post handover instalments start in the SPA, whether at a fixed date or at the actual handover.
  3. The DLD progress for project 4166, through the DLD project status enquiry service, as the tower moves from foundations to structure.

Questions buyers also ask

What is the Shahrukhz by Danube completion date?

30 June 2029 on the DLD register for project 4166. Danube gives 2029 and broker listings Q2 2029.

How far along is construction at Shahrukhz by Danube?

1.86% at the DLD inspection on 13 August 2026, up from 1.22% on 24 April 2026. Propsearch lists Atlas Foundations as foundation contractor.

Has the Shahrukhz by Danube handover date been delayed?

No. The date given at launch, June 2029, matches the DLD registered completion date of 30 June 2029, and no change had been published by 11 October 2026.

How much is due at the Shahrukhz by Danube handover?

Under Danube's 1% plan, about 70% is paid before handover and the remaining 30% after it, over roughly 30 months (Proptz; Continental Club). On a AED 2 million office, that post handover balance is about AED 600,000.

Sources

  1. Continental Club, Shahrukhz By Danube (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 5 Oct 2026; inspection 13 Aug 2026
  2. Danube Properties, Shahrukhz project page (opens in a new tab)danubeproperties.com · accessed 11 Oct 2026
  3. Propsearch, Shahrukhz by Danube (opens in a new tab)propsearch.ae · updated 2 Jun 2026
Request a Unit Review