Handover date

When is the Seacliff by Imtiaz handover date?

Updated 11 October 2026 Seacliff by Imtiaz

Short answer

The registered completion date for Seacliff by Imtiaz is 15 August 2028 on the Dubai Land Department (DLD) project register. The last DLD inspection, on 20 July 2026, put construction at 4.71%. Imtiaz announced a Q1 2028 handover at the June 2026 groundbreaking, so marketing and the register differ by two quarters.

Registered completion date (DLD)

15 Aug 2028

DLD register via Continental Club, updated 8 Oct 2026

Latest construction progress

4.71%

DLD inspection, 20 Jul 2026

Developer's stated date

Q1 2028

Imtiaz via Khaleej Times, 30 Jun 2026

Portal estimate

Aug 2028

Property Finder, accessed 11 Oct 2026

Seacliff by Imtiaz handover date: the latest position

The Dubai Land Department (DLD) project register gives Seacliff by Imtiaz, the 170 unit Imtiaz Developments building on Dubai Islands, a registered completion date of 15 August 2028. Imtiaz announced a Q1 2028 handover when it broke ground in June 2026 (Khaleej Times, 30 June 2026). Full project details are on the Seacliff by Imtiaz page.

The latest DLD inspection, on 20 July 2026, recorded 4.71% progress. Property Finder and Continental Club’s developer field follow the register, with August 2028 and Q3 2028. The DLD register lists 170 units, 113 of them 1 bedrooms.

Seacliff by Imtiaz handover date by building

Seacliff by Imtiaz is one building, DLD project number 4306.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Seacliff by Imtiaz (170 units) 4.71% (20 Jul 2026) 15 Aug 2028 Q1 2028 (Imtiaz, Jun 2026); Q3 2028 (developer field, Continental Club); Aug 2028 (Property Finder)

How the Seacliff by Imtiaz handover date has changed

  • 30 December 2025: first DLD inspection, at 0%.
  • 15 February 2026: sales and construction start (Property Finder, DLD register).
  • 21 April 2026: Alnair reports the launch with a Q1 2028 handover and a 50/50 plan.
  • 24 April 2026: DLD inspection at 1.11%.
  • 30 June 2026: Imtiaz breaks ground on the AED 600 million project and repeats Q1 2028 (Khaleej Times).
  • 20 July 2026: DLD inspection at 4.71%.
  • October 2026: the register still shows 15 August 2028 (Continental Club, updated 8 October 2026).

No change to the registered date has been reported. The difference is between the Q1 2028 marketing date and the later date on the register. Continental Club records a pace of 0.71% a month so far, early in the build.

What the Seacliff by Imtiaz handover date means for payments

The plan is 20% on booking, 30% during construction and 50% on handover (Continental Club, Property Finder and Metropolitan). The construction instalments run from June 2026 to November 2027 (Metropolitan). After that, half the price is due on completion. On a 1 bedroom at the DLD median of AED 2,176,620, the handover payment is about AED 1.09 million. If completion follows the registered August 2028 date rather than Q1 2028, there is a gap of about nine months between the last instalment and that payment.

What to check before relying on the Seacliff by Imtiaz date

  1. Which date is in the SPA. Sales material says Q1 2028, while the register says 15 August 2028.
  2. The grace period after the SPA date. It decides how late completion can run before delay terms apply.
  3. Pace at the next DLD inspection. At 4.71% in July 2026, the building needs close to 4% a month to finish by August 2028.
  4. Funding for the 50% balance. Buyers using a mortgage for the handover payment need it ready for the actual completion month.

Questions buyers also ask

What is the Seacliff by Imtiaz completion date?

The DLD register gives 15 August 2028 (Continental Club, registry updated 8 October 2026). Property Finder also shows August 2028, while Imtiaz announced Q1 2028 at the groundbreaking.

Is Seacliff by Imtiaz finished?

No. Construction started on 15 February 2026, and the DLD inspection on 20 July 2026 recorded 4.71% progress.

Has the Seacliff by Imtiaz handover date been delayed?

No formal change has been published. The register shows 15 August 2028, while marketing has used Q1 2028 throughout 2026, so the gap is between two current dates rather than a recorded delay.

When will Sea Cliff Residence on Dubai Islands be ready?

Sea Cliff Residence is the same project. Its registered completion date is 15 August 2028, with Imtiaz giving Q1 2028.