When is the Sea Legend One handover date?
Short answer
The registered completion date for Sea Legend One is 30 November 2026 on the Dubai Land Department (DLD) project register. The last DLD inspection, on 4 August 2026, put construction at only 22.2%, so the building will not be completed by then. Alnair reported 30 June 2027 in June 2025, and at the recorded pace of about 2% a month completion would fall well after that.
Registered completion date (DLD)
30 Nov 2026
DLD register via Continental Club, updated 8 Oct 2026
Latest construction progress
22.2%
DLD inspection, 4 Aug 2026
Developer's stated date
Q4 2026
Developer supplied, via Continental Club and Property Finder
Date reported at June 2025 sales push
30 Jun 2027
Alnair, 13 Jun 2025
Sea Legend One handover date: the latest position
The Dubai Land Department (DLD) project register gives Sea Legend One, the MVS Real Estate building on Dubai Islands, a registered completion date of 30 November 2026. Property Finder and the developer’s own figure also say Q4 2026. Full project details are on the Sea Legend One page.
The latest DLD inspection, on 4 August 2026, recorded 22.2% progress, with less than four months to the registered date. The date has not been formally changed on the register, but the building cannot be completed by then. An Alnair report in June 2025 gave 30 June 2027, and Continental Club’s projection at the current pace is November 2029.
Sea Legend One handover date by building
Sea Legend One is a single building, DLD project number 3265, listed on the register as “Sea Legend One By Mvs Real Estate”.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Sea Legend One (65 units) | 22.2% (4 Aug 2026) | 30 Nov 2026 | Q4 2026 (developer and Property Finder); 30 Jun 2027 (Alnair, Jun 2025) |
How the Sea Legend One handover date has changed
- 21 September 2023: sales and construction start on the DLD register and Property Finder. Two large registered purchases follow in September 2023.
- 20 January 2025: first DLD inspection, at 0%.
- 13 June 2025: Alnair reports the launch of Sea Legend One with a 60/40 plan and a completion date of 30 June 2027.
- 3 March 2026: DLD inspection at 12.23%.
- 22 June 2026: 18.13%.
- 4 August 2026: 22.2%.
- October 2026: the register still shows 30 November 2026 (Continental Club, updated 8 October 2026).
Sources disagree on the launch date, September 2023 on Property Finder and June 2025 in Alnair’s report. Both point to a date later than the register now shows.
What the Sea Legend One handover date means for payments
The plan is 20% on booking, 40% during construction in four instalments and 40% on handover (Property Finder and Continental Club). The 40% handover payment is due on actual completion, not on 30 November 2026. On a 1 bedroom at the DLD median of AED 2,163,840, that final payment is about AED 865,000. Buyers who have already paid 60% carry that amount through any extra construction time.
What to check before relying on the Sea Legend One date
- Which date the SPA shows. The register says 30 November 2026, while Alnair’s June 2025 report gave 30 June 2027, so contract dates may differ by booking date.
- The grace period and delay terms. With the registered date certain to pass, the SPA terms on late completion are the key document.
- Any extension filed with DLD. A change to the registered completion date will appear on the DLD project status service.
- Construction instalment triggers. Whether the four construction payments follow progress stages or calendar dates decides when they fall due.
Questions buyers also ask
What is the Sea Legend One completion date?
The DLD register gives 30 November 2026 (Continental Club, registry updated 8 October 2026). The building was 22.2% complete on 4 August 2026, so that date will be missed.
Is Sea Legend One finished?
No. The DLD inspection on 4 August 2026 recorded 22.2% progress, up from 18.13% on 22 June 2026.
Has the Sea Legend One handover date been delayed?
In practice, yes. The register and Property Finder still show November 2026, but an Alnair report in June 2025 already gave 30 June 2027, and progress of 22.2% in August 2026 points later still. MVS Real Estate has not published a revised date.
When will Sea Legend One by MVS be ready?
No firm date has been published. Continental Club's projection at the current pace of 1.97% a month is November 2029, which is an estimate, not a developer commitment.