Handover date

When is the Sapphire 32 handover date?

Updated 11 October 2026 Sapphire 32

Short answer

Sapphire 32 has a registered completion date of 15 December 2026 in the DLD project register, and the developer gives Q4 2026. The latest DLD inspection, on 10 July 2026, recorded 62.28% complete, up from 61.87% in March 2026. Finishing by December would need the tower to return to its fastest recorded pace, so the date and grace period in each SPA matter more than the Q4 2026 headline.

Registered completion date (DLD)

15 Dec 2026

DLD project register via Continental Club, accessed 11 Oct 2026

Latest construction progress

62.28%

DLD inspection, 10 Jul 2026

Developer's stated date

Q4 2026

Developer via Continental Club; Property Finder

Progress, March to July 2026

+0.41 points

DLD inspections via Continental Club

Sapphire 32 handover date: the latest position

Sapphire 32 is registered to complete on 15 December 2026, and Dar Al Karama Real Estate gives Q4 2026. At the latest DLD inspection, on 10 July 2026, the tower was 62.28% complete. Prices and plans are on the Sapphire 32 page.

The date has not moved, but progress has slowed. Between 23 March and 10 July 2026 the recorded figure rose by only 0.41 points. To finish on 15 December 2026, the tower would need to add about 38 points in five months.

Sapphire 32 handover date by building

Sapphire 32 is a single tower with five podium levels and 27 residential floors.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Sapphire 32 (232 units, project 2757) 62.28%, 10 Jul 2026 15 Dec 2026 Q4 2026 (developer, via Continental Club); December 2026 (Property Finder)

DLD figures are from Continental Club and Dubai Handover, which republish the DLD project register.

How the Sapphire 32 handover date has changed

Date What happened Source
1 Oct 2023 Construction starts; completion registered for 15 December 2026. DLD register, via Mitchell’s
2024 Most units sell: 204 DLD sales at a median of AED 1,276 per sq ft. Dubai Handover
30 Sep 2024 2.5% complete. DLD inspection, via Dubai Handover
24 Apr 2025 14.5% complete. DLD inspection, via Dubai Handover
27 Nov 2025 34.0% complete. DLD inspection, via Dubai Handover
23 Mar 2026 61.87% complete. DLD inspection, via Continental Club
10 Jul 2026 62.28% complete. DLD inspection, via Continental Club
10 Oct 2026 Registered date still 15 December 2026. DLD snapshot, via Dubai Handover

The registered date and the developer’s Q4 2026 have matched since construction began. Data Habibi gives 31 December 2026 for handover, a fortnight after the registered date.

What the Sapphire 32 handover date means for payments

The standard plan leaves 40% of the price for handover, after 10% on booking and 50% during construction (Data Habibi; Continental Club). Studios and 1 bedrooms pay that 40% on handover. Buyers of 2 and 3 bedrooms on the post-handover plan pay it over two years after handover at about 1.67% a month (offplans.com). A later completion pushes back both the handover payment and the start of those instalments.

What to check before relying on the Sapphire 32 date

  1. A DLD inspection newer than 10 July 2026, through DLD’s project status enquiry for project 2757, to see whether work has picked up.
  2. The completion date and grace period in the SPA, which govern what happens if 15 December 2026 is missed.
  3. Which plan the unit is on, since the post-handover plan changes when the last 40% is paid.

Questions buyers also ask

Is Sapphire 32 finished?

No. It was 62.28% complete at the DLD inspection on 10 July 2026. Its registered completion date is 15 December 2026.

What is the Sapphire 32 completion date?

15 December 2026 in the DLD project register, where the tower is DLD project 2757, registered by Dar Al Karama Real Estate with construction starting on 1 October 2023.

Will Sapphire 32 be ready by December 2026?

Only if work speeds up sharply. About 38 points remained in July 2026, and the tower had added only 0.41 points between 23 March and 10 July 2026. Its fastest recorded stretch was about 28 points in the four months to March 2026, roughly the pace now needed.

Has the Sapphire 32 handover date been delayed?

Not on paper. The registered date has stayed at 15 December 2026 and the developer still gives Q4 2026 (Dubai Handover daily snapshots, August to October 2026). The risk is that the date is not met.

Sources

  1. Mitchell's, Sapphire 32 by Dar Alkarama DLD registry (opens in a new tab)mitchellscommercialrealty.com · registry as at 15 Jun 2026, status 23 Sep 2026
  2. Data Habibi, Sapphire 32 (opens in a new tab)datahabibi.ae · accessed 11 Oct 2026
Request a Unit Review