Handover date

When is the Samana Waves handover date?

Updated 11 October 2026 Samana Waves

Short answer

Samana now gives a Q1 2027 handover for Samana Waves and Q3 2027 for Samana Waves 2. Waves 1 was 90.06% complete at its DLD inspection on 19 June 2026, and Waves 2 was 52.09% complete on 2 October 2026. Their registered completion dates with DLD, 15 April 2026 and 20 March 2026, have both passed without completion.

Registered completion dates (DLD)

15 Apr 2026 and 20 Mar 2026

Waves 1 and Waves 2, both passed; DLD project register via Continental Club

Latest construction progress

90.06% and 52.09%

DLD inspections, 19 Jun 2026 (Waves 1) and 2 Oct 2026 (Waves 2)

Developer's stated dates

Q1 2027 and Q3 2027

Samana project pages, accessed 11 Oct 2026

Dates at launch

Q1 2025 and Q1 2026

Construction Week, 14 Mar 2022; Property Finder

Samana Waves handover date: the latest position

Samana now gives a Q1 2027 handover for Samana Waves and Q3 2027 for Samana Waves 2, on its own project pages (accessed 11 October 2026). Prices, sizes and the payment plans are on the Samana Waves page.

The DLD register has not caught up. It still holds registered completion dates of 15 April 2026 for Waves 1 and 20 March 2026 for Waves 2, and both have passed. Waves 1 was 90.06% complete on 19 June 2026, with no newer inspection published by 8 October 2026. Waves 2 was 52.09% complete on 2 October 2026.

Samana Waves handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Samana Waves (197 units) 90.06%, 19 Jun 2026 15 Apr 2026 (passed) Q1 2027 (Samana); Q2 2026, shown as ready (Property Finder)
Samana Waves 2 (173 units) 52.09%, 2 Oct 2026 20 Mar 2026 (passed) Q3 2027 (Samana); 31 Aug 2027 (JRE)

Waves 2 is DLD project number 2574, with its escrow account at Emirates NBD. The DLD register name for the first building is simply “Samana Waves”.

How the Samana Waves handover date has changed

Date What happened Source
12 Mar 2022 Waves 1 launched, due Q1 2025 Construction Week; Khaleej Times
1 Jul 2022 Waves 1 construction start recorded DLD register
1 Jan 2023 Waves 2 sales start, due Q1 2026 (1 March 2026) Property Finder
21 Sep 2023 Waves 2 construction start recorded DLD register
11 Feb 2026 Waves 2 at 35.40% DLD register
20 Mar 2026 Waves 2 registered completion date passes DLD register
15 Apr 2026 Waves 1 registered completion date passes DLD register
19 Jun 2026 Waves 1 at 90.06%; Waves 2 at 47.25% DLD register
2 Oct 2026 Waves 2 at 52.09% DLD register
11 Oct 2026 Samana shows Q1 2027 and Q3 2027 Samana

Waves 1 is now two years behind its launch date and Waves 2 about 18 months behind. Waves 2 added 4.84 points between June and October 2026. At that pace, the remaining 48 points would take more than two years, so reaching Q3 2027 would need faster work.

What the Samana Waves handover date means for payments

Under the Waves 2 plan on Property Finder, 1% is due on handover and 24% after it, so most of the price is paid before keys. The original Waves 1 plan ran 1% a month for 65 months from March 2022, ending around 2027, regardless of construction stage. Samana’s current Waves 1 plan adds 0.5% a month for 60 months, which extends payments well past handover.

What to check before relying on the Samana Waves date

  1. The building named in the SPA, since Waves 1 and Waves 2 are about 38 points apart.
  2. Any written notice of the revised date, given that both registered dates in the DLD register have passed.
  3. The SPA terms on delay, including any grace period after the original completion date.
  4. The next Waves 1 inspection, which should show whether it has passed 90% since June 2026.

Questions buyers also ask

When will Samana Waves be completed?

Samana gives Q1 2027 for Waves 1, which was 90.06% complete on 19 June 2026. Its registered completion date, 15 April 2026, has passed (DLD project register via Continental Club).

When will Samana Waves 2 be ready?

Samana gives Q3 2027 for Waves 2. The building was 52.09% complete at the DLD inspection on 2 October 2026, and its registered date of 20 March 2026 has passed.

Has the Samana Waves handover date been delayed?

Yes. Waves 1 was due in Q1 2025 at launch in March 2022 and is now dated Q1 2027. Waves 2 was due in Q1 2026 and is now dated Q3 2027.

Is Samana Waves finished?

No. Neither building is recorded as completed in the DLD register. Real Estate Club Dubai still showed Waves 1 at 90% on 8 October 2026.