When is the Samana Park Meadows handover date?
Short answer
Samana Park Meadows is registered with the DLD for completion on 31 August 2027, while Samana Developers announced a March 2028 handover at launch in October 2024. The DLD inspection of 1 October 2026 recorded 38.03% complete. At the pace of the past year, Continental Club projects completion around September 2028, later than both dates.
Registered completion date (DLD)
31 Aug 2027
DLD project register via Continental Club
Latest construction progress
38.03%
DLD inspection, 1 Oct 2026
Developer's date at launch
March 2028
Samana via Zawya, 3 Oct 2024
Projection at past year's pace
About Sep 2028
Continental Club, 2.61 points a month
Samana Park Meadows handover date: the latest position
The Dubai Land Department (DLD) project register lists Samana Park Meadows with a completion date of 31 August 2027. At launch on 3 October 2024, Samana Developers announced completion and handover in March 2028. Prices, sizes and the full plan are on the project page: Samana Park Meadows.
The DLD inspection of 1 October 2026 recorded 38.03% complete. Meeting the August 2027 register date would need about 5.6 points a month for the next 11 months, about double the pace of the past year.
Samana Park Meadows handover date by building
The project is one building of two basements, a ground floor, 16 floors and a roof, with 221 apartments.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Samana Park Meadows (221 units) | 38.03% (1 Oct 2026) | 31 Aug 2027 | March 2028 (Samana at launch); Q3 2027 (Continental Club); August 2027 (Propsearch); Q1 2028 (Data Habibi) |
Earlier DLD inspections: 8.61% on 23 October 2025 and 27.27% on 18 June 2026 (via Continental Club).
How the Samana Park Meadows handover date has changed
| Date | Event | Source |
|---|---|---|
| 1 Aug 2024 | Construction start on the DLD register | DLD via Continental Club |
| 28 Aug 2024 | Project registered with the DLD | Dubai Data |
| 3 Oct 2024 | Launch: AED 220 million, 221 units, from AED 694,000, handover March 2028 | Zawya, Arabian Business |
| 23 Oct 2025 | DLD inspection: 8.61% | DLD register via Continental Club |
| 3 Jan 2026 | Propsearch estimate: August 2027 | Propsearch |
| 18 Jun 2026 | DLD inspection: 27.27% | DLD register via Continental Club |
| 1 Oct 2026 | DLD inspection: 38.03% | DLD register via Continental Club |
The two dates have both stood since 2024. Progress picked up in 2026: 10.76 points between June and October, about 3.2 points a month. Continental Club’s projection of about 22 September 2028 uses the slower 2.61 points a month average of the past year.
What the Samana Park Meadows handover date means for payments
Samana’s non-PDC plan takes 20% on booking, 1% a month for 42 months, 10% in month 12 and 5% in month 18, which is 77% in about three and a half years from booking. The last 23% is paid at 0.5% a month for 46 months; on the PDC plan it is 28% over 56 months. Data Habibi lists 5% due on handover itself.
For a buyer who booked in October 2024, the 42 monthly instalments end around April 2028, close to the launch handover date. On a AED 1.46 million two bedroom, the 0.5% stage is about AED 7,300 a month.
What to check before relying on the Samana Park Meadows date
- Which date the SPA states, 31 August 2027 or March 2028, and the grace period after it.
- Progress at the next DLD inspections, to see whether the 2026 pace of about 3 points a month holds or rises.
- The plan wording, including any handover payment and the start date of the 0.5% instalments.
Questions buyers also ask
When will Samana Park Meadows be completed?
The DLD register gives 31 August 2027 (project number 2896). Samana announced March 2028 at launch, and Data Habibi shows Q1 2028.
Has the Samana Park Meadows handover date been delayed?
No delay has been announced. The launch date was March 2028; the register date of 31 August 2027 is earlier. Progress of 38.03% in October 2026 makes the August 2027 date hard to reach.
How far along is Samana Park Meadows?
38.03% at the DLD inspection of 1 October 2026, up from 27.27% on 18 June 2026 and 8.61% on 23 October 2025 (DLD register via Continental Club).
When does the post-handover plan at Samana Park Meadows start?
Samana's plans end with 0.5% a month for 46 months (non-PDC) or 56 months (PDC). At launch, Samana's chief executive described these as payments after handover, so they start when the building is handed over.