Handover date

When is the Samana Ivy Gardens handover date?

Updated 11 October 2026 Samana Ivy Gardens

Short answer

Samana Ivy Gardens 2 has a registered completion date of 31 December 2027 in the DLD project register, and Samana lists Q4 2027. It was 15.19% complete at the DLD inspection on 18 June 2026. The first Samana Ivy Gardens building was due in May 2026 but was 27.49% complete on 28 April 2026, so its launch date has passed with no revised date published.

Ivy Gardens 2, registered completion date (DLD)

31 Dec 2027

DLD project register via Continental Club, accessed 11 Oct 2026

Ivy Gardens 2, latest progress

15.19%

DLD inspection, 18 Jun 2026

Ivy Gardens (first building), latest progress

27.49%

DLD inspection, 28 Apr 2026

First building, date at launch

May 2026

Gulf News, 31 May 2023

Samana Ivy Gardens handover date: the latest position

Samana Ivy Gardens 2 has a registered completion date of 31 December 2027 in the DLD project register, and Samana lists a Q4 2027 handover. The first Samana Ivy Gardens building was launched for May 2026 completion, a date that has now passed. Prices, sizes and payment plans for both are on the Samana Ivy Gardens page.

Neither building is close to finished. The first was 27.49% complete on 28 April 2026, a month before its target. Ivy Gardens 2 was 15.19% complete on 18 June 2026, with 18 months left to its registered date.

Samana Ivy Gardens handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Samana Ivy Gardens 2 (DLD 2909, 836 units) 15.19%, 18 Jun 2026 31 Dec 2027 Q4 2027 (Property Finder, Dubizzle)
Samana Ivy Gardens (DLD 2642, 374 units) 27.49%, 28 Apr 2026 No revised date published May 2026 at launch; June 2026 (Property Finder)

Both buildings are in the Wadi Al Safa 5 district, the registered area for Dubailand Residence Complex (DLD project register via Continental Club).

How the Samana Ivy Gardens handover date has changed

Date What happened Source
31 May 2023 First building launched: 348 apartments, completion May 2026 Gulf News
30 Nov 2023 First building: construction start recorded DLD register via Continental Club
24 Jun 2024 Ivy Gardens 2 launched: 843 units, completion November 2027 fäm Properties
27 Nov 2024 Ivy Gardens 2 inspection: 1.58% DLD register via Continental Club
2 Jul 2025 Ivy Gardens 2 inspection: 5.47% DLD register via Continental Club
10 Feb 2026 Ivy Gardens 2 inspection: 8.77% DLD register via Continental Club
28 Apr 2026 First building inspection: 27.49% DLD register via Continental Club
18 Jun 2026 Ivy Gardens 2 inspection: 15.19% DLD register via Continental Club
Oct 2026 Ivy Gardens 2 registered for 31 Dec 2027 DLD register via Continental Club

Ivy Gardens 2 moved from November 2027 at launch to a registered 31 December 2027, a one month change. The bigger gap is pace. It took about two years to pass 15%, and the remaining 84.81 points need about 4.6 points a month to meet the registered date. Continental Club’s projection from the average pace since the start runs to 2034. For the first building, the register and portals have not yet shown a date to replace May 2026.

What the Samana Ivy Gardens handover date means for payments

For Ivy Gardens 2, the plan on the DLD listing (via Continental Club) and Property Finder is 20% on booking, 57% during construction and 23% on handover. On a studio at the AED 703,790 DLD median, the handover payment is about AED 162,000. For the first building, Continental Club gives a plan with 1% a month for 35 months, so buyers from 2023 had largely finished construction payments while the building was still about a quarter built. Its 25% post-handover share, at 0.5% a month for 50 months, only starts once handover happens.

What to check before relying on the Samana Ivy Gardens date

  1. Which building is named in the SPA, since Ivy Gardens and Ivy Gardens 2 are separate DLD projects with different dates.
  2. For the first building, the SPA grace period and any written notice of a new date, since May 2026 has passed.
  3. For Ivy Gardens 2, the next DLD inspection. At the 4.6 points a month needed for 31 December 2027, the tower would be near 45% by the end of December 2026.

Questions buyers also ask

When will Samana Ivy Gardens 2 be ready?

The registered completion date is 31 December 2027 and Samana lists Q4 2027. At launch in June 2024 the target was November 2027 (fäm Properties). The tower was 15.19% complete on 18 June 2026.

What is the Samana Ivy Gardens completion date?

For Ivy Gardens 2, 31 December 2027 in the DLD project register. For the first building, the launch target was May 2026 (Gulf News, 31 May 2023) and Property Finder shows June 2026, but it was 27.49% complete on 28 April 2026.

Has the Samana Ivy Gardens handover been delayed?

Yes for the first building, which passed its May 2026 target at about a quarter built. Ivy Gardens 2 has moved from November 2027 at launch to a registered 31 December 2027.

Is Samana Ivy Gardens finished?

No. Neither building was complete by October 2026. The latest DLD inspections recorded 27.49% for the first building (28 April 2026) and 15.19% for Ivy Gardens 2 (18 June 2026).

Sources

  1. DLD project register via Continental Club, Samana Ivy Gardens 2 (inspection 18 Jun 2026) (opens in a new tab)continentalclub.ae · construction section updated 7 Oct 2026, accessed 11 Oct 2026
  2. DLD project register via Continental Club, Dubai handover 2027 tracker (opens in a new tab)continentalclub.ae · updated 10 Oct 2026, accessed 11 Oct 2026