Handover date

When is the Samana Hills South handover date?

Updated 12 October 2026 Samana Hills South

Short answer

The Samana Hills South handover date is 15 May 2028 for the original phase and 31 August 2028 for phases 2 and 3, the registered completion dates on the Dubai Land Department (DLD) register. DLD site inspections put the original phase at 12.12% complete on 28 September 2026, and phases 2 and 3 at 5.26% and 4.60% in June 2026. Samana's own launch dates differ by phase, from Q2 2028 to October 2028, so the date in each buyer's SPA is the one that applies.

Registered completion date, phase 1 (DLD)

15 May 2028

DLD register, project 3796; phases 2 and 3 registered for 31 Aug 2028

Latest construction progress

12.12% (phase 1)

DLD site inspection, 28 Sep 2026; phases 2 and 3 at 5.26% and 4.60% (8 and 22 Jun 2026)

Developer's stated dates

Q2 to Oct 2028

Q2 2028 for phase 1 (Property Finder); Oct 2028 for phase 3 (Samana, 27 Oct 2025)

Date change since launch

Q4 2027 to Q2 2028

Phase 1 only, Data Habibi, accessed 1 Oct 2026

Samana Hills South handover date: the latest position

Samana Hills South, in Saih Shuaib 2, Dubai Industrial City, is three separately registered phases. The Dubai Land Department register holds a registered completion date of 15 May 2028 for the original phase and 31 August 2028 for phases 2 and 3. DLD site inspections recorded the original phase at 12.12% complete on 28 September 2026, and phases 2 and 3 at about 5% in June 2026. Prices, sizes and sales for each phase are on the Samana Hills South page.

The phases are moving at different speeds. Phase 2 went from 0.67% in February 2026 to 5.26% in June, and phase 3 from 0% in September 2025 to 4.60% in June 2026. The original phase moved from 4.54% to 4.84% between April and June 2026, then to 12.12% by 28 September 2026. It still had about 88% left to build with about 19 months to its registered date, and phases 2 and 3 had more than 94% left at their June inspections.

Samana Hills South handover date by phase

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
Phase 1, two buildings, 510 units (project 3796) 12.12%, 28 Sep 2026 15 May 2028 Q2 2028, 15 May 2028 (Property Finder)
Phase 2, 140 units (project 4025) 5.26%, 8 Jun 2026 31 Aug 2028 Q2 2028 (Propsearch estimate); Oct 2028 (Propsearch, Aug 2025 launch note)
Phase 3, 147 units (project 4074) 4.60%, 22 Jun 2026 31 Aug 2028 Oct 2028 (Samana, 27 Oct 2025)

Unit counts are from the DLD register via Continental Club. Propsearch counts 151 units for phase 2, including 10 lofts.

How the Samana Hills South handover date has changed

Date What happened Source
1 Jun 2025 Phase 1 sales and registered construction start. Expected completion 15 May 2028. Property Finder; DLD register
Aug 2025 Phase 2 launched and sold its 140 units; handover given as October 2028. Propsearch
11 Sep 2025 Phase 3 at 0% at its first DLD inspection. DLD register, via Continental Club
27 Oct 2025 Phase 3 launched with 147 units, estimated handover October 2028. Samana, via Zawya
10 Feb 2026 Phase 2 at 0.67%. DLD register, via Continental Club
17 Apr 2026 Phase 1 at 4.54%. DLD register, via Continental Club
8 to 22 Jun 2026 Phases at 4.60% to 5.26%. DLD register, via Continental Club
28 Sep 2026 Phase 1 at 12.12%. DLD register, via Continental Club

Data Habibi records an original developer promise of Q4 2027 for phase 1 and a current target of Q2 2028. No other source checked shows a 2027 date.

What the Samana Hills South handover date means for payments

The share due at handover varies widely by phase. Property Finder lists two options for phase 1: 15% at booking, 10% during construction and 75% at handover, or 20%, 10% and 70%. Data Habibi lists a different phase 1 plan with 1% at handover and 45% paid over 45 months after it. Phase 2 was launched on 20% at booking, 46% during construction, 1% at handover and 33% after handover (Propsearch). For a phase 1 buyer on the 75% option, the May 2028 date decides when three quarters of the price falls due.

What to check before relying on the Samana Hills South date

  1. Which phase and DLD project number your unit is in: 3796, 4025 or 4074. Phase 1 is registered three and a half months earlier than phases 2 and 3.
  2. Which date your SPA uses for phase 2 or 3. The register says 31 August 2028, while Samana’s launch materials said October 2028.
  3. Which payment plan your SPA follows, since phase 1 has been sold on plans with 70% to 75% at handover and on a plan with 1% at handover and the rest after it.

Questions buyers also ask

What is the Samana Hills South completion date?

15 May 2028 for the original phase, on the DLD register for project 3796. Property Finder lists the same date. Phases 2 and 3 are registered for 31 August 2028 (Continental Club, DLD data, 25 Sep 2026).

Is Samana Hills South finished?

No. DLD inspections recorded the original phase at 12.12% on 28 September 2026, up from 4.84% on 22 June 2026, phase 2 at 5.26% on 8 June 2026 and phase 3 at 4.60% on 22 June 2026.

When will Samana Hills South 2 be ready?

The DLD register holds 31 August 2028. Propsearch lists an estimated Q2 2028, while its note on the August 2025 sales launch gives October 2028. Phase 2 was 5.26% built on 8 June 2026.

When will Samana Hills South 3 be ready?

The DLD register holds 31 August 2028. Samana gave an estimated handover of October 2028 when it launched phase 3 (Zawya, 27 Oct 2025). Phase 3 was 4.60% built on 22 June 2026.

Has the Samana Hills South handover date been delayed?

Data Habibi records an original developer promise of Q4 2027 for the first phase and a current target of Q2 2028. The DLD registered dates have not changed in the sources checked (accessed 1 Oct 2026).

Sources

  1. Continental Club, Samana Hills South (DLD register) (opens in a new tab)continentalclub.ae · registry updated 25 Sep 2026
  2. Continental Club, Samana Hills South 2 (DLD register) (opens in a new tab)continentalclub.ae · registry updated 25 Sep 2026
  3. Continental Club, Samana Hills South 3 (DLD register) (opens in a new tab)continentalclub.ae · registry updated 25 Sep 2026
  4. Propsearch, Samana Hills South 2 (opens in a new tab)propsearch.ae · updated 10 Apr 2026
  5. Data Habibi, Samana Hills South (opens in a new tab)datahabibi.ae · accessed 1 Oct 2026