When is the Samana Business Park handover date?
Short answer
Samana Business Park is due for handover in Q3 2028, and its registered completion date with DLD is 30 September 2028; Samana Business Park 2 is registered for 31 October 2028. The first building was 12.83% complete at its DLD inspection on 24 September 2026, and the second 2.96% on 16 April 2026. The date is later than the Q4 2027 shown in earlier marketing, and both buildings have most of their construction still ahead.
Registered completion date (DLD)
30 Sep 2028
Business Park 2: 31 Oct 2028
Latest construction progress
12.83%
DLD inspection, 24 Sep 2026
Developer's stated date
Q3 2028
Samana, accessed 11 Oct 2026
Earlier marketed date
Q4 2027
fäm Properties and agent listings
Samana Business Park handover date: the latest position
Samana gives Q3 2028 as the handover date, and the DLD project register holds a registered completion date of 30 September 2028 for the first building. The second building, registered as Samana Business Park 2, is due on 31 October 2028. Prices, unit types and the payment plan are on the Samana Business Park page.
The first building was 12.83% complete at its DLD inspection on 24 September 2026, with two years left to its registered date. Business Park 2 started five months later and was 2.96% complete at its last published inspection, on 16 April 2026.
Samana Business Park handover date by building
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Samana Business Park (project 3812, 103 units) | 12.83%, 24 Sep 2026 | 30 Sep 2028 | Q3 2028 (Samana) |
| Samana Business Park 2 (project 4110, 174 units) | 2.96%, 16 Apr 2026 | 31 Oct 2028 | Q4 2028 (Continental Club) |
The first building is the smaller one: two basements, a ground floor, eight upper floors and a roof. Business Park 2 is taller, with an underground level, four basements, a ground floor, 14 floors and a roof, and it holds most of the units.
How the Samana Business Park handover date has changed
| Date | What happened | Source |
|---|---|---|
| 1 Jun 2025 | Construction start recorded for building 1 | DLD register |
| 2025 | Project marketed with a Q4 2027 handover | fäm Properties; agent listings |
| 1 Nov 2025 | Construction start recorded for Business Park 2 | DLD register |
| 16 Apr 2026 | Business Park 2 at 2.96% | DLD register |
| 22 Apr 2026 | Building 1 at about 5.09% | DLD register |
| 18 Jun 2026 | Building 1 at 5.61% | DLD register |
| 24 Sep 2026 | Building 1 at 12.83% | DLD register |
| 11 Oct 2026 | Samana’s page shows Q3 2028 | Samana |
The marketed date has moved about three quarters later, from Q4 2027 to Q3 2028. Progress on the first building was slow in its first year, about half a point between April and June 2026, then rose by more than 7 points in the three months to September. To reach completion by 30 September 2028, the remaining 87% has to be built in 24 months, a pace of about 3.6 points a month.
What the Samana Business Park handover date means for payments
Samana’s plan is mostly time-based rather than tied to construction stages. On the PDC plan, buyers pay 15% on booking, 1% a month for 36 months and lump sums of 10%, 5% and 5% in months 12, 18 and 24. The remaining 29% is paid at 0.5% a month for 58 months after handover (Samana). A later handover would push back the start of the post-handover instalments, while the 36 monthly payments run on the calendar.
What to check before relying on the Samana Business Park date
- Which of the two buildings the unit is in. Business Park 2 is registered a month later and started later.
- The SPA completion date and grace period, since some buyers may hold contracts drawn up when Q4 2027 was being marketed.
- The next DLD inspection for Business Park 2, as no figure has been published since April 2026.
Questions buyers also ask
When will Samana Business Park be completed?
The DLD register holds a registered completion date of 30 September 2028 for the first building and 31 October 2028 for Samana Business Park 2. Samana gives Q3 2028.
Has the Samana Business Park handover date been delayed?
Earlier marketing, including fäm Properties' project page, gave Q4 2027. Samana's own page now says Q3 2028, in line with the registered date of 30 September 2028.
When will Samana Business Park 2 be ready?
Samana Business Park 2 has a registered completion date of 31 October 2028. It started on 1 November 2025 and was 2.96% complete at its DLD inspection on 16 April 2026.
Is Samana Business Park finished?
No. The first building was 12.83% complete on 24 September 2026, with about two years left to its registered completion date.