Handover date

When is the Rove Home Dubai Marina handover date?

Updated 11 October 2026 Rove Home Dubai Marina

Short answer

The registered completion date for Rove Home Dubai Marina is 31 March 2028 on the Dubai Land Department (DLD) project register, while IRTH Development and Property Finder give Q4 2027. The last DLD inspection, on 6 July 2026, put construction at 7.8%. Progress rose only 0.66 points between December 2025 and July 2026, so the gap between the two dates matters for the 50% due at handover.

Registered completion date (DLD)

31 Mar 2028

DLD register via Continental Club, updated 9 Oct 2026

Latest construction progress

7.8%

DLD inspection, 6 Jul 2026

Developer's stated date

Q4 2027

IRTH via Bayut, 13 Feb 2026

Portal estimate

31 Dec 2027

Property Finder, accessed 11 Oct 2026

Rove Home Dubai Marina handover date: the latest position

The Dubai Land Department (DLD) project register gives Rove Home Dubai Marina a registered completion date of 31 March 2028. IRTH Development, which builds the tower with Rove Hotels, gave an anticipated handover of Q4 2027 in February 2026, and Property Finder lists 31 December 2027. Full project details are on the Rove Home Dubai Marina page.

The latest DLD inspection, on 6 July 2026, recorded 7.8% progress. The tower needs about 92 more points of progress in roughly 21 months to meet the registered date. The register lists 682 units, while IRTH’s February 2026 profile gives 679 apartments.

Rove Home Dubai Marina handover date by building

Rove Home Dubai Marina is one tower, DLD project number 3393.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Rove Home Dubai Marina (682 units) 7.8% (6 Jul 2026) 31 Mar 2028 Q4 2027 (IRTH via Bayut); 31 Dec 2027 (Property Finder)

How the Rove Home Dubai Marina handover date has changed

  • 8 November 2024: first DLD inspection, at 0%.
  • 1 December 2024: sales launch and construction start (Property Finder, DLD register), with Q4 2027 given as the handover quarter.
  • 20 April 2025: 0.14%.
  • 30 July 2025: 2.92%.
  • 3 December 2025: 7.14%.
  • 13 February 2026: IRTH’s developer profile on Bayut gives an anticipated handover of Q4 2027.
  • 23 March 2026: 7.47%.
  • 6 July 2026: 7.8%, with the register showing 31 March 2028.
  • October 2026: the register still shows 31 March 2028 (Continental Club, updated 9 October 2026), while Property Finder and Metropolitan keep Q4 2027.

The marketing date has not changed since launch. The registered date is one quarter later. Continental Club’s average pace for the project is 0.44% a month, well below what either date requires.

What the Rove Home Dubai Marina handover date means for payments

The plan was 10% on booking, 40% during construction in two instalments and 50% on handover (Property Finder and Continental Club). Half of the price therefore falls due when the building is handed over. If completion moves from Q4 2027 to the registered 31 March 2028 or later, that 50% payment moves with it. The developer stock is sold out, so buyers today purchase on resale and take over whatever remains of the original seller’s plan.

What to check before relying on the Rove Home Dubai Marina date

  1. Which date the SPA uses. Contracts signed at launch may show Q4 2027, while the register shows 31 March 2028.
  2. The grace period in the SPA. It sets how long the developer can run past the contract date before buyer remedies apply.
  3. A newer DLD inspection. A reading after 6 July 2026 will show whether the 2026 slowdown has continued.
  4. When rental income can start. Units are sold furnished, but no rent is possible until the building is completed and the unit handed over.

Questions buyers also ask

What is the Rove Home Dubai Marina completion date?

The DLD register gives 31 March 2028 (Continental Club, registry updated 9 October 2026). Property Finder lists an expected completion of 31 December 2027.

Is Rove Home Dubai Marina finished?

No. The DLD inspection on 6 July 2026 recorded 7.8% progress, up from 7.47% on 23 March 2026.

Has the Rove Home Dubai Marina handover date been delayed?

The marketing date has stayed at Q4 2027 since launch in December 2024, but the DLD register holds a later date, 31 March 2028. Progress slowed in 2026, from 7.14% in December 2025 to 7.8% in July 2026.

When will Rove Home Dubai Marina be ready to move in?

Not before the building is completed and handed over. The registered completion date is 31 March 2028, and furnished units are then handed over in line with each SPA.

Sources