Handover date

When was Rosewater at Creek Beach handed over?

Updated 6 October 2026 Rosewater at Creek Beach

Short answer

Rosewater at Creek Beach was handed over in 2025. The Dubai Land Department (DLD) project record gives a handover date of 1 June 2025, after the last DLD inspection recorded the project 100% complete on 7 November 2024. Building 1, Building 2 and Building 3 are one registration, project 2193, so Building 2 has the same date. The register also holds an anticipated completion date of 31 March 2023, which predates the 100% inspection by more than a year.

Handover date (DLD project record)

1 Jun 2025

DLD project 2193, via Dubricks

Construction progress

100%

DLD inspection, 7 Nov 2024, via Continental Club

Anticipated completion date (DLD)

31 Mar 2023

DLD register, via Continental Club and Dubricks

Date given at launch

Q2 2025

Property Finder; Emaar payment plan, via Mitchells

Rosewater at Creek Beach handover date: the latest position

Rosewater at Creek Beach is finished and handed over. The Dubai Land Department (DLD) project record gives a handover date of 1 June 2025, and the last DLD site inspection recorded the project 100% complete on 7 November 2024. Prices, sizes and rents are on the Rosewater at Creek Beach page.

Emaar launched Rosewater in October 2019 with a Q2 2025 handover, so it was delivered on its launch date. By August 2025, Building 2 apartments were advertised as ready to move in, and ready resales have been registered in all three buildings in 2026.

Rosewater at Creek Beach handover date by building

Rosewater is one DLD registration, project 2193, with three buildings and 211 homes. The buildings share one set of dates.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Rosewater at Creek Beach Building 1 (G+M+10) 100%, 7 Nov 2024 31 Mar 2023 (anticipated) Handover 1 Jun 2025 (DLD record); Q2 2025 (Property Finder)
Rosewater at Creek Beach Building 2 (G+M+11) 100%, 7 Nov 2024 31 Mar 2023 (anticipated) Handover 1 Jun 2025 (DLD record); Q2 2025 (Property Finder)
Rosewater at Creek Beach Building 3 (G+M+7) 100%, 7 Nov 2024 31 Mar 2023 (anticipated) Handover 1 Jun 2025 (DLD record); Q2 2025 (Property Finder)

Floor counts and the inspection date are from the DLD register via Continental Club. Building 2 is the tallest of the three, with 84 of the 211 homes on Continental Club’s breakdown.

How the Rosewater at Creek Beach handover date has changed

The developer’s date held from launch to handover. The register’s earlier 2023 date did not.

Date What happened Source
18 Oct 2019 Launch; DLD registration follows on 28 October 2019. DLD record, via Dubricks
Launch Handover set for Q2 2025, with 30% due on completion, estimated June 2025. Property Finder; Emaar plan, via Mitchells
1 Apr 2020 Construction starts. DLD register
31 Mar 2023 Anticipated completion date on the register passes. DLD register
7 Nov 2024 DLD inspection records 100%. DLD, via Continental Club
1 Jun 2025 Handover date on the DLD project record. DLD record, via Dubricks
Aug 2025 Building 2 apartments listed as ready to move in. Property Finder
Jan to Apr 2026 Ready resales registered in Building 2. DXBOffPlan, DLD data

Sources disagree on when building work ended. Propsearch says the project was completed in March 2023, in line with the register’s anticipated date, while DXBinteract dates completion to November 2024, the month of the 100% inspection.

What the Rosewater at Creek Beach handover date meant for payments

Rosewater was sold on 10% at booking, 60% during construction and 30% on handover (Property Finder; Habico Properties). The 30% balance therefore fell due around the June 2025 handover. On a 1 bedroom at the AED 1 million launch price recorded by Propsearch, that was AED 300,000. No post-handover instalments were published, so the handover payment closed the developer plan.

What to check when buying a resale unit at Rosewater at Creek Beach

  1. The building name on the title deed. Listings use Building 1, 2 and 3, and the DLD project name is Creek Beach Rosewater, so checks against DLD records need the building as well as the unit number.
  2. That the 30% handover payment was settled. A seller who completed handover should hold a title deed rather than an Oqood.
  3. The start date of service charges for the unit, which follows the 2025 handover rather than the 2023 date on the register.
  4. Recent sales in the same building. In Building 2, 2 bedroom resales between January and April 2026 ranged from AED 2.38 million to AED 3.23 million.

Questions buyers also ask

When was Rosewater at Creek Beach Building 2 handed over?

With the other two buildings. Building 2 is part of DLD project 2193, which has a handover date of 1 June 2025 and was 100% complete at the DLD inspection of 7 November 2024. Ready resales in Building 2 were registered from January 2026 (DXBOffPlan).

What is the Rosewater building 2 handover date?

1 June 2025 on the DLD project record, the same as Building 1 and Building 3. Emaar's payment plan had estimated the final 30% at 100% completion in June 2025 (Mitchells).

Was Rosewater at Creek Beach delayed?

Not against Emaar's launch date of Q2 2025, which it met. The 100% inspection came on 7 November 2024, after the 31 March 2023 anticipated completion date on the DLD register, and sources disagree on whether building work ended in March 2023 (Propsearch) or November 2024 (DXBinteract).

When did Rosewater at Creek Beach launch?

On 18 October 2019, with DLD registration on 28 October 2019 and construction starting on 1 April 2020 (DLD project record, via Dubricks).

Sources

  1. Continental Club, Rosewater (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 4 Oct 2026
  2. Mitchell's, Rosewater project brief (Emaar payment plan) (opens in a new tab)mitchellscommercialrealty.com · accessed 6 Oct 2026
  3. DXBinteract, Creek Beach Rosewater (opens in a new tab)dxbinteract.com · accessed 6 Oct 2026