When is the Samana Rome handover date?
Short answer
Samana Rome has a registered completion date of 31 December 2027 in the DLD project register, and Samana lists a Q4 2027 handover. The DLD inspection on 16 September 2026 recorded the building 38.71% complete. The date has not moved since sales opened in January 2025, but holding it needs about 4 points of progress a month, faster than the pace in mid 2026.
Registered completion date (DLD)
31 Dec 2027
DLD project register via Continental Club, accessed 11 Oct 2026
Latest construction progress
38.71%
DLD inspection, 16 Sep 2026
Developer's stated date
Q4 2027
Samana via Property Finder and Bayut, accessed 11 Oct 2026
Rome 2 By SD, registered completion
30 Jun 2027
32.85% built, 16 Sep 2026, DLD via Continental Club
Samana Rome handover date: the latest position
Samana Rome has a registered completion date of 31 December 2027 in the DLD project register, and Samana’s handover date on Property Finder and Bayut is Q4 2027. Prices, sizes and the payment plan are on the Samana Rome page.
The DLD inspection on 16 September 2026 recorded the building 38.71% complete. With about 15 months left to the registered date, the remaining 61.29 points need close to 4 points a month. Between the June and September 2026 inspections the building gained 9.68 points, or a little under 3 points a month.
Samana Rome handover date by building
The register lists Samana Rome as “Rome By Sd” in Majan (Wadi Al Safa 3). A second Samana building of the same size, Rome 2 By Sd, sits in the same district with an earlier date.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Rome By Sd, Samana Rome (DLD 3218, 42 units) | 38.71%, 16 Sep 2026 | 31 Dec 2027 | Q4 2027 (Property Finder, Bayut) |
| Rome 2 By Sd (DLD 3329, 42 units) | 32.85%, 16 Sep 2026 | 30 Jun 2027 | Q2 2027 (developer, via Continental Club) |
Both buildings are basement, ground, five floors and roof, and both record a construction start of 1 January 2025 (DLD project register via Continental Club). Rome 2 is behind Rome on progress but registered six months earlier, so its date is the more stretched of the two.
How the Samana Rome handover date has changed
| Date | What happened | Source |
|---|---|---|
| 1 Jan 2025 | Sales open; construction start recorded; handover December 2027 | Property Finder; DLD register |
| 21 Oct 2025 | Progress reported at 9% | Property Finder |
| 4 Jun 2026 | Inspection records about 29% | DLD register via Continental Club |
| 16 Sep 2026 | Inspection records 38.71% | DLD register via Continental Club |
| 4 Oct 2026 | Registered completion date still 31 Dec 2027 | DLD register via Continental Club |
The date has held since launch. Progress roughly quadrupled between October 2025 and September 2026, but the building still needs a faster finish phase to complete by 31 December 2027.
What the Samana Rome handover date means for payments
Bayut lists a 50/50 plan: 15% down payment, 5% in month 4, 10% each in months 8, 15 and 21, and 50% on handover. Under that plan, all construction instalments fall within 21 months of booking, so buyers from January 2025 had paid 50% by late 2026, and the other half is tied to handover. On a 2 bedroom at the AED 2,167,578 DLD median, the handover payment is about AED 1.08 million. Property Finder also shows a 75/25 plan and a plan with 50% after handover, so the share due at handover depends on the SPA.
What to check before relying on the Samana Rome date
- Whether the unit is in Rome or Rome 2, since the registered dates are 31 December 2027 and 30 June 2027.
- The size of the handover payment in the SPA. Under the 50/50 plan half the price falls due at completion, which usually needs a mortgage approval ready in time.
- The next DLD inspection. Progress near 50% by the end of 2026 would keep the Q4 2027 date within reach.
Questions buyers also ask
When will Samana Rome be ready?
The registered completion date is 31 December 2027 (DLD project register via Continental Club), and Samana lists Q4 2027. The building was 38.71% complete on 16 September 2026.
What is the Samana Rome completion date?
31 December 2027 in the DLD project register, where the building is listed as Rome By Sd, DLD project 3218.
Has the Samana Rome handover date been delayed?
No. Property Finder has shown a December 2027, or Q4 2027, handover since sales opened on 1 January 2025, and the register still shows 31 December 2027.
When will Rome 2 By SD be ready?
Rome 2 By SD, a separate 42 unit Samana building in Majan (DLD project 3329), has a registered completion date of 30 June 2027 and was 32.85% complete on 16 September 2026.