When is the Rashid Yachts and Marina handover date?
Short answer
Rashid Yachts and Marina has no single handover date: each tower has its own, and the registered completion dates on the Dubai Land Department (DLD) register run from 30 November 2026 for Seascape to 30 June 2030 for Aurea. The latest DLD inspections put Seascape at 79.13% (6 May 2026) and Bayline and Avonlea at 61.31% and 63.71% (July 2026), while the towers due in 2028 to 2030 were between 0% and 18%. Seagate is complete and Sunridge was recorded 100% built on 17 March 2026.
Next registered completion date (DLD)
30 Nov 2026
Seascape, DLD register via Mitchells and Continental Club, Sep 2026
Latest construction progress, Seascape
79.13%
DLD site inspection, 6 May 2026
Last registered completion date (DLD)
30 Jun 2030
Aurea, DLD register via Mitchells, accessed 1 Oct 2026
Towers completed
2
Seagate (registered 30 Sep 2025) and Sunridge (100%, 17 Mar 2026)
Rashid Yachts and Marina handover date: the latest position
Rashid Yachts and Marina, Emaar’s waterfront community at Mina Rashid, hands over tower by tower. The registered completion dates on the Dubai Land Department (DLD) register run from 30 November 2026 for Seascape to 30 June 2030 for Aurea, and the developer and portal dates for towers without a registered date fall inside that range. Prices and the full tower list are on the Rashid Yachts and Marina page.
Two towers are finished. Seagate is listed as completed on the register, with a registered completion date of 30 September 2025, and tenancy contracts there were registered from January 2026. Sunridge, 130 homes, was recorded 100% complete on 17 March 2026, ahead of its developer handover date of Q1 2027. The next tower due is Seascape, 79.13% complete at the DLD inspection of 6 May 2026. At its January to May pace of about 2.8 points a month, the remaining 20.87 points would take until around December 2026, close to its 30 November date.
Rashid Yachts and Marina handover date by building
Towers still to hand over, in order of their published dates. Registered dates are from the DLD register; Clearpoint, Bayline, Avonlea and Ocean Point have none filed.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Seascape (395 homes) | 79.13%, 6 May 2026 | 30 Nov 2026 | Q4 2026 |
| Clearpoint (478 homes) | 45.05%, 21 Apr 2026 | Not filed | Q3 2027; 1 Jul 2027 (Property Finder) |
| Bayline (151 homes) | 61.31%, 19 Jul 2026 | Not filed | Nov 2027 (Emaar brief) |
| Avonlea (163 homes) | 63.71%, 21 Jul 2026 | Not filed | Nov 2027 (Emaar brief) |
| Ocean Point (217 homes) | 26.95%, 21 Apr 2026 | Not filed | Jun 2028 (portal); Q2 2028 (Data Habibi) |
| Ocean Star | No DLD figure found | Not found | Jul 2028 (portal) |
| Ocean Cove (233 homes) | 17.93%, 14 Apr 2026 | 31 Aug 2028 | Aug 2028 (portal) |
| Ocean Views (78 homes) | 6.18%, 21 Apr 2026 | 30 Sep 2028 | Sep 2028 (portal) |
| Porto View (115 homes) | 6.26%, 2 Jun 2026 | 31 Oct 2028 | Oct 2028 (portal) |
| Pier Point 1 (122 homes) | 8.27%, 14 May 2026 | 31 Oct 2028 | Oct 2028 (portal) |
| Marina Views (554 homes) | 7.09%, 5 May 2026 | 31 Dec 2028 | Dec 2028 (Property Finder) |
| Marina Place 1 (162 homes) | 4.23%, 3 Apr 2026 | 31 Dec 2028 | Dec 2028 (portal) |
| Sera 2 (183 homes) | 0.04%, 2 Jun 2026 | 30 Nov 2029 | Nov 2029 (portal) |
| Baystar by Vida (328 homes) | 6.30%, 16 Jun 2026 | 31 Dec 2029 | Dec 2029 (portal) |
| Aurea (172 homes) | 0.00%, 23 Sep 2025 | 30 Jun 2030 | Jun 2030 (portal) |
Sera 1, Fior 1, Marina Place 2 and Pier Point 2 are separate registrations not shown above; Esto’s register summary put Sera 1 at 0%, Marina Place 2 at 2% and Pier Point 2 at 8% (accessed 1 October 2026).
Completed: Seagate (302 homes, 100% on 14 April 2025, registered completion 30 September 2025) and Sunridge (130 homes, 100% on 17 March 2026).
Seashore, also sold as Seashore at Mina Rashid, is not a separate project on the register. Propsearch lists it as the 15 storey building of Seagate, alongside Seagate Buildings 2, 3 and 4, so Seashore Residences buyers have Seagate’s dates: 100% on 14 April 2025 and a registered completion date of 30 September 2025. Seashore was marketed from 2019 with handover in Q3 or Q4 2022 (Edge Realty; Gold Pillars), and Propsearch records Seagate’s estimated handover moving from September 2022 to September 2025.
How the Rashid Yachts and Marina handover dates have changed
The registered and published dates have held so far. What has changed is the spread, as each new release added a later date.
| Date | What happened | Source |
|---|---|---|
| May 2019 | First Mina Rashid homes offered, in the project later relaunched as Seagate; Seashore sold with handover due in 2022. | Propsearch; Gold Pillars |
| 1 Sep 2019 | Seagate construction start. | DLD register |
| 13 Apr 2023 | Seascape start, registered completion 30 November 2026. | DLD register |
| Sep to Nov 2023 | Sunridge (Q1 2027) and Clearpoint (Q3 2027) start. | DLD register, via Continental Club |
| 29 Feb 2024 | Bayline and Avonlea start, Emaar date November 2027. | DLD register; Emaar brief |
| Dec 2024 to Mar 2026 | Later towers registered with completion dates from August 2028 to June 2030. | DLD register, via Mitchells |
| 14 Apr 2025 | Seagate, including Seashore, 100%; registered completion 30 September 2025, three years after the 2022 launch date. | DLD register; Propsearch |
| 17 Mar 2026 | Sunridge recorded 100% complete. | DLD register |
| 1 May 2024 to 6 May 2026 | Seascape rises from 8.96% to 49.78% (June 2025), 69.45% (January 2026) and 79.13%. | DLD inspections, via Tohid Fetrat and Continental Club |
| 1 Oct 2026 | Every registered completion date on file matches the portal date for that tower. | DLD register, via Mitchells |
What the Rashid Yachts and Marina handover date means for payments
The share due at handover varies by tower. Marina Views is on 10% at booking, 70% during construction and 20% on handover (Property Finder). Bayline and Avonlea run ten 10% instalments, the later six tied to construction milestones, with the final 10% due on 100% completion, scheduled for November 2027. Data Habibi lists Clearpoint at 10%, 80% and 10%. Seashore, now complete, was sold on 5% down, 55% during construction and 40% on handover (Gold Pillars), so the larger final payment waited for the 2025 completion. On a unit at the AED 2.11 million starting price for towers still on sale, a 20% handover payment would be AED 422,000.
What to check before relying on the Rashid Yachts and Marina date
- Which registration your unit sits in. Marina Place, Pier Point and Sera each have two registrations with separate dates and progress.
- The SPA date for Clearpoint, Bayline, Avonlea and Ocean Point buyers, since these towers have no registered completion date to compare against.
- Seascape’s next DLD inspection, since its May 2026 pace put completion close to the 30 November 2026 date.
- For Sunridge owners, the handover notice date, since the building is finished on the register but the developer date is Q1 2027.
Questions buyers also ask
Which Rashid Yachts and Marina tower hands over next?
Seascape, with a registered completion date of 30 November 2026. The DLD site inspection of 6 May 2026 recorded it 79.13% complete, up from 69.45% on 19 January 2026 (Continental Club, registry updated 29 Sep 2026).
Is Rashid Yachts and Marina finished?
Only in part. Seagate is listed as completed on the DLD register, and Sunridge was recorded 100% complete on 17 March 2026. The other tracked towers were between 0% and 79.13% complete at their latest DLD inspections between April and July 2026.
When will Sunridge at Rashid Yachts and Marina be ready?
The building is finished on the DLD register, at 100% on 17 March 2026 (Real Estate Club Dubai, checked 28 Sep 2026). The developer's handover date is Q1 2027 and portals show February 2027, so owners should check when Emaar issues the handover notice.
Have the Rashid Yachts and Marina handover dates been delayed?
No revised date has been published for any tower, and every registered completion date checked on 1 October 2026 matches the portal date for that tower. Seascape's 30 November 2026 date is the one to watch, since it needed about 21 more points of progress after its May 2026 inspection.
When was Seashore Residences at Mina Rashid handed over?
Seashore is the 15 storey building of the Seagate registration, DLD project 2163, so it shares Seagate's dates: 100% at the DLD inspection of 14 April 2025 and a registered completion date of 30 September 2025 (Propsearch; DLD register via Mitchells). It was sold from 2019 with completion due in late 2022, a date Propsearch records as revised to September 2025.
How much is due at handover at Rashid Yachts and Marina?
It depends on the tower. Marina Views is on a 10/70/20 plan with 20% at handover (Property Finder). Bayline and Avonlea put the final 10% on 100% completion, and Clearpoint is listed at 10/80/10.