Handover date

When is the Q Gardens Aliya handover date?

Updated 11 October 2026 Q Gardens Aliya

Short answer

The registered completion date for Q Gardens Aliya is 30 June 2027 on the Dubai Land Department (DLD) project register. The last DLD inspection, on 5 July 2026, put construction at 7.7%, up only 0.06 points since December 2025. Property Finder already shows a later Q4 2027 handover, and at this pace the registered date is hard to meet.

Registered completion date (DLD)

30 Jun 2027

DLD register via Continental Club, updated 7 Oct 2026

Latest construction progress

7.7%

DLD inspection, 5 Jul 2026

Developer's stated date

Q2 2027

Developer supplied, via Continental Club

Portal estimate

Q4 2027

Property Finder, accessed 11 Oct 2026

Q Gardens Aliya handover date: the latest position

The Dubai Land Department (DLD) project register gives Q Gardens Aliya, the AYS Developers building in Jumeirah Village Circle (JVC) District 12, a registered completion date of 30 June 2027. Continental Club, which republishes the register, records the developer’s own handover as Q2 2027. Full project details are on the Q Gardens Aliya page.

The latest DLD inspection, on 5 July 2026, recorded 7.7% progress. That is almost the same as the 7.64% recorded on 23 December 2025. Portals do not agree on the date: Property Finder shows Q4 2027, and fäm Properties still shows 30 November 2026.

Q Gardens Aliya handover date by building

Q Gardens Aliya is one building with 278 units on the DLD register (project number 3290).

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Q Gardens Aliya (278 units, studios, 1 bedrooms and shops) 7.7% (5 Jul 2026) 30 Jun 2027 Q2 2027 (developer, via Continental Club); Q4 2027 (Property Finder)

How the Q Gardens Aliya handover date has changed

  • 18 September 2024: first DLD inspection, at 0%.
  • 1 October 2024: sales and construction start, per Property Finder and the DLD register. fäm Properties gives a 1 November 2024 launch and a 30 November 2026 completion date.
  • 15 May 2025: DLD inspection at 6.59%.
  • 23 December 2025: DLD inspection at 7.64%.
  • 5 July 2026: DLD inspection at 7.7%, with the registered completion date at 30 June 2027.
  • October 2026: the register still shows 30 June 2027 (Continental Club, updated 7 October 2026). Property Finder and Metropolitan show Q4 2027.

The pace since mid 2025 is the main issue. At 7.7% in July 2026, the building would need more than 92 points of progress in less than a year. Continental Club puts the median pace for completed Dubai projects at 2.48% a month.

What the Q Gardens Aliya handover date means for payments

On the plan listed by Continental Club, 20% is paid on booking, 45% during construction and 35% on handover. Under that plan, the handover date decides when the largest single payment falls due. Property Finder also shows a plan with 40% during construction, 1% on handover and 39% spread after handover, which moves most of the balance past the handover date. fäm Properties shows 10/45/35. Buyers on resale take over whatever schedule the original SPA set.

What to check before relying on the Q Gardens Aliya date

  1. The completion date and grace period in the SPA. Marketing dates range from November 2026 to Q4 2027, and the contract date is the one that applies.
  2. A DLD inspection after 5 July 2026. The DLD project status service shows whether progress has moved past the 7.7% recorded then.
  3. How construction instalments are linked. If the 45% construction share is tied to progress milestones, a pause in work also delays those payments.
  4. The 35% handover payment. Buyers planning to fund it with a mortgage need the bank’s valuation timed to the actual handover, not the registered date.

Questions buyers also ask

What is the Q Gardens Aliya completion date?

The DLD register gives 30 June 2027 as the completion date (Continental Club, registry updated 7 October 2026). Property Finder shows Q4 2027 and fäm Properties an older 30 November 2026.

Is Q Gardens Aliya finished?

No. The DLD inspection on 5 July 2026 recorded 7.7% progress. The previous inspection, on 23 December 2025, recorded 7.64%.

Has the Q Gardens Aliya handover date been delayed?

The dates in circulation have moved later. fäm Properties still shows 30 November 2026, the register shows 30 June 2027 and Property Finder shows Q4 2027. Progress has barely changed since December 2025, so a further change to the registered date is possible.

How much is due at the Q Gardens Aliya handover?

Continental Club lists 35% due on handover, after 20% on booking and 45% during construction. Property Finder also shows a plan with 1% on handover and 39% after handover. The SPA sets the actual amount.