Handover date

When is the Pelagos by IGO handover date?

Updated 11 October 2026 Pelagos by IGO

Short answer

Pelagos by IGO had a registered completion date of 31 March 2026, the same Q1 2026 handover IGO promised at launch, and that date has passed. The last DLD inspection, on 30 April 2026, recorded the tower 84.23% complete, and the register still showed it under construction in late September 2026. No revised date has been published; at its past year's pace, Continental Club estimates completion around January 2027.

Registered completion date (DLD)

31 Mar 2026 (passed)

DLD register via Continental Club

Latest construction progress

84.23%

DLD inspection, 30 Apr 2026

Developer's stated date

Q1 2026

IGO at launch, 12 Nov 2024

Estimate at current pace

Around Jan 2027

Continental Club calculation, not a developer date

Pelagos by IGO handover date: the latest position

Pelagos by IGO was registered with the Dubai Land Department (DLD) for completion on 31 March 2026, and IGO promised a Q1 2026 handover when it launched the tower in November 2024. Both dates have passed. Full project details are on the Pelagos by IGO page.

The latest DLD inspection, on 30 April 2026, recorded the tower 84.23% complete. The register still showed Pelagos as under construction on 27 September 2026, with the completion date unchanged. IGO had not published a new handover date by 11 October 2026.

Pelagos by IGO handover date by building

Pelagos is a single 296 unit tower in Dubai Marina, registered as DLD project 3246 under the name PELaGOS By IGO.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Pelagos by IGO 84.23% (30 Apr 2026) 31 Mar 2026 (passed) Q1 2026 (IGO at launch); Q3 2026 (sales site, undated)
DLD inspection Progress
18 Mar 2025 69.88%
19 Jan 2026 About 80.4%
30 Apr 2026 84.23%

Sources: DLD register via Continental Club. The January 2026 figure is derived from Continental Club’s reported rise of 3.81 points between 19 January and 30 April 2026.

How the Pelagos by IGO handover date has changed

Date What happened Source
12 Nov 2024 Launch at Bluewaters; completion scheduled for Q1 2026 IGO via Dubai Property Guide
1 Dec 2024 Registered construction start DLD register
18 Mar 2025 69.88% complete DLD register via Continental Club
31 Mar 2026 Registered completion date passes DLD register
30 Apr 2026 84.23% complete DLD register via Continental Club
4 May 2026 IGO says Pelagos is “taking its final shape” IGO, LinkedIn
7 Oct 2026 Register still shows 31 Mar 2026 and 84.23% Continental Club

Progress slowed after the first year. Between 18 March 2025 and 30 April 2026, the tower added about 14 points. Continental Club, using the past year of inspections, puts the pace at 1.84 points a month and estimates completion around 15 January 2027. That is an estimate, not a date from IGO or the DLD.

What the Pelagos by IGO handover date means for payments

Buyers on the 50/50 plan without post-handover payments owe the second half on handover or 100% completion, so that payment waits for the building to finish. Buyers on the post-handover version pay part of the second half on handover and the rest every three months for 18 months afterwards, so their whole schedule starts later if handover is late (IGO sales presentation). The fixed instalments dated 1 March, 1 July and 1 November 2025 were not linked to progress and have already fallen due.

What to check before relying on the Pelagos by IGO date

  1. The completion date and grace period in the SPA. With 31 March 2026 passed, the grace period sets what remedies a buyer has.
  2. A building completion certificate. Handover follows the certificate, and none had been reported by 11 October 2026.
  3. The next DLD inspection. No inspection after 30 April 2026 had been published by 7 October 2026, so the register may lag the site.

Questions buyers also ask

Is Pelagos by IGO finished?

Not as of the last DLD record. The tower was 84.23% complete at the inspection on 30 April 2026, and the register still listed it as under construction on 27 September 2026 (Mitchells).

Has the Pelagos by IGO handover date been delayed?

Yes, in practice. The registered completion date of 31 March 2026 and IGO's Q1 2026 launch promise have both passed. The register had not been updated with a new date by 7 October 2026.

When will Pelagos by IGO be completed?

No new official date has been published. Continental Club estimates 100% around 15 January 2027 at the pace of the past year, and the project's sales site shows Q3 2026. Neither is a DLD or confirmed IGO date.

What is the Pelagos by IGO completion date in the DLD register?

31 March 2026, for DLD project 3246, registered under Digo Real Estate Development, a branch of Invest Group Overseas.

Sources

  1. DLD project register via Continental Club, Pelagos by IGO (opens in a new tab)continentalclub.ae · inspection 30 Apr 2026, registry updated 7 Oct 2026
  2. Mitchells, PELaGOS By IGO DLD registry and registered sales (opens in a new tab)mitchellscommercialrealty.com · register as at 27 Sep 2026
  3. Dubai Handover, PELaGOS By IGO (opens in a new tab)dubaihandover.com · snapshot 10 Oct 2026
  4. Pelagos by IGO sales site (opens in a new tab)pelagos-by-igo.ae · accessed 11 Oct 2026
Request a Unit Review