Handover date

When is the One River Point handover date?

Updated 11 October 2026 One River Point

Short answer

One River Point has a registered completion date of 9 June 2027, and Ellington gives Q2 2027. The latest DLD inspection, on 21 July 2026, recorded 35.43% complete. At the past year's pace of 1.74 points a month, Continental Club projects completion in August 2029, and some portals already show Q3 2027.

Registered completion date (DLD)

9 Jun 2027

DLD project register via Continental Club

Latest construction progress

35.43%

DLD inspection, 21 Jul 2026

Developer's stated date

Q2 2027

Ellington, 3 Nov 2023 and project brief

Completion at the past year's pace

Aug 2029

Continental Club estimate, not a developer date

One River Point handover date: the latest position

The DLD project register holds a registered completion date of 9 June 2027 for One River Point. Ellington Properties gives an anticipated completion in the second quarter of 2027, the date it has used since launch. Prices, sizes and the payment plan are on the One River Point page.

The latest DLD inspection, on 21 July 2026, recorded 35.43% complete. Ellington has not revised its date, but portals have started to move: JRE and Luxury Located show Q3 2027.

One River Point handover date by building

One River Point is one tower on the Dubai Water Canal, DLD project 2929, with 298 registered units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
One River Point (298 units) 35.43%, 21 Jul 2026 9 Jun 2027 Q2 2027 (Ellington; Propsearch); Q3 2027 (JRE; Luxury Located)

How the One River Point handover date has changed

Date What happened Source
24 Oct 2023 Construction start registered DLD register
3 Nov 2023 Launch by Dutco and Ellington; completion due Q2 2027 Ellington Properties
12 Jan 2024 First DLD inspection records 0% DLD register
6 Feb 2026 Programme one year in; tower at level 8 BSBG
27 Mar 2026 DLD inspection records 28.79% DLD register
21 Jul 2026 DLD inspection records 35.43% DLD register
Sep 2026 Some portals show Q3 2027 Luxury Located, JRE

Between March and July 2026, the tower gained 6.64 points, about 1.7 points a month. To finish by 9 June 2027, the remaining 64.57 points would need about 6 points a month. Continental Club, using a year of inspections, puts completion at 22 August 2029 if the pace does not change. That estimate is a calculation, not a date given by Ellington.

What the One River Point handover date means for payments

Ellington’s plan of 30 October 2023 puts 20% on booking and 30% on four dated instalments within 240 days of reservation, so buyers from 2023 and 2024 have paid half the price. Four more instalments of 5% follow at 30%, 40%, 50% and 60% construction, and the last 30% is due on completion (Mitchells). The 50% and 60% stages move with the build, and so does the completion payment. On a 1 bedroom at the DLD median of AED 2,797,828, that final payment is about AED 839,000 (Continental Club, register updated 6 October 2026).

What to check before relying on the One River Point date

  1. The completion date and grace period in the SPA, compared with 9 June 2027 in the register.
  2. The next DLD inspections, measured against the roughly 6 points a month the registered date needs.
  3. Whether Ellington issues a revised date, as some portals already show Q3 2027.
  4. The timing of a mortgage for the 30% completion payment, since a later completion can outlast an approval.

Questions buyers also ask

When will One River Point be completed?

The registered completion date in the DLD project register is 9 June 2027, and Ellington gives Q2 2027. The tower was 35.43% complete on 21 July 2026.

Has the One River Point handover date been delayed?

Not officially. Ellington announced Q2 2027 at launch on 3 November 2023 and has not changed it. Some portals, including JRE and Luxury Located, now show Q3 2027, and Continental Club's estimate at the recorded pace is 22 August 2029.

How far along is One River Point?

35.43% at the DLD inspection of 21 July 2026, up from 28.79% on 27 March 2026. BSBG reported the tower at level 8 in February 2026.

Is One River Point finished?

No. It was 35.43% complete at the July 2026 DLD inspection.