When is the One Park Square by Iman handover date?
Short answer
One Park Square by Iman has a registered completion date of 30 June 2028, matching Iman Developers' Q2 2028 target. The latest DLD inspection, on 22 September 2026, recorded 20.05% complete. Meeting the date needs close to 4 points of progress a month from here, against about 1 point a month on average since January 2025.
Registered completion date (DLD)
30 Jun 2028
DLD project register via Continental Club and Mitchells
Latest construction progress
20.05%
DLD inspection, 22 Sep 2026
Developer's stated date
Q2 2028
Iman Developers
Date given at launch
Q2 2028
Propsearch, Nov 2024
One Park Square by Iman handover date: the latest position
The DLD project register holds a registered completion date of 30 June 2028 for One Park Square by Iman, listed there as One Park Square By Iman. Iman Developers gives the second quarter of 2028, as do Propsearch and Property Finder. Prices, home types and the payment plan are on the One Park Square by Iman page.
The latest DLD inspection, on 22 September 2026, recorded 20.05% complete. The date has not changed since launch, but about 80% of the work remains with 21 months left.
One Park Square by Iman handover date by building
The project is one tower in JVC District 11, DLD project 3366, with 269 registered units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| One Park Square by Iman (269 units) | 20.05%, 22 Sep 2026 | 30 Jun 2028 | Q2 2028 (Iman Developers; Propsearch; Property Finder) |
How the One Park Square by Iman handover date has changed
| Date | What happened | Source |
|---|---|---|
| Oct 2024 | Fact sheet gives completion in Q2 2028 | Iman fact sheet |
| Nov 2024 | Launch; all units sold within four hours; Q2 2028 | Propsearch, Iman Developers |
| 1 Jan 2025 | Construction start registered | DLD register |
| Sep 2026 | Iman posts a construction update | Iman Developers |
| 22 Sep 2026 | DLD inspection records 20.05% | DLD register |
| Oct 2026 | Register holds completion on 30 Jun 2028 | DLD register via Mitchells |
The date has held at Q2 2028 since launch. Progress has averaged about 1 point a month across the 21 months since the registered start. To finish by 30 June 2028, the remaining 79.95 points would need close to 4 points a month. This is a calculation from the register, not a date given by Iman.
What the One Park Square by Iman handover date means for payments
Under Iman’s launch plan, buyers pay 20% on booking, 10% within 90 days, then 10% each at 20%, 40% and 60% construction completion, and 40% on completion (Iman fact sheet). At 20.05% complete in September 2026, the 20% milestone had just been reached. The 40% and 60% instalments follow construction, so they move with the pace on site. The final 40% is due on completion. On a unit at the median registered price of AED 1.12 million, that is about AED 448,000 (Mitchells, 5 October 2026). There is no post-handover plan.
What to check before relying on the One Park Square by Iman date
- The completion date and grace period in the SPA, compared with 30 June 2028 in the register.
- The next DLD inspections, measured against the roughly 4 points a month the registered date needs.
- Which construction-linked instalments have been called, since they follow construction progress rather than calendar dates.
Questions buyers also ask
When will One Park Square by Iman be completed?
The registered completion date in the DLD project register is 30 June 2028, and Iman Developers gives Q2 2028. The tower was 20.05% complete on 22 September 2026.
What is the One Park Square completion date?
30 June 2028 in the DLD register (Mitchells, register as at 4 Oct 2026). Iman, Propsearch and Property Finder all give Q2 2028.
Has the One Park Square handover date been delayed?
No. Iman gave Q2 2028 at the November 2024 launch, and the date has not moved. The pace of construction is the open question.
When did construction start at One Park Square?
The DLD register records 1 January 2025. Iman announced the groundbreaking after the launch sell-out, and posted a construction update in September 2026.