Handover date

When is the One by Preston handover date?

Updated 11 October 2026 One by Preston

Short answer

The registered completion date for One by Preston in the DLD project register is 31 December 2027, and Preston Development says completion is scheduled for December 2027. The last published DLD inspection, dated 16 December 2024, recorded 0% progress, and no newer figure has been published. An older Property Finder date of 1 September 2026 has passed, so the December 2027 date is the current one.

Registered completion date (DLD)

31 Dec 2027

DLD register via Continental Club, updated 10 Oct 2026

Last published construction progress

0%

DLD inspection, 16 Dec 2024

Developer's stated date

December 2027

Preston Development, 8 Jul 2026

Earlier portal date

1 Sep 2026

Property Finder, accessed 11 Oct 2026

One by Preston handover date: the latest position

The Dubai Land Department (DLD) project register lists 31 December 2027 as the registered completion date for One by Preston (DLD register via Continental Club, updated 10 October 2026). Preston Development gave the same month at its official launch in July 2026 (Middle East Construction News, 8 July 2026). Homes, prices and plans are on the project page: One by Preston.

There is little construction data. The only published DLD inspection, dated 16 December 2024, recorded 0% progress, and the DLD project record shows a planned construction start of February 2026 (Data Habibi).

One by Preston handover date by building

One by Preston is one six storey building with 56 units in Dubai South Residential District.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
One by Preston (56 units) 0% (16 Dec 2024) 31 Dec 2027 December 2027 (Preston); Q4 2027 (Ezre, JRE); 1 Sep 2026 (Property Finder, older listing)

How the One by Preston handover date has changed

  • 1 November 2024: bookings start, according to Property Finder, which shows an expected completion of 1 September 2026.
  • 16 December 2024: DLD inspection at 0%.
  • February 2026: planned construction start in the DLD project record (Data Habibi).
  • July 2026: Preston announces approval of the escrow account and the official launch, with completion scheduled for December 2027. It later says 50% of units sold within days and SPAs were issued (Zawya).
  • October 2026: the DLD register shows a registered completion date of 31 December 2027.

The move from a September 2026 portal date to December 2027 is a gap of about 15 months.

What the One by Preston handover date means for payments

Preston’s July 2026 plan puts 70% of the price into the construction period and 30% over 30 months after handover. On a AED 999,000 2 bedroom, that is about AED 299,700 after handover, or about AED 9,990 a month. Portal listings show a 20/24/6/50 plan instead, with 6% due on handover and 50% over 50 or 120 months afterwards (OffPlanIndex; Ezre). On Ezre’s studio price of AED 729,786, the portal plan means about AED 43,800 on handover and about AED 3,000 a month for 120 months afterwards. Under either version, post-handover instalments start only once the building is handed over, so the completion date also sets when they begin.

What to check before relying on the One by Preston date

  1. The completion date and grace period in the SPA, since Property Finder still carries an older date of 1 September 2026.
  2. A current DLD inspection reading, because the last published figure is 0% from December 2024.
  3. Which payment plan the SPA uses, since the 70/30 and 20/24/6/50 plans put very different amounts at handover.
  4. The escrow account named in the SPA, which Data Habibi lists with the National Bank of Fujairah, since payments before handover are made into it.

Questions buyers also ask

When will One by Preston be ready?

The registered completion date is 31 December 2027, and Preston Development says completion is scheduled for December 2027 (Middle East Construction News, 8 Jul 2026).

What is the One by Preston completion date?

31 December 2027 in the DLD register (via Continental Club). Ezre and JRE list Q4 2027.

Has the One by Preston handover date been delayed?

Property Finder still shows an expected completion of 1 September 2026, with bookings from 1 November 2024. The developer's date at the official launch in July 2026 was December 2027, about 15 months later.

Has construction started at One by Preston?

The DLD project record shows a planned construction start of February 2026 (Data Habibi). The only published DLD inspection, dated 16 December 2024, recorded 0%, and no later progress figure had been published by 11 October 2026.

Sources

  1. Ezre, One By Preston (opens in a new tab)ezre.ae · accessed 11 Oct 2026
  2. JRE, One By Preston (opens in a new tab)jre.ae · accessed 11 Oct 2026
  3. OffPlanIndex, One By Preston (opens in a new tab)offplanindex.ae · accessed 11 Oct 2026