When is the One by Binghatti handover date?
Short answer
Binghatti gives Q4 2026 for One by Binghatti, after an original promise of Q2 2026. The DLD register still holds a registered completion date of 30 May 2026, which has passed. The tower was 50.21% complete at the DLD inspection on 14 May 2026, up from 38.68% in December 2025, so about half the work remained seven months before the end of 2026.
Registered completion date (DLD)
30 May 2026
DLD register, project 3107; passed
Latest construction progress
50.21%
DLD inspection, 14 May 2026
Developer's stated date
Q4 2026
Binghatti, accessed 11 Oct 2026
Change since launch
Q2 2026 to Q4 2026
Data Habibi: a seven month postponement
One by Binghatti handover date: the latest position
Binghatti says One by Binghatti is expected to be completed by Q4 2026. The DLD register still holds the original registered completion date of 30 May 2026 for the Business Bay tower, covered in full on the One by Binghatti page.
The DLD inspection on 14 May 2026, two weeks before that date, recorded 50.21% complete. No newer inspection had been published by 4 October 2026. A passed date on the register means the record has not been updated, not that the tower is finished.
One by Binghatti handover date by building
One by Binghatti is a single tower under one DLD project number.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| One by Binghatti (DLD project 3107, 755 units) | 50.21%, 14 May 2026 | 30 May 2026 | Q4 2026 (Binghatti, accessed 11 Oct 2026); Q4 2026 (Data Habibi); May 2026 (Propsearch) |
How the One by Binghatti handover date has changed
| Date | What was published | Source |
|---|---|---|
| 1 Mar 2024 | Registered construction start | DLD register via Mitchells |
| 27 May 2024 | Launch at the Bulgari Yacht Club; original promise Q2 2026 | Propsearch; Data Habibi |
| 16 Dec 2025 | 38.68% complete at DLD inspection | DLD register via Continental Club |
| 14 May 2026 | 50.21% complete at DLD inspection | DLD register via Continental Club |
| 30 May 2026 | Registered completion date passes | DLD register |
| Oct 2026 | Binghatti gives Q4 2026 | Binghatti |
Between December 2025 and May 2026 the tower gained 11.53 points, a little over 2 points a month. Binghatti has not explained the move from Q2 to Q4 2026.
To finish by 31 December 2026, the remaining 49.79 points would need to be completed in about seven and a half months from the May inspection, around 6.6 points a month. That is about three times the rate recorded between the last two inspections. Propsearch’s May 2026 estimate and the register’s 30 May 2026 date are both out of date, so Binghatti’s Q4 2026 is the only current published date.
What the One by Binghatti handover date means for payments
Binghatti’s plan puts 30% of the price on completion. On a 1 bedroom at AED 2,250,000, close to September 2026 registered prices, that is AED 675,000. On a unit bought at AED 3.2 million, as several 1 bedrooms were in February 2026, it is AED 960,000. The move from Q2 2026 to Q4 2026 or later shifts that payment, and any mortgage drawdown for it, by the same amount of time.
What to check before relying on the One by Binghatti date
- The SPA completion date and grace period, since the 30 May 2026 date on the register has passed.
- A written revised date from Binghatti, given that its page and Propsearch now disagree.
- The next DLD inspection for project 3107, to see whether progress since May supports a Q4 2026 finish.
- Mortgage approval timing for the 30% completion payment, if the date moves again.
Questions buyers also ask
Is One by Binghatti finished?
No. It was 50.21% complete at the DLD inspection on 14 May 2026, and the register lists it as under construction (Mitchells, 4 October 2026).
What is the One by Binghatti completion date?
The registered completion date on the DLD register is 30 May 2026, which has passed. Binghatti's current completion date is Q4 2026.
Has the One by Binghatti handover date been delayed?
Yes. Data Habibi records the original promise as Q2 2026 and the current target as Q4 2026, a seven month postponement. Propsearch still shows May 2026, and the DLD register has not been updated from 30 May 2026.
When did One by Binghatti launch?
Binghatti launched the tower at the Bulgari Yacht Club on 27 May 2024 (Propsearch). The registered construction start is 1 March 2024.