When is the Oasis Residences Dubai South handover date?
Short answer
Oasis Residences Dubai South has a registered completion date of 1 July 2027, while HZ Development's site shows Q1 2027 and Propsearch April 2027. The last Dubai Land Department inspection, on 16 July 2026, recorded 35.25% complete. At the March to July 2026 pace the building would reach 100% around early 2028, so the July 2027 date needs faster progress.
Registered completion date
1 Jul 2027
DLD project register via Continental Club
Latest construction progress
35.25%
DLD inspection, 16 Jul 2026
Developer's stated date
Q1 2027
HZ Development project page, accessed 11 Oct 2026
Estimate at recent pace
About early 2028
Calculation from the March to July 2026 DLD readings, not a developer date
Oasis Residences Dubai South handover date: the latest position
Oasis Residences Dubai South is registered with the Dubai Land Department (DLD) for completion on 1 July 2027. At the last DLD inspection, on 16 July 2026, the building was 35.25% complete. Prices, sizes and the payment plan are on the project page: Oasis Residences Dubai South.
HZ Development’s own project page shows Q1 2027, earlier than the register. Between March and July 2026 the building gained about 3.4 points a month. Finishing by 1 July 2027 needs about 5.6 points a month from mid-July 2026. At the recent pace, 100% would come around early 2028, about seven months after the registered date.
Oasis Residences Dubai South handover date by building
The project is a single five-storey building of 159 apartments (DLD project 3726), registered by Al Helal Al Zahaby Real Estate Development and sold as HZ Development.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Oasis Residences Dubai South (159 apartments, G + 4 + roof) | 35.25% (16 Jul 2026) | 1 Jul 2027 | Q1 2027 (HZ Development); Apr 2027 (Propsearch); 31 Mar 2027 (Takween Aldar); Jul 2027 (Property Finder) |
How the Oasis Residences Dubai South handover date has changed
| Date | Event | Source |
|---|---|---|
| 1 Jul 2025 | Construction starts and bookings open; completion registered for 1 Jul 2027 | DLD via Continental Club; Property Finder |
| 7 Aug 2025 | Project registered with DLD | DLD via dxboffplan |
| 15 Oct 2025 | Public launch with AX Capital as sales agent | Khaleej Times |
| 23 Mar 2026 | DLD inspection: about 22.3% (implied by the later gain) | DLD via Continental Club |
| 13 Apr 2026 | Propsearch estimates handover in April 2027 | Propsearch |
| 16 Jul 2026 | DLD inspection: 35.25% | DLD via Continental Club |
| 21 Sep 2026 | Latest registered sale, a 1 bedroom at AED 777,974 | DLD via Continental Club |
The registered date has not moved. Broker dates have ranged from 31 March 2027 to July 2027. The building went from start to about 22% in under nine months, then gained 13 points in the four months to July 2026.
What the Oasis Residences Dubai South handover date means for payments
Property Finder lists 10% down, 40% during construction, 10% on handover and 40% after handover, and Continental Club spreads the last 40% over 36 months. Another plan listed by brokers puts 3% on handover and 37% over 33 months (OffPlanIndex). On both, little is due at handover itself. A later completion pushes back the start of the post-handover instalments rather than a single large payment. On a 1 bedroom at the median AED 870,601, the 40% post-handover share is about AED 348,000.
What to check before relying on the Oasis Residences Dubai South date
- The completion date in the SPA, since dates given to buyers range from 31 March 2027 to 1 July 2027.
- When the post-handover instalments start. The SPA should say whether they run from handover or from a fixed date.
- The next DLD inspection. Keeping to 1 July 2027 implies about 66% by the end of 2026; the March to July pace implies about 54%.
- The plan’s handover share. It is 10% on one plan and 3% on another.
Questions buyers also ask
Is Oasis Residences Dubai South finished?
No. The DLD inspection of 16 July 2026 recorded the building 35.25% complete. Its registered completion date is 1 July 2027.
What is the Oasis Residences Dubai South completion date?
1 July 2027 on the DLD register (via Continental Club). Property Finder lists July 2027, Propsearch April 2027 and HZ Development's own page Q1 2027.
Has the Oasis Residences Dubai South handover date been delayed?
No revised date has been filed. The register has held 1 July 2027 since construction started on 1 July 2025. Earlier broker dates of March or April 2027 are now behind the register date.
Is Oasis Residences in Dubai South a single building?
Yes. The DLD register lists one building of 159 apartments, with a ground floor and four residential floors.