Handover date

When is the Nineteen Riviera Lagoon handover date?

Updated 11 October 2026 Nineteen Riviera Lagoon

Short answer

The registered completion date for Nineteen Riviera Lagoon is 12 February 2027, per the Dubai Land Department (DLD) project register, and Property Finder lists delivery in Q1 2027. The last DLD inspection, on 25 June 2026, put construction at 34.06%, up from 12.11% on 26 December 2025. Brokers quoted Q4 2026 when villas were first sold in 2024, and Dubainary now lists Q2 2027, so the date has already moved once on portals.

Registered completion date (DLD)

12 Feb 2027

DLD project register via Continental Club

Latest construction progress

34.06%

DLD inspection, 25 Jun 2026

Developer date shown on portals

Q1 2027

Property Finder, accessed 11 Oct 2026

Date quoted at launch

Q4 2026

Everhomes, prices as of 15 Jul 2024

Nineteen Riviera Lagoon handover date: the latest position

The Dubai Land Department (DLD) register gives Nineteen Riviera Lagoon a completion date of 12 February 2027. Property Finder shows the same timing as Q1 2027. More detail on the villas and prices is on the Nineteen Riviera Lagoon project page.

The last DLD inspection, on 25 June 2026, recorded 34.06% of construction complete. That leaves about two thirds of the work for the roughly eight months between that inspection and the registered date. Between 26 December 2025 and 25 June 2026, progress rose by about 22 points.

Nineteen Riviera Lagoon handover date by building

The register lists the project as one entry covering all 19 villas, described as residential development of 19 villas of ground plus two floors. Riviera’s plans add a basement with parking for 7 to 12 cars per villa.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Nineteen Riviera Lagoon, 19 villas (project 2980) 34.06% (25 Jun 2026) 12 Feb 2027 Q1 2027 (Property Finder); Q2 2027 (Dubainary)

The 19 villas fall into five types: two of type one, three of type two, five of type three, five of type four and four of type five (DLD register via Continental Club). No source gives a separate date for any villa type.

How the Nineteen Riviera Lagoon handover date has changed

Date What was recorded Source
Mar 2023 Land plot purchase registered at AED 57.1 million DLD via Mitchells
15 Jul 2024 Villas marketed with completion in Q4 2026 Everhomes
12 Aug 2024 Construction start on the DLD register DLD via Continental Club
26 Dec 2025 DLD inspection: 12.11% complete Property Finder
25 Jun 2026 DLD inspection: 34.06% complete DLD via Continental Club
Oct 2026 Registered completion 12 Feb 2027; portals show Q1 2027 or Q2 2027 DLD register, Property Finder, Dubainary

The main portals no longer show the first date of Q4 2026. The register date of 12 February 2027 is about two months later. Dubainary’s Q2 2027 is later again, and sources disagree by up to one quarter.

What the Nineteen Riviera Lagoon handover date means for payments

Property Finder and Everhomes list 10% on booking, 40% during construction and 50% on handover. Ezre lists 40% on handover, with 50% paid in five instalments within 13 months of booking. Under the 10/40/50 plan, a villa bought at AED 23.5 million would leave about AED 11.75 million due at handover, so a later handover also moves the largest payment later. No source lists a post-handover plan for this project.

What to check before relying on the Nineteen Riviera Lagoon date

  1. The completion date and grace period in the SPA, compared with the 12 February 2027 register date.
  2. The handover share in the signed schedule, since sources list both 50% and 40%.
  3. The next DLD inspection, through the DLD project status service, to see whether progress has moved on from 34.06%.

Questions buyers also ask

What is the Nineteen Riviera Lagoon completion date?

The DLD project register gives a completion date of 12 February 2027 for project number 2980. Construction started on 12 August 2024 (DLD project register via Continental Club, updated 5 October 2026).

Is Nineteen Riviera Lagoon finished?

No. The last DLD inspection, on 25 June 2026, recorded 34.06% of construction complete. No newer inspection had been published by 11 October 2026.

Has the Nineteen Riviera Lagoon handover date been delayed?

On portals, yes. Brokers quoted Q4 2026 at launch in 2024 (Everhomes). The DLD register now shows 12 February 2027, Property Finder Q1 2027 and Dubainary Q2 2027.

Do all 19 villas hand over at the same time?

The DLD register lists Nineteen Riviera Lagoon as one project with one completion date for all 19 villas. It does not give separate dates by villa type.

Sources

  1. Continental Club, Nineteen Riviera Lagoon (DLD project register) (opens in a new tab)continentalclub.ae · inspection 25 Jun 2026, registry updated 5 Oct 2026
  2. Everhomes, Nineteen Riviera Lagoon (opens in a new tab)everhomes.ae · prices as of 15 Jul 2024
  3. Dubainary, Nineteen Riviera Lagoon (opens in a new tab)dubainary.com · accessed 11 Oct 2026
Request a Unit Review