Handover date

When is the Naia Island handover date?

Updated 1 October 2026 Naia Island

Short answer

The Naia Island handover date is 2029, the opening year given when Shamal Holding unveiled the island on 6 August 2025, and Property Finder lists June 2029. The latest progress figure is land reclamation, which Shamal reported 75% complete in March 2026, up from 55% in February 2026; no Dubai Land Department (DLD) construction percentage or registered completion date has been published. Shamal has not given separate handover dates for the estate plots, the branded residences or the Cheval Blanc Maison.

Registered completion date (DLD)

None published

No DLD project record republished, checked 1 Oct 2026

Latest construction progress

75% of land reclamation

Shamal Holding, via Dredging Today, 11 Mar 2026

Developer's stated date

2029

Opening year, Dubai Media Office via The National, 6 Aug 2025

Portal estimate

June 2029

Property Finder, accessed 1 Oct 2026. Propsearch: 2029

Naia Island handover date: the latest position

Naia Island is due to open in 2029. That was the year given by the Dubai Media Office when Shamal Holding unveiled the island on 6 August 2025, and Matthews, the project management consultant, also gives completion as 2029. Property Finder lists June 2029 and Propsearch lists 2029. The plot sales, prices and the island’s plan are covered on the Naia Island page.

Work is still at the land stage. Shamal reported land reclamation 55% complete in February 2026 and 75% complete in March 2026. Van Oord, the marine contractor, is due to finish reclamation and marine works such as quay walls and culverts in the first half of 2027. No Dubai Land Department completion percentage or registered completion date has been published for the island, so the 2029 date rests on the developer’s announcement and portal estimates rather than the DLD register.

Naia Island handover date by component

Shamal has not published separate dates for each part of the island. The table shows what has been published for each.

Component Construction progress (date) Registered completion date Developer or portal date
Land reclamation and marine works, about 13 hectares 75% of reclamation (Shamal, Mar 2026) None published First half of 2027 (Van Oord, Aug 2025)
Cheval Blanc Maison, 30 suites and 40 pool villas No figure published None published 2029 opening (Dubai Media Office, via The National, 6 Aug 2025)
91 estate plots No figure published; 63 sold by Apr 2026 (Gulf News) None published No plot handover date published
Naia Island as a whole No DLD figure published None published June 2029 (Property Finder); 2029 (Propsearch; Matthews)

Property Finder’s timeline also lists booking from 1 March 2027 and construction start on 2 March 2027, dates that do not match the plot sales and reclamation already reported in 2025 and 2026.

How the Naia Island handover date has changed

The 2029 date has not changed since launch.

Date What happened Source
6 Aug 2025 Shamal unveiled Naia Island with early works under way, scheduled to open in 2029. Dubai Media Office; The National
19 Aug 2025 Van Oord won the reclamation contract, due to finish in the first half of 2027. Dredging Today
13 Feb 2026 Land reclamation 55% complete. Shamal Holding
Mar 2026 Land reclamation 75% complete. Shamal, via Dredging Today, 11 Mar 2026
27 Apr 2026 63 of 91 plots sold, including a record AED 377 million plot. Gulf News
9 May 2026 Handover still targeted around 2029. Arabian Post
14 Sep 2026 Shamal marked one year since launch, with no new date or progress figure. Shamal Holding

What to check before relying on the Naia Island date

  1. Whether you are buying a plot or a finished residence. The 2029 date refers to the island’s opening, and Shamal has published no handover date for the plots.
  2. The completion date written into your sale contract, since there is no DLD registered completion date to fall back on.
  3. Whether the plot or residence is registered with DLD, and under which project and escrow account, through DLD’s project status enquiry service.
  4. Whether the marine works finish in the first half of 2027, since the plots sit on the land being created under that contract.

Questions buyers also ask

What is the Naia Island completion date?

2029. The Dubai Media Office gave 2029 as the opening year when the island was unveiled on 6 August 2025, and Matthews, the project management consultant, gives completion as 2029. Property Finder lists June 2029. No DLD registered completion date has been published.

Is Naia Island finished?

No. The island itself is still being built. Shamal Holding reported land reclamation 75% complete in March 2026, and Van Oord's reclamation and marine works contract runs to the first half of 2027.

When will Naia Island plots be ready?

Shamal Holding has not published a handover date for the 91 estate plots. The reclamation and marine works that create the land are scheduled to finish in the first half of 2027 (Van Oord, Aug 2025), and the island as a whole is due to open in 2029.

Has the Naia Island handover date been delayed?

No change has been published. The 2029 date given at launch in August 2025 was repeated in May 2026 and is still the date on Property Finder and Propsearch as of 1 October 2026. Shamal's post marking one year since launch, on 14 September 2026, gave no new date.

When will the Cheval Blanc at Naia Island open?

The Cheval Blanc Maison, with 30 suites and 40 private pool villas, is part of the 2029 opening announced in August 2025 (The National, 6 Aug 2025). No separate opening date has been published.

Sources