Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Meriden Beach by Green Horizon handover date?

Updated 11 October 2026 Meriden Beach by Green Horizon

Short answer

Meriden Beach Residences by Green Horizon has a registered completion date of 10 December 2027 in the Dubai Land Department project register, while Green Horizon markets completion in Q1 2028. A DLD inspection on 29 April 2026 recorded 1.37% complete. The developer date is later than the registered date, and no DLD reading newer than April 2026 had been published by October 2026.

Registered completion date (DLD)

10 Dec 2027

DLD project register via Continental Club, registry updated 8 Oct 2026

Latest construction progress

1.37%

DLD inspection, 29 Apr 2026

Developer's stated date

Q1 2028

Green Horizon launch release, 20 Nov 2025, and website

Portal date

Dec 2027

Property Finder, accessed 11 Oct 2026

Meriden Beach by Green Horizon handover date: the latest position

Meriden Beach by Green Horizon has a registered completion date of 10 December 2027 in the Dubai Land Department (DLD) project register, where it is project number 4010. Green Horizon markets the building, Meriden Beach Residences, for completion in Q1 2028. The latest DLD inspection, on 29 April 2026, recorded 1.37% complete. Full project details are on the Meriden Beach by Green Horizon page.

The developer’s date is one quarter later than the registered date. That gap is unusual: in most projects the registered date is the later one.

Meriden Beach by Green Horizon handover date by building

Meriden Beach is one low-rise building on Island A of Dubai Islands: ground floor, two podium levels, eight floors and a roof.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Meriden Beach Residences (65 units, DLD) 1.37% (29 Apr 2026) 10 Dec 2027 Q1 2028 (Green Horizon); Dec 2027 (Property Finder)

Marketing material counts 63 residences; the register counts 65 (DLD project register via Continental Club, registry updated 8 October 2026).

How the Meriden Beach by Green Horizon handover date has changed

Date What was stated Source
26 Aug 2025 First DLD inspection at 0% DLD register via Continental Club
20 Nov 2025 Launch; construction to start in 2025, completion Q1 2028 Green Horizon via Zawya
10 Dec 2025 Registered construction start; booking date on Property Finder DLD register; Property Finder
29 Apr 2026 DLD inspection at 1.37% DLD register via Continental Club
Oct 2026 Register shows 10 December 2027; Green Horizon still Q1 2028 DLD register; Green Horizon

Neither date has been revised since launch. The DLD register has no inspection after April 2026, so there is no official figure for progress over the summer of 2026. OffPlan Insider’s listing, accessed 11 October 2026, describes construction as about 15% complete but gives no source for that figure.

What the Meriden Beach by Green Horizon handover date means for payments

Green Horizon’s plan is 35/65: 10% on booking, 25% during construction and 65% on handover. OffPlan Insider details the 25% as 10% thirty days after booking with the SPA, then 5% at 6, 12 and 18 months. Those instalments are set by time, so the full 35% falls due by about mid 2027, before either completion date. The 65% balance, about AED 1.24 million on a AED 1.9 million apartment, is due at handover, so the timing of completion decides when most of the price is paid.

What to check before relying on the Meriden Beach by Green Horizon date

  1. Which date the SPA states. A contract tied to 10 December 2027 gives a different grace period end than one tied to Q1 2028.
  2. A newer DLD reading. The April 2026 figure of 1.37% is the latest official one, and broker estimates since then are unsourced.
  3. The unit and floor in the SPA, given the gap between the 63 unit marketing count and the 65 units in the register.

Questions buyers also ask

What is the Meriden Beach Residences completion date?

The DLD register records 10 December 2027 for project 4010, Meriden Beach By Green Horizon. Green Horizon gives Q1 2028.

Has the Meriden Beach handover date been delayed?

No change has been announced. Green Horizon gave Q1 2028 at launch in November 2025 and still does. The registered date of 10 December 2027 is earlier than that.

How far along is construction at Meriden Beach?

The DLD inspection of 29 April 2026 recorded 1.37%, up from 0% on 26 August 2025. Construction is registered as starting on 10 December 2025.

How much is due on handover at Meriden Beach?

65% of the price, after 10% on booking and 25% during construction (Green Horizon).

Sources

  1. OffPlan Insider, Meriden Beach Residences (opens in a new tab)offplaninsider.com · accessed 11 Oct 2026
Request a Unit Review