Handover date

When is the Linea by Holm handover date?

Updated 11 October 2026 Linea by Holm

Short answer

Linea by Holm has a registered completion date of 15 June 2028 in the Dubai Land Department project register, while Holm Developments' project page gives Q1 2028. A DLD inspection on 27 July 2026 recorded 0.69% complete. The developer date is about one quarter earlier than the registered date, and the building was still at an early stage in mid 2026.

Registered completion date (DLD)

15 Jun 2028

DLD project register via Continental Club, registry updated 5 Oct 2026

Latest construction progress

0.69%

DLD inspection, 27 Jul 2026

Developer's stated date

Q1 2028

Holm Developments, project page, accessed 11 Oct 2026

Broker listings

Q2 2028

TruHauz and OffPlan Insider, accessed 11 Oct 2026

Linea by Holm handover date: the latest position

Linea by Holm has a registered completion date of 15 June 2028 in the Dubai Land Department (DLD) project register, where it is listed as Linea By Holm, project number 4331. Holm Developments’ project page gives Q1 2028. The DLD inspection of 27 July 2026 recorded 0.69% of construction complete. Full project details are on the Linea by Holm page.

Broker listings such as TruHauz and OffPlan Insider show Q2 2028, matching the register. Holm has not announced any change of date.

Linea by Holm handover date by building

Linea is one low-rise building of 210 apartments: 96 studios, 89 one bedrooms and 25 two bedrooms (DLD register).

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Linea by Holm (210 units) 0.69% (27 Jul 2026) 15 Jun 2028 Q1 2028 (Holm, Propsearch); Q2 2028 (TruHauz, OffPlan Insider)

The previous inspection, on 7 May 2026, recorded about 0.14% (DLD project register via Continental Club, registry updated 5 October 2026).

How the Linea by Holm handover date has changed

Date What was stated Source
20 Jan 2026 Project page published; completion Q1 2028 Holm Developments
1 Feb 2026 Launch and registered construction start; registered completion 15 June 2028 TruHauz; DLD register via Continental Club
18 May 2026 Aroma International Building Contracting appointed main contractor Holm Developments
27 Jul 2026 DLD inspection at 0.69% DLD register via Continental Club
Oct 2026 Holm still shows Q1 2028; register shows 15 June 2028 Holm; DLD register

Holm’s first project, HOLM One, nearby in Jumeirah Garden City, also targets Q1 2028. Holm has not completed a building in Dubai yet, so neither date can be checked against an earlier record.

What the Linea by Holm handover date means for payments

Holm publishes a 35/65 plan. Sources split the 35% differently: ezre lists 5% on booking, 5% on signing the SPA and 25% in four instalments over 21 months after the SPA, while OffPlan Insider and TruHauz show 20% on booking and 15% during construction. Under the ezre schedule, the pre-handover instalments are set by months after signing rather than by progress, so they end around late 2027 whatever stage the building has reached. The 65% balance is due at handover, so the timing of completion decides when most of the price is paid.

What to check before relying on the Linea by Holm date

  1. Which date the SPA states, Q1 2028 or 15 June 2028, and the grace period after it.
  2. Whether instalments are dated or tied to progress. At 0.69% in July 2026, dated instalments could run well ahead of construction.
  3. The DLD inspection in late 2026. The first readings after the May 2026 contractor appointment will show the build pace.

Questions buyers also ask

What is the Linea by Holm completion date?

The DLD register records 15 June 2028 for project 4331, Linea By Holm. Holm gives Q1 2028.

Has the Linea by Holm handover date been delayed?

No delay has been announced. The sources differ by about a quarter: Holm and Propsearch give Q1 2028, the register and broker listings point to Q2 2028.

Is construction under way at Linea by Holm?

Yes. Construction is registered as starting on 1 February 2026, Holm appointed Aroma International Building Contracting as main contractor on 18 May 2026, and the DLD inspection of 27 July 2026 recorded 0.69%.

How much is due on handover at Linea by Holm?

65% of the price, under the 35/65 plan Holm publishes.

Sources

  1. Propsearch, Linea by Holm (opens in a new tab)propsearch.ae · accessed 11 Oct 2026
  2. TruHauz, Linea by Holm (opens in a new tab)truhauz.com · accessed 11 Oct 2026
  3. OffPlan Insider, LINEA by HOLM (opens in a new tab)offplaninsider.com · accessed 11 Oct 2026
Request a Unit Review