When is the Lincoln Star Residence handover date?
Short answer
Lincoln Star Residence had a registered completion date of 30 September 2026, and the developer still lists Q3 2026. The last published DLD inspection, on 26 February 2026, recorded the building 47.21% complete. That date has now passed with no new date filed, so the SPA's grace period and the next DLD inspection are what count.
Registered completion date (DLD)
30 Sep 2026
DLD project register via Mitchells; passed
Latest construction progress
47.21%
DLD inspection, 26 Feb 2026
Developer's stated date
Q3 2026
Lincoln Star Group, accessed 11 Oct 2026
Date at groundbreaking
Q4 2025
Zawya, 23 Oct 2024
Lincoln Star Residence handover date: the latest position
Lincoln Star Residence was registered with DLD for completion on 30 September 2026. That date has passed, and the register still lists the building as under construction. Prices, sizes and the payment plan are on the Lincoln Star Residence page.
The last published DLD inspection, on 26 February 2026, recorded 47.21% complete. The developer’s page still says “anticipated completion Q3 2026” (accessed 11 October 2026). Until a new inspection or a revised date is filed, there is no official date after September 2026.
Lincoln Star Residence handover date by building
The project is a single building, DLD project 3102, with 48 units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Lincoln Star Residence (G+4+roof, 48 units) | 47.21%, 26 Feb 2026 | 30 Sep 2026 (passed) | Q3 2026 (Lincoln Star Group); Dec 2025 (Property Finder) |
How the Lincoln Star Residence handover date has changed
| Date | What happened | Source |
|---|---|---|
| 1 May 2024 | Bookings open | Property Finder |
| 28 May 2024 | First DLD inspection, 0% | DLD via Dubai Handover |
| 23 Oct 2024 | Groundbreaking, handover targeted for Q4 2025 | Zawya |
| 21 Apr 2025 | Inspection records 17.1% | DLD via Dubai Handover |
| 6 Oct 2025 | Inspection records 30.6% | DLD via Dubai Handover |
| 26 Feb 2026 | Inspection records 47.21% | DLD via Mitchells |
| 30 Sep 2026 | Registered completion date passes | DLD register |
| 11 Oct 2026 | Developer still shows Q3 2026 | Lincoln Star Group |
The Q4 2025 target slipped by at least nine months. Progress rose about 16.6 points between October 2025 and February 2026, about 3.5 points a month. At that pace the building would have been around 72% complete by the end of September 2026, not finished. This is an estimate from the published inspections, not a DLD figure.
What the Lincoln Star Residence handover date means for payments
The listed plan is 20% on booking, 18% during construction, 10% on handover and 52% after handover at 1% a month (Property Finder; Aigents Realty). Only 38% is paid before the keys. A later handover pushes back the 10% handover payment and the start of the 52 monthly post-handover instalments. On a 1 bedroom at the 2026 DLD median of AED 923,683, the handover payment is about AED 92,400 and each monthly instalment after it about AED 9,240.
What to check before relying on the Lincoln Star Residence date
- The SPA completion date and grace period. The registered date has passed, so the contract terms decide what happens next.
- DLD’s project status service for project 3102, for an inspection newer than February 2026.
- Any revised completion date filed with DLD, as the developer’s Q3 2026 date ended on 30 September 2026.
Questions buyers also ask
Is Lincoln Star Residence finished?
No. The DLD register still lists it as under construction (register as at 4 Oct 2026), and the last published inspection, on 26 February 2026, recorded 47.21% complete.
When will Lincoln Star Residence be completed?
The registered completion date was 30 September 2026, which has passed. The developer lists anticipated completion as Q3 2026. No revised date had been filed by 11 October 2026.
Has the Lincoln Star Residence handover date been delayed?
Yes. At groundbreaking in October 2024 the target was Q4 2025 (Zawya). Property Finder later showed December 2025, the developer moved to Q3 2026, and the 30 September 2026 registered date passed with the building last recorded at under half complete.
How many units are in Lincoln Star Residence?
48: 6 studios, 18 one bedroom and 22 two bedroom apartments, and 2 three bedroom townhouses, in one ground plus four storey building (DLD project register).