Short answer

The La Boutique by LMD handover date is Q4 2026, and the registered completion date on the Dubai Land Department (DLD) register is 31 December 2026. The DLD recorded the building 38.09% complete on 18 June 2026, up from 21.63% in March. With most of the work still to do six months before the date, a handover in 2027 is more likely than one by December 2026; Propsearch's earlier Q2 2026 estimate has already passed.

Registered completion date

31 Dec 2026

DLD register via Continental Club, updated 7 Oct 2026

Latest construction progress

38.09%

DLD inspection, 18 Jun 2026

Developer's stated date

Q4 2026

LMD, via Property Finder and Continental Club

Earlier portal estimate

Q2 2026

Propsearch, updated 7 May 2026

La Boutique by LMD handover date: the latest position

La Boutique by LMD, a 119 unit building in Culture Village, Al Jaddaf, has a registered completion date of 31 December 2026 on the Dubai Land Department (DLD) register. LMD’s date, shown on Property Finder and Continental Club, is Q4 2026. More on homes, prices and the payment plan is on the La Boutique by LMD project page.

At the DLD inspection of 18 June 2026, the building was 38.09% complete. Work sped up in spring 2026, adding 16.46 points in under three months, but even at that rate the remaining 62% would take until well into 2027. Continental Club’s estimate, based on the pace over the past year, puts 100% around 25 February 2028.

La Boutique by LMD handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
La Boutique by LMD (119 units) 38.09% (18 Jun 2026) 31 Dec 2026 Q4 2026 (LMD; Property Finder; Bayut); Q2 2026 (Propsearch, May 2026)

Recorded inspections:

Inspection Progress Source
25 Nov 2025 14.33% Property Finder
25 Mar 2026 21.63% DLD register via Continental Club
18 Jun 2026 38.09% DLD register via Continental Club

How the La Boutique by LMD handover date has changed

Date Event Source
1 Jul 2024 Sales open from AED 909,000; registered construction start. Property Finder; DLD register
9 Sep 2025 Bayut lists expected completion in Q4 2026. Bayut
7 May 2026 Propsearch says the estimated handover “was Q2 2026”. Propsearch
18 Jun 2026 DLD inspection records 38.09%. Continental Club
Oct 2026 Register still shows 31 December 2026; Property Finder shows December 2026. Continental Club; Property Finder

LMD has not announced a change to its Q4 2026 date. The gap between that date and the recorded progress is the main open question.

What the La Boutique by LMD handover date means for payments

The plan is 20% on booking, 40% during construction and 40% on handover, with nothing after handover (Property Finder, Bayut). On a 1 bedroom registered at AED 986,000 in March 2026, the handover payment is about AED 394,400. If completion moves into 2027 or 2028, that payment moves with it, while the 40% construction stage continues to fall due during the build.

LMD’s most recent completion, Marina Living in Dubai Marina, was handed over in August 2026 (Zawya, 6 August 2026). It gives a reference for how LMD manages the handover process, though not for this building’s timing.

What to check before relying on the La Boutique by LMD date

  1. The grace period in the SPA after 31 December 2026, and what remedy applies if it is exceeded.
  2. The DLD inspection after June 2026. A figure near 60% by the end of the year would still leave months of work.
  3. For resale buyers, the instalments the seller has paid, since the developer’s 40% construction stage may be partly outstanding.

Questions buyers also ask

Is La Boutique by LMD finished?

No. The DLD recorded it 38.09% complete on 18 June 2026, and no newer inspection had been published by 7 October 2026.

What is the La Boutique by LMD completion date?

31 December 2026 on the DLD register for project 3120. LMD gives Q4 2026.

Has the La Boutique by LMD handover date been delayed?

Propsearch's estimate of Q2 2026 has passed. LMD and the register still show Q4 2026 and 31 December 2026, but at the pace recorded over the past year Continental Club projects 100% around 25 February 2028.

How much is paid at La Boutique by LMD handover?

40% of the price on the 20/40/40 plan, about AED 380,000 on a AED 950,000 1 bedroom.

Sources

  1. DLD project register via Continental Club, La Boutique by LMD (opens in a new tab)continentalclub.ae · inspection 18 Jun 2026, register updated 7 Oct 2026
  2. Propsearch, La Boutique by LMD (opens in a new tab)propsearch.ae · updated 7 May 2026
Request a Unit Review