Handover date

When is the Jouri Hills handover date?

Updated 11 October 2026 Jouri Hills

Short answer

Arada's current handover target for Jouri Hills is Q4 2026. The DLD register still shows a registered completion date of 30 June 2026, which has passed. The latest DLD inspection, on 5 October 2026, recorded 78.47% complete. Arada first promised completion by mid-2025, so the date has moved by about 18 months, and the recent pace points to early 2027 rather than late 2026.

Registered completion date (DLD)

30 Jun 2026

Passed; moved from 30 Jun 2025 in Aug 2026

Latest construction progress

78.47%

DLD inspection, 5 Oct 2026

Developer's stated date

Q4 2026

Arada website, via NAHY (31 Jul 2026)

Date given at launch

Mid-2025

Propsearch, Nov 2022

Jouri Hills handover date: the latest position

Arada’s current target for Jouri Hills is the fourth quarter of 2026, the date on its website when NAHY checked it on 31 July 2026. The DLD project register shows a registered completion date of 30 June 2026, which has now passed. Prices, home types and the payment plan are on the Jouri Hills page.

The latest DLD inspection, on 5 October 2026, recorded 78.47% complete. The sources reviewed show no handover announcement, and about a fifth of the work remains.

Jouri Hills handover date by building

The DLD register holds Jouri Hills as one project, DLD project 2506, with 295 units across its townhouses, villas and mansions. The register does not split the date by cluster.

Building or phase Construction progress (DLD, date) Registered completion date Developer or portal date
Jouri Hills (all 295 units) 78.47%, 5 Oct 2026 30 Jun 2026 (passed) Q4 2026 (Arada website, Jul 2026); Q4 2026 (Data Habibi)

How the Jouri Hills handover date has changed

Date What happened Source
Nov 2022 Launch at Cityscape Dubai; completion due by mid-2025 Propsearch
1 Aug 2023 Construction start registered DLD register
Oct 2023 Main contract to Intermass, 21 month programme; project sold out Propsearch
16 Mar 2026 DLD inspection records 51.89% DLD register
23 Apr 2026 DLD inspection records 58.05% DLD register
31 Jul 2026 Arada website shows Q4 2026 NAHY
Late Aug 2026 Registered completion date moves from 30 Jun 2025 to 30 Jun 2026 Dubai Handover snapshots
5 Oct 2026 DLD inspection records 78.47% DLD register

Between 23 April and 5 October 2026, progress rose 20.42 points, about 3.8 points a month. At that pace, the remaining 21.53 points would take about five and a half months, which points to around March 2027. Finishing within Q4 2026 would need roughly double that pace. This is a calculation from the register, not a date given by Arada.

What the Jouri Hills handover date means for payments

The plan is 20% on booking, 40% during construction and 40% on handover (Continental Club; Projects Scout), with no post-handover instalments. The 40% handover payment is large on homes at this level. On a 3 bedroom townhouse at AED 4,997,722, it is about AED 2.0 million. On a 5 bedroom villa at AED 10.1 million, it is about AED 4.06 million. That payment falls due only when Arada issues the handover notice, so the slip from mid-2025 has also pushed it back.

What to check before relying on the Jouri Hills date

  1. The anticipated completion date and grace period in the original SPA, since many contracts were signed against mid-2025.
  2. Whether the register’s completion date moves again, as it did in August 2026.
  3. Whether the plot’s cluster is in the first handover batch, since a 295 unit villa community may not hand over all at once.
  4. The handover notice and snagging timeline, as the 40% balance becomes due when the notice is issued.

Questions buyers also ask

When will Jouri Hills be completed?

Arada's target is Q4 2026. The DLD register shows 30 June 2026, which has passed. At the 5 October 2026 inspection the community was 78.47% complete.

Has the Jouri Hills handover been delayed?

Yes. At launch in November 2022, completion was scheduled for mid-2025 (Propsearch). Data Habibi records an 18 month postponement to Q4 2026, and the DLD registered completion date moved from 30 June 2025 to 30 June 2026 in late August 2026 (Dubai Handover).

Is Jouri Hills finished?

No. The DLD inspection of 5 October 2026 recorded 78.47% complete, and the sources reviewed show no handover announcement.

When did construction start at Jouri Hills?

The DLD register records 1 August 2023. Arada awarded the AED 645 million main contract to Intermass in October 2023, with a 21 month programme (Propsearch).

Sources

  1. Propsearch, Jouri Hills (opens in a new tab)propsearch.ae · updated 8 Apr 2026
  2. Data Habibi, Jouri Hills (opens in a new tab)datahabibi.ae · accessed 11 Oct 2026
  3. Projects Scout, Jouri Hills by Arada (opens in a new tab)projectsscout.com · accessed 11 Oct 2026