Illustration: construction cranes on a residential tower at dusk
Handover date

When is the HQ by Rove handover date?

Updated 11 October 2026 HQ by Rove

Short answer

HQ by Rove is due for handover in Q1 2029, and its registered completion date in the Dubai Land Department project register is 31 March 2029. A DLD inspection on 6 July 2026 recorded construction at 0.7%. The date has not changed since launch, but the project is at foundation stage and IRTH's first Rove Home tower has already passed its own registered date.

Registered completion date (DLD)

31 Mar 2029

DLD project register via Continental Club, registry updated 8 Oct 2026

Latest construction progress

0.7%

DLD inspection, 6 Jul 2026

Developer's stated date

Q1 2029

IRTH, HQ by Rove site, accessed 11 Oct 2026

Change since launch

None

Q1 2029 in IRTH brochure, Sep 2025

HQ by Rove handover date: the latest position

IRTH Group gives an anticipated handover of Q1 2029 for HQ by Rove, and the Dubai Land Department (DLD) project register lists a completion date of 31 March 2029 for the project, registered as Hq By Rove, number 4143. The latest DLD inspection, on 6 July 2026, recorded 0.7% of construction complete. Full project details are on the HQ by Rove page.

Unlike many off-plan projects, the developer date and the registered date line up. The open question is pace: in July 2026 the site was at foundation stage, with about 32 months left to the registered date.

HQ by Rove handover date by building

HQ by Rove is one office tower with 414 registered units on Marasi Bay in Business Bay.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
HQ by Rove (414 office units) 0.7% (6 Jul 2026) 31 Mar 2029 Q1 2029 (IRTH); Q1 2029 (Crown Key)

Earlier DLD inspections recorded 0% on 8 October 2025 and 0.06% on 23 March 2026 (DLD project register via Continental Club, registry updated 8 October 2026).

How the HQ by Rove handover date has changed

Date What was stated Source
Aug 2025 Rove Hotels and IRTH announce HQ by Rove Rove Hotels
29 Sep 2025 Brochure and payment plan; completion Q1 2029 IRTH via Mitchell’s
22 Oct 2025 Project registered with DLD; end date 31 March 2029 DLD register via Mitchell’s
15 Dec 2025 Registered construction start DLD register
6 Jul 2026 DLD inspection at 0.7% DLD register via Continental Club
8 Oct 2026 Register still shows 31 March 2029 DLD register via Mitchell’s

IRTH’s record on its residential towers is the main reference point. Rove Home Downtown had a registered completion date of 30 April 2026, but a DLD inspection on 9 June 2026 put it at 62.69%. Rove Home Marasi Drive was 10% complete on 6 July 2026 against a registered date of 31 August 2027, and Property Finder had earlier shown March 2027 for it (DLD register via Mitchell’s).

What the HQ by Rove handover date means for payments

The plan is 50/50. Buyers pay 15% down, then 5% on each of 1 November 2025, 1 April 2026, 1 September 2026 and 1 February 2027. Three further 5% instalments are tied to 40%, 60% and 80% construction progress, printed as due on or before 1 December 2027, 1 May 2028 and 1 November 2028. The last 50% is due on completion (IRTH brochure dated 29 September 2025, via Mitchell’s).

The dated instalments mean 35% is paid by February 2027 regardless of progress. If construction runs late, the milestone instalments and the 50% completion payment move later with it.

What to check before relying on the HQ by Rove date

  1. The anticipated completion date and grace period in the SPA, given that IRTH’s first tower passed its registered date before reaching 63%.
  2. How the progress-linked instalments are triggered. The brochure wording “on or before” a date should be matched against the SPA clause.
  3. Inspections in 2027. The plan expects 40% progress by 1 December 2027; DLD readings will show whether the site is on that track.

Questions buyers also ask

What is the HQ by Rove completion date?

The DLD register records a completion date of 31 March 2029 for project 4143, Hq By Rove. IRTH gives Q1 2029.

Has the HQ by Rove handover date been delayed?

Not so far. IRTH's September 2025 brochure gave Q1 2029 and the DLD register still shows 31 March 2029 (Mitchell's, register checked 8 Oct 2026).

How far along is construction at HQ by Rove?

The DLD inspection of 6 July 2026 recorded 0.7%, up from 0.06% on 23 March 2026. Construction is registered as starting on 15 December 2025.

How much is due on completion at HQ by Rove?

Half the price. The plan is 15% down, 35% in seven instalments of 5%, and 50% on completion (IRTH brochure, 29 Sep 2025).

Sources

  1. IRTH, HQ by Rove project site (opens in a new tab)hq-by-rove.ae · accessed 11 Oct 2026
  2. Crown Key, HQ by Rove (opens in a new tab)crownkey.ae · accessed 11 Oct 2026
  3. Property Finder, Rove Home Marasi Drive (opens in a new tab)propertyfinder.ae · accessed 11 Oct 2026