When is the Haven by Aldar handover date?

Updated 1 October 2026 Haven by Aldar

Short answer

Aldar's Haven project page gives Q4 2027 for completion, a quarter later than the Q3 2027 it announced at launch in October 2023. On the DLD register, Haven by Aldar 1 has a registered completion date of 28 November 2027 and Haven by Aldar 3 has 30 March 2028. DLD inspections on 28 July 2026 recorded Haven 1 at 44.15%, Haven 2 at 40.02% and Haven 3 at 57.62%, so each phase has its own date.

Registered completion date (DLD), Haven 1

28 Nov 2027

DLD project 2873. Haven 3: 30 Mar 2028

Latest construction progress

40.02% to 57.62%

DLD inspections, 28 Jul 2026, three phases

Developer's stated date

Q4 2027

Aldar project page, data dated 24 Mar 2025

Date change since launch

Q3 2027 to Q4 2027

Aldar, 26 Oct 2023 launch; Property Finder Q4 2027

Haven by Aldar handover date: the latest position

Aldar’s project page for Haven, with data dated 24 March 2025, gives Q4 2027 for completion. That is one quarter later than the date in Aldar’s launch announcement of 26 October 2023, which said first handovers were expected in Q3 2027. Property Finder also lists Q4 2027. Prices, sizes and the payment plan are on the Haven by Aldar page.

The Dubai Land Department holds Haven as three projects, with registered completion dates from 28 November 2027 to 30 March 2028. DLD inspections on 28 July 2026 put them at 40.02% to 57.62% complete.

Haven by Aldar handover date by phase

All three phases are filed by Aurora SPV 1, Aldar’s Dubai vehicle, in Wadi Al Safa 5. Haven 1 and Haven 2 have a registered construction start of 30 April 2024.

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
Haven by Aldar 1, 462 villas (DLD 2873) 44.15%, 28 Jul 2026 28 Nov 2027 Q4 2027 (Aldar; Property Finder)
Haven by Aldar 2, 474 homes (DLD 2874) 40.02%, 28 Jul 2026 Not shown in republished register data Q4 2027 (Aldar; Property Finder)
Haven by Aldar 3, 292 homes (DLD 2875) 57.62%, 28 Jul 2026 30 Mar 2028 Q4 2027 (Aldar); Sep 2027 (Property Finder, Haven Phase 3 listing)

The three records hold 1,228 homes, about half of the 2,428 Aldar announced for the community. Haven by Aldar 3 is the furthest along but has the latest registered date. Haven by Aldar 2 has moved fastest recently: 8.48% on 11 December 2025 (fäm), 27.8% at the 13 April 2026 inspection and 40.02% on 28 July 2026.

How the Haven by Aldar handover date has changed

Date What happened Source
26 Oct 2023 Launch; construction to start Q2 2024, first handovers expected Q3 2027 Aldar
16 Jan 2024 Three phases registered with DLD DLD register, via HomeSearch
30 Apr 2024 Registered construction start; Haven 1 completion filed as 28 Nov 2027 DLD register, via Dubricks
24 Mar 2025 Aldar’s project page data: completion Q4 2027 Aldar
11 Dec 2025 Haven 2 at 8.48% fäm Properties
13 Apr 2026 Haven 2 at 27.8% DLD inspection, via Continental Club
28 Jul 2026 Haven 1 at 44.15%, Haven 2 at 40.02%, Haven 3 at 57.62% DLD inspections
Sep 2026 Register shows 28 Nov 2027 (Haven 1) and 30 Mar 2028 (Haven 3) DLD register, via Continental Club

What the Haven by Aldar handover date means for payments

Property Finder lists 5% at booking, 65% during construction and 30% on handover. The handover share is the largest single payment. On a 3 bedroom townhouse at the AED 2.5 million launch price, it is AED 750,000. A buyer in Haven by Aldar 3 could pay it up to four months later than one in Haven by Aldar 1 if each phase completes on its registered date.

What to check before relying on the Haven by Aldar date

  1. Which of the three DLD projects the unit is in. The registered dates run from 28 November 2027 for Haven 1 to 30 March 2028 for Haven 3.
  2. The SPA date for Haven by Aldar 2 units. No registered completion date was found for that phase in the republished register data, so the SPA is the reference.
  3. Which Aldar date the SPA uses. Contracts signed at launch may carry Q3 2027, while Aldar’s page now gives Q4 2027.
  4. That the unit is in Haven and not Verdes by Haven, whose first phase is registered for 31 May 2028 and was 13.41% built in July 2026.

Questions buyers also ask

Is Haven by Aldar finished?

No. DLD inspections on 28 July 2026 recorded Haven by Aldar 1 at 44.15%, Haven by Aldar 2 at 40.02% and Haven by Aldar 3 at 57.62%.

What is the Haven by Aldar completion date?

Aldar's project page gives Q4 2027. The DLD register gives 28 November 2027 for Haven by Aldar 1 and 30 March 2028 for Haven by Aldar 3. No registered completion date was found for Haven by Aldar 2 in the register data republished by Continental Club and HomeSearch.

When will Haven by Aldar be ready?

On Aldar's own date, in Q4 2027. The phase registered for March 2028, Haven by Aldar 3, was the furthest along at 57.62% in July 2026.

Has the Haven by Aldar handover date been delayed?

It has moved once. Aldar's launch announcement on 26 October 2023 said first handovers were expected in Q3 2027; its project page, with data dated 24 March 2025, gives Q4 2027. No later change has been published.

Does Verdes by Haven hand over at the same time?

No. Verdes by Haven is a separate apartment project. Verdes by Haven 1 has a registered completion date of 31 May 2028 and was 13.41% built at the DLD inspection on 23 July 2026 (Mitchells).

Sources

  1. Aldar Properties, Haven project page (opens in a new tab)aldar.com · data dated 24 Mar 2025, accessed 1 Oct 2026