
When is the Haus of Tenet handover date?
Short answer
IRTH gives Q2 2028 for Haus of Tenet, while the Dubai Land Department (DLD) register lists an anticipated completion date of 31 August 2028. The latest published DLD inspection, on 22 December 2025, recorded 20.62%, but the register also lists the project as pending with a construction start of 1 March 2026. The progress figure should be read with caution until a newer inspection is published.
Registered completion date (DLD)
31 Aug 2028
DLD register via Dubricks and Doment
Latest construction progress
20.62%
DLD inspection, 22 Dec 2025, via Continental Club
Developer's stated date
Q2 2028
IRTH, Feb 2026
Portal dates
29 to 30 Jun 2028
GI Properties; PropertyStellar, Oct 2026
Haus of Tenet handover date: the latest position
IRTH gives Q2 2028 for Haus of Tenet, its office tower in Business Bay. The Dubai Land Department (DLD) register lists an anticipated completion date of 31 August 2028 for project 4253, filed by Irth Urban Two Development. Full project details are on the Haus of Tenet page.
The register’s progress data is unclear. It shows 20.62% at an inspection on 22 December 2025, but also a pending status and a construction start of 1 March 2026. No later inspection had been published by early October 2026.
Haus of Tenet handover date by building
Haus of Tenet is one 21 storey tower with up to 225 offices.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Haus of Tenet (up to 225 offices) | 20.62% (22 Dec 2025); 0.62% (25 Nov 2025) | 31 Aug 2028 | Q2 2028 (IRTH; GRAF); 30 Jun 2028 (GI Properties); 29 Jun 2028 (PropertyStellar) |
Datadubai lists the project for 2028 with about 21% progress, without a day or month.
How the Haus of Tenet handover date has changed
| Date | What was stated | Source |
|---|---|---|
| 25 Nov 2025 | DLD inspection at 0.62% | DLD register via Lankea |
| 22 Dec 2025 | DLD inspection at 20.62% | DLD register via Continental Club |
| 10 Feb 2026 | Launch announced by IRTH; anticipated handover Q2 2028 | IRTH |
| 28 Feb 2026 | Sales start | GI Properties |
| 1 Mar 2026 | Registered construction start | DLD register via Dubricks |
| 29 Apr 2026 | Registration date; anticipated completion 31 August 2028 | DLD register via Dubricks |
| 5 Oct 2026 | Register still shows the December 2025 inspection | DLD register via Continental Club |
The developer quarter has not changed since launch. IRTH’s other projects show how its dates have held so far: Rove Home Downtown passed its registered 30 April 2026 date at 62.69% complete on 9 June 2026 (DLD register via Mitchell’s).
What the Haus of Tenet handover date means for payments
The plan is 10/40/50, so half the price is due on completion (GRAF). One published schedule puts 35% on fixed dates between booking and 1 February 2027, with three more 5% instalments tied to 40%, 60% and 80% construction (Tohid Fetrat). Under that schedule, a later completion delays the milestone instalments and the 50% balance, but not the dated ones. On an AED 3.2 million office, AED 1.6 million is due at completion.
What to check before relying on the Haus of Tenet date
- Which date the SPA states: Q2 2028, 30 June 2028 or the registered 31 August 2028, and the grace period after it.
- The live status in the DLD project status enquiry, since the copies of the register show a pending status and two very different progress readings.
- How the 40%, 60% and 80% instalments are certified, as they depend on DLD progress figures.
Questions buyers also ask
When will Haus of Tenet be completed?
IRTH gives Q2 2028. The DLD register lists 31 August 2028 (Dubricks; Doment, accessed October 2026).
How far along is construction at Haus of Tenet?
The latest published DLD figure is 20.62% at an inspection on 22 December 2025. An earlier reading, on 25 November 2025, was 0.62%. The register lists a construction start of 1 March 2026 and a pending status, so the figures do not line up.
Has the Haus of Tenet handover date been delayed?
IRTH has kept Q2 2028 since the February 2026 launch. The registered date of 31 August 2028 has been later than IRTH's quarter from the start, not a later change.
Is the Haus of Tenet handover date the same as HQ by Rove?
No. HQ by Rove, IRTH's other office tower, has a registered completion date of 31 March 2029.
