Handover date

When is the Grand Polo Club and Resort handover date?

Updated 1 October 2026 Grand Polo Club and Resort

Short answer

Grand Polo Club and Resort has no single handover date. The Dubai Land Department (DLD) register gives each of its 13 registered clusters its own completion date, from February 2029 for Chevalia Estate to August 2029 for Equiterra and Equestra, and Property Finder lists 1 June 2029 for the project. The most advanced cluster, Montura, was 11.08% complete at the DLD inspection of 5 August 2026, and several later clusters were below 2%. Emaar itself has not published a handover date.

Registered completion dates (DLD)

Feb to Aug 2029

13 clusters, DLD register via fäm Properties, accessed 1 Oct 2026

Latest construction progress, most advanced cluster

11.08%

Montura, DLD site inspection, 5 Aug 2026

Developer's stated date

Not published

Emaar launch release and community page; clusters marked Q2 2029 as developer supplied on Continental Club

Portal estimate

1 Jun 2029

Property Finder, accessed 28 Sep 2026

Grand Polo Club handover date: the latest position

Grand Polo Club and Resort has no single handover date. The Dubai Land Department (DLD) register gives each of its 13 registered clusters its own completion date, from February 2029 for Chevalia Estate to August 2029 for Equiterra and Equestra, and Property Finder lists 1 June 2029 for the project. Emaar has not published a handover date in its launch release or on its community page. Prices and villa types are on the Grand Polo Club and Resort page.

Construction is at an early stage. The most advanced cluster, Montura, was 11.08% complete at the DLD inspection of 5 August 2026, and Chevalia Fields was 10.03% on 21 July 2026. The clusters launched later, Equiterra, Equiterra 2 and Equestra, were around 1% in April and May 2026.

Grand Polo Club handover date by cluster

The table lists every Grand Polo cluster found on the DLD register, with its project number. Registered completion dates are shown to the month, or to the day where a tracker publishes it.

Cluster (DLD project) Construction progress (DLD, date) Registered completion date Developer or portal date
Chevalia Estate (3699) 2.28%, 21 Apr 2026 Feb 2029 Not published
Chevalia Fields (3701) 10.03%, 21 Jul 2026 Apr 2029 Q2 2029 (Continental Club)
Selvara (3822) 2.81%, 14 May 2026 Apr 2029 Not published
Selvara 2 (3823) 4.04%, 14 May 2026 Apr 2029 Not published
Montura 2 (3704) 5.01%, 6 Jul 2026 May 2029 Q2 2029 (Continental Club)
Selvara 3 (3866) 2.98%, 6 May 2026 31 May 2029 Q2 2029 (Continental Club)
Selvara 4 (3875) 2.88%, 6 May 2026 31 May 2029 Not published
Montura (3700) 11.08%, 5 Aug 2026 30 Jun 2029 Q2 2029 (Continental Club)
Montura 3 (3703) 1.06%, 21 Apr 2026 Jun 2029 Not published
Chevalia Estate 2 (4067) 4.09%, 25 Jun 2026 30 Jun 2029 Q2 2029 (Continental Club)
Equiterra 2 (4162) 1.04%, 29 Apr 2026 Jul 2029 Not published
Equiterra (4185) 0.83%, 14 May 2026 Aug 2029 Not published
Equestra (4186) 1.02%, 4 May 2026 Aug 2029 Not published

The order of registered dates does not follow progress on site. Chevalia Estate has the earliest date, February 2029, but was 2.28% built in April 2026, while Montura, registered for June 2029, was furthest ahead.

How the Grand Polo Club handover date has changed

No date has moved so far. The dates below are those set as each cluster was registered.

Date What happened Source
13 Mar 2025 Montura construction start registered, with a completion date of 30 June 2029. DLD register, via Overit
23 Apr 2025 Emaar launched Grand Polo Club and Resort, with no handover date given. Emaar
2 Nov 2025 Selvara 3 and Selvara 4 construction start registered, both due 31 May 2029. DLD register, via Continental Club
Late 2025 Equiterra, Equiterra 2 and Equestra registered, due July to August 2029. DLD register, via fäm Properties
16 Feb 2026 Chevalia Estate 2 construction start registered, due 30 June 2029. DLD register, via Dubai Handover
Apr to Aug 2026 Inspections recorded 0.83% to 11.08% across the clusters. DLD register, via fäm Properties
Sep 2026 Property Finder still lists 1 June 2029. Property Finder

What the Grand Polo Club handover date means for payments

Property Finder lists 10% at launch, 70% during construction in 7 instalments and 20% at handover. On a 3 bedroom villa listed from AED 5.7 million, the handover payment is AED 1.14 million, and AED 3.99 million is paid during construction. Emaar has not published the plan on its own pages. With most of the price due during construction, the timing of the 7 instalments matters as much as the 2029 date.

What to check before relying on the Grand Polo Club date

  1. Which cluster your villa is in. Registered dates run from February to August 2029, six months apart, and progress ranged from under 1% to 11.08%.
  2. The completion date and grace period in your SPA, since Emaar has not published a project-wide date to compare against.
  3. How your 7 construction instalments are scheduled, whether by date or by construction milestone, given that some clusters were near 1% built in mid 2026.
  4. The DLD figure for your cluster’s project number, through DLD’s project status enquiry service, since Propsearch still described the project as at the planning stage on 16 September 2026.

Questions buyers also ask

What is the Grand Polo Club and Resort completion date?

It depends on the cluster. On the DLD register, Chevalia Estate is due in February 2029, Chevalia Fields, Selvara and Selvara 2 in April 2029, Montura 2, Selvara 3 and Selvara 4 in May 2029, Montura, Montura 3 and Chevalia Estate 2 in June 2029, Equiterra 2 in July 2029, and Equiterra and Equestra in August 2029.

When will Grand Polo Club and Resort be ready?

The first registered completion date is February 2029 and the last is August 2029. Property Finder lists 1 June 2029 for the project as a whole. Emaar has not published its own date.

How far along is construction at Grand Polo Club?

Montura was 11.08% complete on 5 August 2026 and Chevalia Fields 10.03% on 21 July 2026. Most other clusters were between 0.83% and 5.01% at inspections from April to July 2026 (DLD register, via fäm Properties).

Has the Grand Polo Club handover date been delayed?

No change has been recorded. The registered completion dates set when each cluster was filed still stand, and Property Finder still lists 1 June 2029 (accessed 28 Sep 2026).

How much is due at the Grand Polo Club handover?

Under the plan on Property Finder, 20% is due at handover. On a 3 bedroom villa listed from AED 5.7 million, that is AED 1.14 million.

Sources