Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Golden Wood Views 5 handover date?

Updated 11 October 2026 Golden Wood Views 5

Short answer

Golden Wood Views 5 has a registered completion date of 14 October 2026, and the developer's handover target is Q4 2026. The last published Dubai Land Department inspection, on 25 April 2026, recorded the building 89.05% complete. Data Habibi's record shows an earlier delivery date of Q4 2025, so the building is about a year behind its first date, and the October 2026 date depends on the final 11% being certified.

Registered completion date

14 Oct 2026

DLD project register via Continental Club

Latest construction progress

89.05%

DLD inspection, 25 Apr 2026

Developer's handover target

Q4 2026

Continental Club, developer supplied

Earlier delivery date

Q4 2025

Data Habibi

Golden Wood Views 5 handover date: the latest position

Golden Wood Views 5 is registered with the Dubai Land Department (DLD) for completion on 14 October 2026, and the developer’s handover target is Q4 2026. fäm Properties and Propsearch give the same October 2026 date. Prices, sizes and the developer’s record are on the project page: Golden Wood Views 5.

The last published DLD inspection, on 25 April 2026, recorded 89.05% complete. On 10 October 2026, four days before the registered date, a daily tracker of the register still showed 89%, an active status and an unchanged date (Dubai Handover). A building only counts as handed over once the register shows it completed, so the date will either be met by a new inspection near 100% or moved.

Golden Wood Views 5 handover date by building

Golden Wood Views 5 is a single 25-storey building with 161 units (DLD project number 2539).

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Golden Wood Views 5 (161 units) 89.05% (25 Apr 2026) 14 Oct 2026 Q4 2026 (developer via Continental Club); October 2026 (Propsearch, fäm)

The previous inspection, on 27 October 2025, recorded 83.05%, so the building gained six points between October 2025 and April 2026 (DLD project register via Continental Club).

How the Golden Wood Views 5 handover date has changed

Date Event Source
14 Oct 2022 Construction start recorded. Registered completion 14 October 2026 DLD via Continental Club
Not dated Earlier delivery date of Q4 2025 shown Data Habibi
27 Oct 2025 DLD inspection: 83.05% DLD via Continental Club
20 Jan 2026 Broker listing: handover expected by end of Q4 2026 Property Finder
25 Apr 2026 DLD inspection: 89.05% DLD via Continental Club
10 Oct 2026 Register still at 89%, date unchanged at 14 October 2026 Dubai Handover

The Q4 2025 delivery date in Data Habibi’s record was missed. The registered date of 14 October 2026 has stayed the same through 2026, but the pace between the last two inspections was about one point a month. If that pace continued, the building would have been near 95% in October 2026.

What the Golden Wood Views 5 handover date means for payments

The handover date matters most for buyers on post-handover plans, since it starts the clock on the instalments that follow. Data Habibi lists a plan of 10% on booking, 49% during construction, 1% on handover and the remaining 40% after handover. A January 2026 listing on a 64/36 plan showed 52.5% already paid, 11.5% due on handover and 36% at 1% a month for 36 months after handover. Another offered 20% on booking and 80% over five years after handover (Property Finder). If handover moves into 2027, these schedules move with it.

What to check before relying on the Golden Wood Views 5 date

  1. A newer DLD inspection. The 89.05% figure is from April 2026, and the register needs to show the building completed before handover.
  2. The handover notice from Golden Woods, which sets the date the handover payment is due and the post-handover schedule begins.
  3. The completion date and grace period in the SPA for the unit, since the first Q4 2025 date was already missed.

Questions buyers also ask

When will Golden Wood Views 5 be completed?

The DLD register records a completion date of 14 October 2026. The developer gives Q4 2026, and Propsearch estimates October 2026.

Is Golden Wood Views 5 finished?

Not according to the last published DLD inspection, which recorded 89.05% complete on 25 April 2026. A daily tracker of the register still showed 89% and an active status on 10 October 2026 (Dubai Handover).

Has the Golden Wood Views 5 handover date been delayed?

Yes, against the first date. Data Habibi's record gives Q4 2025, while the registered completion date is 14 October 2026 and the developer now says Q4 2026.

What happens to payments at Golden Wood Views 5 handover?

Several plans leave a large balance for after handover. Data Habibi lists 1% on handover and 40% after it, and January 2026 listings offered 36% over 36 months or 80% over five years after handover (Property Finder).

Sources

  1. Propsearch, Golden Wood Views 5 (opens in a new tab)propsearch.ae · updated 16 Aug 2026
  2. Data Habibi, Golden Wood Views 5 (opens in a new tab)datahabibi.ae · accessed 11 Oct 2026
Request a Unit Review