When is the Ghaff Land Residence handover date?
Short answer
Ghaff Land Residence had a registered completion date of 30 June 2026, and that date has passed. The last Dubai Land Department inspection, on 15 July 2026, recorded the building 64.46% complete. No revised date had been filed by October 2026. Finishing in 2026 would need about six times the March to July pace, and Continental Club's straight-line estimate is mid 2028.
Registered completion date
30 Jun 2026 (passed)
DLD project register via Continental Club
Latest construction progress
64.46%
DLD inspection, 15 Jul 2026
Developer's stated date
Q2 2026
Continental Club (developer supplied)
Portal dates now shown
Jul 2026 to Q4 2026
Property Finder, accessed 11 Oct 2026; Bayut listing, 26 Apr 2026
Ghaff Land Residence handover date: the latest position
Ghaff Land Residence was registered with the Dubai Land Department (DLD) for completion on 30 June 2026. That date has passed. At the last DLD inspection, on 15 July 2026, the building was 64.46% complete, and in October 2026 the register still showed the June date. Prices, sizes and the payment plan are on the project page: Ghaff Land Residence.
The developer’s stated date was Q2 2026. Property Finder now shows 30 July 2026, which has also passed, and a Bayut listing from April 2026 gave Q4 2026. None of these later dates is on the DLD register.
Ghaff Land Residence handover date by building
Ghaff Land Residence is one building with 168 units, registered as “Ghaff Land Residence” (DLD project 3307) in Al Hebiah Second, the DLD district for Dubai Studio City.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Ghaff Land Residence (168 units, B + G + 8 + roof) | 64.46% (15 Jul 2026) | 30 Jun 2026 (passed) | Q2 2026 (developer, via Continental Club); 30 Jul 2026 (Property Finder); Q4 2026 (Bayut listing, Apr 2026) |
How the Ghaff Land Residence handover date has changed
| Date | Event | Source |
|---|---|---|
| 15 Jan 2024 | Sales and construction start; completion registered for 30 Jun 2026 | Property Finder; DLD via Continental Club |
| 26 Nov 2024 | First DLD inspection | DLD via Continental Club |
| 1 Jul 2025 | DLD inspection: 39.35% | DLD via Continental Club |
| 11 Nov 2025 | DLD inspection: 52.02% | DLD via Continental Club |
| 5 Mar 2026 | DLD inspection: 60.00% | DLD via Continental Club |
| 26 Apr 2026 | Bayut listing gives Q4 2026 | Bayut |
| 30 Jun 2026 | Registered completion date passes | DLD via Continental Club |
| 15 Jul 2026 | DLD inspection: 64.46% | DLD via Continental Club |
| Oct 2026 | Register unchanged; Property Finder shows 30 Jul 2026 | Continental Club; Property Finder |
Property Finder’s own project description still says Q3 2025, an earlier target that was also missed. The pace has slowed with each inspection: about three points a month from July to November 2025, about two points a month to March 2026 and about one point a month from March to July 2026. Finishing by 31 December 2026 would need about six points a month from August, several times the recent rate. Continental Club’s projection from the past year’s average of 1.54 points a month is 16 June 2028.
What the Ghaff Land Residence handover date means for payments
Property Finder lists 20% at launch, 20% during construction, 10% on handover and 50% after handover. Under that plan 40% has been paid and the other 60% starts only on handover, so the delay pushes back both the handover payment and the post-handover instalments. Continental Club describes a 50/50 plan with half on handover, and a Bayut listing from April 2026 described a 50/50 post-handover plan. Each unit’s SPA sets which applies.
What to check before relying on the Ghaff Land Residence date
- Whether DLD has registered a new completion date. The 30 June 2026 date has passed, and Property Finder’s 30 July 2026 has passed too.
- The completion date and grace period in the SPA, since sales from January 2024 may carry Q3 2025, Q2 2026 or June 2026.
- When post-handover instalments start, as up to 50% of the price is tied to the handover date.
- The next DLD inspection, the first reading since 15 July 2026, to see whether the pace recovers.
Questions buyers also ask
Is Ghaff Land Residence finished?
No. The DLD inspection of 15 July 2026 recorded the building 64.46% complete, two weeks after its registered completion date of 30 June 2026.
When will Ghaff Land Residence be completed?
No new date has been filed with DLD. Property Finder shows 30 July 2026, which has also passed, and a Bayut listing gave Q4 2026. Continental Club's estimate from the past year's pace is 16 June 2028, a calculation rather than a developer date.
Has the Ghaff Land Residence handover date been delayed?
Yes, against the register. The DLD date of 30 June 2026 and the developer's Q2 2026 both passed with the building about two thirds built.
How much is due after handover at Ghaff Land Residence?
Under the plan listed by Property Finder, 10% is due on handover and 50% after it. Continental Club describes 50% on handover instead.