Handover date

When is the Ghaf Woods handover date?

Updated 1 October 2026 Ghaf Woods

Short answer

Ghaf Woods has no single handover date. The first phases, Serra and Cilia, are listed for Q3 and Q4 2027, and Lacina has a registered completion date of 30 December 2027 on the Dubai Land Department (DLD) register. Later phases run to 2029: Distrikt is registered for 30 September 2028 and Capria East and West for May 2029. At the DLD inspections of 17 August 2026, Cilia was 43.82% built, Serra 42.05% and Distrikt 8.39%. Serra and Cilia have no completion date on the register, and portals give some phases different dates from the DLD.

Earliest registered completion date (DLD), Lacina

30 Dec 2027

DLD register, via Mitchells, 23 Sep 2026

Most advanced phase, Cilia

43.82%

DLD site inspection, 17 Aug 2026 (Serra 42.05% the same day)

Portal date for the first phases, Serra and Cilia

Q3 to Q4 2027

Property Finder, accessed 28 Sep 2026

Latest registered completion date, Capria East

15 May 2029

DLD register, via Mitchells, 28 Sep 2026

Ghaf Woods handover date: the latest position

Ghaf Woods does not have one handover date. Majid Al Futtaim registers each phase as a separate project, and the dates run from late 2027 for the first apartment phases to May 2029 for Capria East and West. The furthest along are Cilia, 43.82% built, and Serra, 42.05%, both at DLD inspections on 17 August 2026, and portals list them for Q4 and Q3 2027. More on prices and the community is on the Ghaf Woods page.

The first phases have about a year left to their listed dates with more than half of the work still to do. Serra gained 3.62 points and Cilia 4.28 points between the inspections of 6 July and 17 August 2026. Neither has a completion date on the DLD register yet, so their dates come from portals and the SPA.

Ghaf Woods handover date by phase

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
Serra (535 homes, 10 buildings) 42.05%, 17 Aug 2026 None on register Q3 2027 (Property Finder; Data Habibi)
Cilia (546 homes, 10 buildings) 43.82%, 17 Aug 2026 None on register Q4 2027 (Property Finder)
Lacina (324 homes, 3 buildings) 20.81%, 6 Jul 2026 30 Dec 2027 Q4 2027 (Property Finder)
Distrikt (550 homes) 8.39%, 17 Aug 2026 30 Sep 2028 Q3 2029 (Property Finder)
Capria East (553 homes, 9 buildings) 0.94%, 23 Jun 2026 15 May 2029 Q3 2028 (Data Habibi)
Capria West (714 homes, 12 buildings) 1.23%, 23 Jun 2026 8 May 2029 Q2 2029 (Data Habibi)
Maravelle Residences (96 homes) Not published Not found Q2 2029 (Data Habibi)

Home counts are from the DLD register, except Maravelle, which is from Data Habibi. Property Finder also lists a villa phase, Arista, for Q4 2027; no matching DLD record was found.

How the Ghaf Woods handover date has changed

Date What happened Source
5 Jun 2024 Ghaf Woods launched: over 7,000 homes in eight phases to be released by 2031. Majid Al Futtaim
27 Nov 2024 Lacina, the second phase, reported sold out. Majid Al Futtaim, via Amazing Architecture
Dec 2024 Registered construction starts for Lacina (1 Dec) and Serra and Cilia (27 Dec). DLD register
21 May 2025 Capria launched as phase three. Majid Al Futtaim, via mid-east.info
Aug to Sep 2025 Registered starts for Capria West (15 Aug) and Capria East (15 Sep), both due May 2029. DLD register
8 Jun 2026 AED 2 billion main contract for Capria East, Capria West and Maravelle awarded to ECC. Majid Al Futtaim
17 Aug 2026 Cilia 43.82%, Serra 42.05%, Distrikt 8.39% at DLD inspections. DLD register

Sources disagree on two phases. Data Habibi says Capria East’s original promise was Q4 2028, now Q3 2028, while the DLD register gives 15 May 2029. One broker lists Lacina for Q4 2028, a year after its registered 30 December 2027.

What the Ghaf Woods handover date means for payments

Most phases were sold on 10% at booking, 50% during construction and 40% on handover, including Serra, Distrikt, Capria and Maravelle. Continental Club lists Cilia’s plan as 60% before completion and 40% on handover. On Serra’s AED 1.23 million launch price, the 40% handover payment is AED 492,000, due when that phase completes, which for Serra is listed as Q3 2027.

What to check before relying on the Ghaf Woods date

  1. Which phase and building the unit is in. Dates run from Q3 2027 for Serra to May 2029 for Capria East.
  2. The completion date written into the SPA for Serra or Cilia, since neither has a completion date on the DLD register.
  3. Which date applies for Capria East, where a portal shows Q3 2028 and the DLD register 15 May 2029.
  4. The DLD project number for the phase (for example 3076 for Serra, 3016 for Cilia), to read its own inspection figure through DLD’s project status service.

Questions buyers also ask

When will Ghaf Woods be ready?

Phase by phase. Serra is listed for Q3 2027 and Cilia and Lacina for Q4 2027, with Lacina registered for 30 December 2027. Distrikt is registered for 30 September 2028, Capria West for 8 May 2029 and Capria East for 15 May 2029 (DLD register; Property Finder).

What is the Ghaf Woods completion date?

There is no single completion date. Majid Al Futtaim plans more than 7,000 homes in eight phases released to 2031, and each registered phase has its own date on the DLD register.

Is Ghaf Woods finished?

No phase has been handed over. The most advanced, Cilia and Serra, were 43.82% and 42.05% built at the DLD inspections of 17 August 2026.

When will Serra at Ghaf Woods be ready?

Property Finder and Data Habibi list Q3 2027. The DLD register shows a construction start of 27 December 2024 but no completion date for Serra, and the phase was 42.05% built on 17 August 2026.

Has the Ghaf Woods handover date been delayed?

No delay has been announced by Majid Al Futtaim. Sources disagree on some phases: Data Habibi lists Capria East for Q3 2028, while the DLD register gives 15 May 2029, and one broker lists Lacina for Q4 2028 against a registered 30 December 2027.

Sources

  1. Mitchells Commercial Realty, Serra DLD registry (project 3076) (opens in a new tab)mitchellscommercialrealty.com · registry as at 23 Sep 2026
  2. Mitchells Commercial Realty, Cilia DLD registry (project 3016) (opens in a new tab)mitchellscommercialrealty.com · registry as at 23 Sep 2026
  3. Mitchells Commercial Realty, Lacina DLD registry (project 3336) (opens in a new tab)mitchellscommercialrealty.com · registry as at 23 Sep 2026
  4. Continental Club, Cilia, Ghaf Woods (DLD project 3016) (opens in a new tab)continentalclub.ae · registry updated 26 Sep 2026
  5. Data Habibi, Serra (opens in a new tab)datahabibi.ae · accessed 1 Oct 2026
  6. Data Habibi, Capria East (opens in a new tab)datahabibi.ae · accessed 1 Oct 2026
  7. Data Habibi, Capria West (opens in a new tab)datahabibi.ae · accessed 1 Oct 2026
  8. Data Habibi, Maravelle Residences (opens in a new tab)datahabibi.ae · accessed 1 Oct 2026