Handover date

When is the Gate Royale Residences handover date?

Updated 11 October 2026 Gate Royale Residences

Short answer

Gate Royale Residences has a registered completion date of 2 June 2027, and Baron Development gives Q2 2027. A Dubai Land Department inspection on 3 September 2026 recorded construction 1.74% complete, up from 0% in June 2025. With about nine months left and almost the whole building still to be built, the registered date had not been revised by 25 September 2026, but it is far ahead of the progress on record.

Registered completion date

2 Jun 2027

DLD project register via Continental Club

Latest construction progress

1.74%

DLD inspection, 3 Sep 2026

Developer's stated date

Q2 2027

Baron Development, via Continental Club and brokers

Progress since registered start

1.74 points in 15 months

Start 3 Jun 2025, DLD register

Gate Royale Residences handover date: the latest position

Gate Royale Residences is registered with the Dubai Land Department (DLD) for completion on 2 June 2027, and Baron Development gives Q2 2027. A DLD inspection on 3 September 2026 recorded the building 1.74% complete. Prices, sizes and the payment plan are on the project page: Gate Royale Residences.

The date has not passed and has not been changed. But the building would need to go from 1.74% to 100% in about nine months to meet it, after recording 1.74 points in the fifteen months since the registered construction start.

Gate Royale Residences handover date by building

Gate Royale is one G+2P+9 building, registered as DLD project 3824 in Jebel Ali First, the DLD district for Al Furjan.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Gate Royale Residences (61 units) 1.74% (3 Sep 2026) 2 Jun 2027 Q2 2027 (Baron, via Continental Club and Aigents Realty)

How the Gate Royale Residences handover date has changed

Date Event Source
3 Jun 2025 Construction start on the DLD register; completion set for 2 Jun 2027 DLD via Continental Club
12 Jun 2025 DLD inspection: 0% DLD via Continental Club
28 Jul 2025 Project registered with the DLD DXB Off Plan, citing DLD records
9 to 21 Sep 2025 Launch from AED 949,000 with a Q2 2027 handover Khaleej Times; Baron Development
3 Sep 2026 DLD inspection: 1.74% DLD via Continental Club
25 Sep 2026 Register update still holds 2 Jun 2027 DLD via Continental Club

The date has stayed at Q2 2027 since launch. The register allows two years for the whole build, and the first fifteen months of that period produced 1.74%.

What the Gate Royale Residences handover date means for payments

Under the 50/50 plan, buyers pay 10% on booking and 10% on signing the SPA, then 30% in instalments during construction, and 50% on handover (Tanami Properties). Whether those 30% of instalments follow the calendar or construction stages decides how much is paid while the site is at an early stage. The 50% balance follows the actual handover, so a later completion moves it back. Baron’s launch release mentions a post-handover plan option, which would spread part of that balance after the keys, but no terms are published.

What to check before relying on the Gate Royale Residences date

  1. The completion date and grace period in the SPA. If the contract says 2 June 2027, the grace period sets how long the developer has after that.
  2. The instalment triggers for the 30% construction share. Time based instalments would be paid ahead of visible progress.
  3. Whether Baron applies to extend the registered date. An extension would show on the DLD register.
  4. The next DLD inspection. Only two readings are on file, 0% and 1.74%.

Questions buyers also ask

When will Gate Royale Residences be completed?

The registered completion date is 2 June 2027, and Baron gives Q2 2027. Construction was 1.74% complete on 3 September 2026.

Is Gate Royale Residences on schedule?

The DLD record shows 1.74% progress fifteen months after the registered start of 3 June 2025, with about nine months to the 2 June 2027 completion date. No revised date was on the register at its 25 September 2026 update.

Has the Gate Royale Residences handover date been delayed?

Not officially. Baron still gives Q2 2027 and the register still holds 2 June 2027. The progress on record is far behind what that date would need.

How much is due at handover at Gate Royale Residences?

50% of the price under the 50/50 plan. Baron mentions a post-handover option, but its terms are not published.

Sources