When is the Enre Residence by Imtiaz handover date?
Short answer
Enre Residence by Imtiaz has a registered completion date of 15 August 2028 with the Dubai Land Department, while Imtiaz Developments gives an estimated completion of Q1 2028. A DLD inspection on 28 July 2026 recorded construction 14.63% complete, up from 7.25% in April. The two dates are about five months apart, so the SPA for each unit decides which one applies.
Registered completion date
15 Aug 2028
DLD project register via Continental Club
Latest construction progress
14.63%
DLD inspection, 28 Jul 2026
Developer's stated date
Q1 2028
Imtiaz Developments, accessed 11 Oct 2026
Progress in three months
+7.38 points
7.25% (27 Apr 2026) to 14.63% (28 Jul 2026)
Enre Residence by Imtiaz handover date: the latest position
Enre Residence by Imtiaz is registered with the Dubai Land Department (DLD) for completion on 15 August 2028. Imtiaz Developments gives an earlier estimate of Q1 2028 on its own project page. The last DLD inspection, on 28 July 2026, recorded the building 14.63% complete. Prices, sizes and the payment plan are on the project page: Enre Residence by Imtiaz.
Construction is at an early stage. It started on 15 February 2026, and the register still showed the July reading on 4 October 2026 (Mitchells). Neither date has passed.
Enre Residence by Imtiaz handover date by building
Enre is one building of 10 storeys over a basement, with 170 units, registered as “Enre Residence By Imtiaz” (DLD project 4336) in Madinat Al Mataar, the DLD name for the Dubai South Residential District.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Enre Residence By Imtiaz (170 units) | 14.63% (28 Jul 2026) | 15 Aug 2028 | Q1 2028 (Imtiaz); Q3 2028 (DXB Properties) |
How the Enre Residence by Imtiaz handover date has changed
| Date | Event | Source |
|---|---|---|
| 15 Feb 2026 | Construction start on the DLD register; completion registered for 15 Aug 2028 | DLD via Continental Club |
| 27 Apr 2026 | DLD inspection: 7.25% | DLD via Continental Club |
| 9 Jul 2026 | Broker listing gives Q3 2028 handover | DXB Properties |
| 28 Jul 2026 | DLD inspection: 14.63% | DLD via Continental Club |
| Aug 2026 | Daily snapshots show the 15 Aug 2028 date unchanged | Dubai Handover |
| 4 Oct 2026 | Register still shows 14.63% and 15 Aug 2028 | Mitchells |
| 11 Oct 2026 | Imtiaz still states Q1 2028 and shows 19% on its tracker | Imtiaz Developments |
The developer’s date has not moved, and neither has the registered date. The difference between them has been there since the project was registered: Q1 2028 is the target Imtiaz markets, while 15 August 2028 is the date on file with the DLD.
What the Enre Residence by Imtiaz handover date means for payments
Under the 60/40 plan, 20% is paid on booking and 40% in instalments during construction, so 60% is paid before the keys. The remaining 40% falls due on handover. One broker schedule ties the construction instalments to months after booking, ending 23 months in (Grand Reve Realty). On that schedule, early buyers finish the 60% well before either handover date, and the 40% balance waits for completion. There is no post-handover plan on the developer’s page.
What to check before relying on the Enre Residence by Imtiaz date
- Which of the two dates is in the SPA, and the grace period attached to it. Q1 2028 and 15 August 2028 are about five months apart.
- Whether instalments follow the calendar or construction stages. Time based instalments continue even if the build slows.
- The pace at the next inspection. Reaching 100% by 15 August 2028 from 14.63% in July 2026 needs about 3.5 points a month over the remaining 24 months or so. The April to July 2026 pace was about 2.5 points a month.
Questions buyers also ask
When will Enre Residence by Imtiaz be completed?
The DLD registered completion date is 15 August 2028. Imtiaz Developments gives an estimated completion of Q1 2028 on its project page (accessed 11 October 2026).
What is the Enre Residence completion date on the DLD register?
15 August 2028, under DLD project number 4336. The register lists construction start as 15 February 2026 (DLD project register via Continental Club, updated 25 September 2026).
How far along is Enre Residence by Imtiaz?
14.63% at the DLD inspection of 28 July 2026, up from 7.25% on 27 April 2026. The register still showed 14.63% on 4 October 2026. Imtiaz's own tracker showed 19% when accessed on 11 October 2026, without a date.
Has the Enre Residence handover date been delayed?
No change to the registered date has been recorded. Dubai Handover's daily snapshots showed 15 August 2028 throughout August 2026, and the date had not passed. The gap is between the developer's Q1 2028 and the register's August 2028.