Handover date

When is the Enchante by Grid handover date?

Updated 11 October 2026 Enchante by Grid

Short answer

Enchante by Grid has a registered completion date of 15 December 2028, and GRID gives Q4 2028. The only DLD inspection on record, on 17 April 2026, recorded 0%, before construction was registered as starting on 25 May 2026. GRID broke ground in July 2026, so the date rests on a build that has only just begun.

Registered completion date (DLD)

15 Dec 2028

DLD project register via Continental Club

Latest construction progress

0%

DLD inspection, 17 Apr 2026

Developer's stated date

Q4 2028

GRID via Zawya, 27 Jul 2026

Date given at launch

Dec 2028

Arabian Business, 19 May 2026

Enchante by Grid handover date: the latest position

The DLD project register holds a registered completion date of 15 December 2028 for Enchante by Grid, listed there as Enchante By Grid. GRID’s own target is the fourth quarter of 2028, and its project website shows December 2028. Prices, sizes and the payment plan are on the Enchante by Grid page.

Construction has only just begun. The DLD inspection of 17 April 2026 recorded 0%, the register shows construction starting on 25 May 2026, and GRID announced its groundbreaking on 27 July 2026. No later inspection has been published (register updated 8 October 2026).

Enchante by Grid handover date by building

The DLD register lists the project as one entry, DLD project 4460, with 286 units. GRID describes four connected towers, and all of them share the one registered date.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Enchante by Grid (four towers, 286 units) 0%, 17 Apr 2026 15 Dec 2028 Q4 2028 (GRID, Jul 2026); Dec 2028 (Property Finder)

How the Enchante by Grid handover date has changed

Date What happened Source
17 Apr 2026 DLD inspection records 0% DLD register
7 May 2026 Launch event; handover given as December 2028; nearly 60% sold Arabian Business
25 May 2026 Construction start registered DLD register
27 Jul 2026 Groundbreaking; handover Q4 2028; more than 60% sold Zawya
Oct 2026 Website timeline: top-out October 2027, handover December 2028 GRID website

The date has not changed since launch. With no inspection after groundbreaking, there is not yet a pace to compare against the register. The full build must fit into about 31 months between the May 2026 start and 15 December 2028.

What the Enchante by Grid handover date means for payments

The published plan is 20% on booking, 20% during construction and 60% on handover (Continental Club; Inside Realty). Property Finder and OPR show 10/30/60 in their headline figures. Under either split, 60% of the price falls due on handover. On a studio at the DLD median of AED 595,000, that is AED 357,000. On a 2 bedroom at the median of AED 1,295,800, it is about AED 777,500 (Continental Club, register updated 7 October 2026). There is no post-handover plan in the published schedules, so a later handover moves the largest payment later.

What to check before relying on the Enchante by Grid date

  1. The completion date and grace period in the SPA, compared with 15 December 2028 in the register.
  2. The first DLD inspections after groundbreaking, which will give the first real measure of progress.
  3. Whether the tower for the unit has its own schedule. The register shows one entry, but GRID describes four towers.
  4. The 60% handover payment, and whether a mortgage or cash will cover it in late 2028.

Questions buyers also ask

When will Enchante by Grid be completed?

The registered completion date in the DLD project register is 15 December 2028. GRID gives the fourth quarter of 2028 (Zawya, 27 Jul 2026).

Has construction started at Enchante by Grid?

Yes. The DLD register records a construction start of 25 May 2026, and GRID announced the groundbreaking on 27 July 2026. The only DLD inspection published so far, on 17 April 2026, recorded 0%.

Has the Enchante by Grid handover date been delayed?

No. GRID gave December 2028 at launch in May 2026, repeated Q4 2028 at the groundbreaking in July, and the register holds 15 December 2028.

When will Enchante by Grid top out?

GRID's project website lists a top-out in October 2027, followed by an expected handover in December 2028. It marks these dates as tentative (accessed 11 Oct 2026).

Sources