When is the Empire Gardens handover date?
Short answer
The Empire Gardens handover date is Q4 2028, and the DLD register lists a completion date of 31 December 2028. The DLD recorded construction at 0.04% complete on 1 July 2026. The date has held since launch in October 2025, but work only began in April 2026, so the pace over 2027 will decide whether it is met.
Registered completion date (DLD)
31 Dec 2028
DLD register via Continental Club
Latest construction progress
0.04%
DLD inspection, 1 Jul 2026
Developer's stated date
Q4 2028
Empire Developments via Ezre, accessed 11 Oct 2026
Date change since launch
None recorded
Q4 2028 at launch, Oct 2025
Empire Gardens handover date: the latest position
Empire Gardens is due for handover in Q4 2028. Empire Developments publishes that quarter, and the Dubai Land Department (DLD) register lists a completion date of 31 December 2028, the last day of it. See the full project guide for Empire Gardens.
The building is at the very start of construction. The DLD register records the start as 25 April 2026, and the inspection on 1 July 2026 put progress at 0.04%. The previous inspection, on 12 December 2025, recorded 0.00%. Empire Developments launched the project in October 2025, so sales ran for about six months before registered work began.
Empire Gardens handover date by building
Empire Gardens is one 13 floor residential building, registered as a single project.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Empire Gardens (221 units) | 0.04% (1 Jul 2026) | 31 Dec 2028 | Q4 2028 (Empire Developments via Ezre; Data Habibi) |
The register entry is DLD project 4246, with its escrow account at Emirates NBD. Its 221 units are 101 studios, 100 one bedroom, 12 two bedroom and 8 three bedroom homes. Data Habibi counts 224 units. By September 2026, 105 sales had been registered against the project, so most buyers are already tied to the same completion date.
How the Empire Gardens handover date has changed
| Date | What was published | Source |
|---|---|---|
| Oct 2025 | Launch; handover given as Q4 2028 | Binayah, 20 Oct 2025; Oliva |
| 12 Dec 2025 | DLD inspection: 0.00% | DLD register via Continental Club |
| 25 Apr 2026 | Registered construction start | DLD register via Continental Club |
| 1 Jul 2026 | DLD inspection: 0.04%; completion date 31 December 2028 | DLD register via Continental Club |
| 11 Oct 2026 | Developer still gives Q4 2028 | Ezre |
The handover quarter has not moved. Binayah’s launch page gives Q4 2028 in its description and Q3 2028 in its summary box, the only source to mention an earlier quarter.
What the Empire Gardens handover date means for payments
The plan is 20% on booking, 36% during construction and 44% after handover (Ezre and Binayah). Data Habibi splits it as 35% during construction, 1% at handover and 44% over 44 months after handover. The handover date therefore sets two things: when the keys are released and when the 44-month post-handover schedule begins. A later handover pushes the whole post-handover schedule back with it.
What to check before relying on the Empire Gardens date
- The completion date and grace period in the SPA, compared with the registered 31 December 2028.
- Whether post-handover instalments start at the actual handover date or at a fixed calendar date in the SPA.
- DLD progress for project 4246 in 2027. At 0.04% in July 2026, almost the whole build has to fit into the roughly 27 months left to the registered date.
Questions buyers also ask
When will Empire Gardens be ready?
Empire Developments gives Q4 2028, and the DLD register lists a completion date of 31 December 2028.
What is the Empire Gardens completion date?
31 December 2028 on the DLD register for project 4246 (DLD register via Continental Club, as at 8 Oct 2026).
Has the Empire Gardens handover date been delayed?
No change has been recorded. Launch listings in October 2025 gave Q4 2028, and the developer and the register still do. One broker page also mentions Q3 2028.
When does the post-handover plan at Empire Gardens start?
After handover. Buyers pay about 56% before receiving the keys and 44% afterwards, which Data Habibi describes as spread over 44 months.